Levels of uncertainty

From apppm
(Difference between revisions)
Jump to: navigation, search
(Bibliography)
Line 10: Line 10:
 
== Introduction ==
 
== Introduction ==
  
- Consequences of poor uncertainty management
+
Uncertainty is a fact of life that we all must contend with. From personal decisions to corporate strategies, uncertainty is an ever-present challenge that can affect the outcomes of our choices. When it comes to managing uncertainty, there are various levels of uncertainty that managers can use to identify the threats, that lie up ahead. Poor uncertainty management at any of these levels can lead to consequences that range from minor inconveniences to severe financial losses or even personal harm. In this wiki-article, we will explore the different levels of uncertainty, as well as strategies for effectively managing uncertainty at each level.
- Different definition in different fields and different take-aways. Therefore, no right or wrong, but a list of useful tools to most (or something like that)
+
 
 +
The right indentation of uncertainty levels has many different roots within different fields. Therefore, there is no “one size fits all” way to assess uncertainty but uncertainty management must be seen as a collection of methods that can be applied to different situations (Riesch, 2012). Levels of uncertainty can, thus, be described based on knowledge, severity, or the source of uncertainty. When each is applicable and how to mitigate the uncertainty, will be described further in this article.
  
 
== Nature of uncertainty ==
 
== Nature of uncertainty ==
  
- Risk vs. uncertainty
+
'''Key challenges with managing uncertainty'''
 +
When uncertainty is mismanaged project performance is at great risk. One of the most common mistakes, when it comes to uncertainty, is to underestimate or ignore what cannot be measured. This is most often done either because of a lack of awareness or because of an optimism bias in the project. In the way that unmeasurable challenges probably not are that big a deal, and through the idea that “Of course this team can overcome any obstacle”. Lastly, uncertainties can be downplayed and used as a deliberate way of overselling projects (Geraldi et al., 2017).
  
-   Risk refers to events rather than general sources of uncertainty (Petit, 2012)
+
'''Uncertainty management vs. risk management'''
 +
When managing uncertainty, there is an important distinction to be made between risk and uncertainty. Risk refers to specific events rather than general sources of uncertainty (Petit, 2012) and is thereby measurable. Efforts to do this is included in general project risk management (Wiki: PRM). Examples of PRM are easy to grasp as most have tried to estimate the odds that some process fails and planned what to do in the case, that it does. Uncertainty management must also consider unforeseeable events and non-quantifiable uncertainties. And as you may think about it, what really is certain? Not much is. Uncertainty management is therefore more about being adaptive and quick on your feet, as too much rigidity in project planning can cause fragility in the project in the face of unforeseen happenings (Geraldi et al., 2017).
  
-   Un-measurable – as opposed to risk (Link PRM or similar on wiki)
+
Uncertainty management also diverts from risk management by dealing with more than just disruptions to the project (or possible disruptions to the project). As uncertainty contains a big personal and emotional aspect as well. This is to say, that stakeholder engagement in the project can vary on the specific stakeholder’s perception of the risk (Geraldi et al., 2017). Managing expectations and minimizing threats in an unforeseeable landscape is exactly what levels of uncertainty is for.
  
- Emotional aspect of uncertainty – show difficulty of management
 
  
== Uncertainty based on knowledge (2 levels) (van Asselt & Rotmans, 2002) ==
+
== Why are we uncertain?/Uncertainty based on knowledge (2 levels) ==
- Epistemic
+
- Aleatoric
+
  
== Uncertainty based on severity (4 levels) (Meyer et al., 2002) ==
+
One way of creating levels of uncertainty is to consider the knowledgebase for the uncertainty. This reveals two inherent levels of uncertainty, as some concerns can be diminished by doing more research, and some are caused by internal randomness of the phenomena (Wiki: Epistemic vs. aleatory uncertainty)
  
- Four types of uncertainty:
+
'''Epistemic uncertainty'''
 +
Epistemic uncertainty refers to uncertainty arising from a lack of knowledge or information about a particular system, process, or event. It is a type of uncertainty that can be reduced through gathering more data, improving models or theories, and enhancing our understanding of the underlying mechanisms (Kiureghian & Ditlevsen, 2009).
  
- Variation:
+
Effective management of epistemic uncertainty involves identifying and addressing knowledge gaps, building robust models and decision-making frameworks, and continuously monitoring and updating assumptions as new information becomes available (van Asselt & Rotmans, 2002).
Activities such as worker sickness, that push the critical path of a project. Often combined small influences
+
'''
 +
Aleatoric uncertainty'''
 +
Aleatory uncertainty refers to inherent randomness or variability in a particular system, process, or event that cannot be reduced or eliminated through additional information or analysis. This type of uncertainty is often associated with natural phenomena, such as weather patterns, seismic activity, or the behavior of complex systems. A simple dice is also a perfect example of aleatory uncertainty, in which the internal randomness of the outcome cannot be altered, even though the odds are known (Kiureghian & Ditlevsen, 2009).
  
- Foreseen uncertainty:
+
Effective management of aleatory uncertainty involves understanding and quantifying the range of potential outcomes, building robust systems that can withstand a range of potential scenarios, and implementing appropriate risk management strategies to minimize the impact of adverse events (van Asselt & Rotmans, 2002).
Identifiable influences that may or may not occur. Very risk management appropriate
+
  
- Unforeseen uncertainty:
 
Basically unknown-unknowns
 
  
- Chaos:
+
== How critical is the uncertainty?/Uncertainty based on severity (4 levels) ==
When the outcome of a project ends up being so far from the initial project scope that it has little to no application for it. This can mean project failure, or a completely unforeseen secondary benefit.
+
  
- Briefly: four types of uncertainty (Millett, 2002)
+
Authors such as Meyer et al. (2002) propose a different framework for assessing levels of uncertainty. They propose four levels based on the severity of the situation (Meyer et al., 2002).
  
- 1: Near-term and predictable future
+
'''Variation'''
 +
Activities such as worker sickness, that push the critical path of a project (Wiki: CPM) and similar occurrences can be seen as variation in a project (Meyer et al., 2002). Events on this level can further be compared to what Millet (2002) describes as uncertainty within a near-term future (Millett, 2002).
  
- 2: A limited number of possible outcomes can be assessed
+
To manage variation, including buffers in a Critical Path strategy to catch up on delays, can be recommended.
  
- 3: A range of possible outcomes can be assessed
+
'''Foreseen uncertainty'''
 +
Meyer’s take on foreseen uncertainty is very similar to what have previously been described as risk management in this article. Foreseen uncertainties are identifiable influences that may or may not occur.
  
- 4: Highly uncertain
+
To manage foreseen uncertainty, the tools in Project Risk Management can be applied as well as doing contingency plans for the project.
  
- Like Meyer, but less tangible. (Mentioned as perspective and as warrant)
+
'''Unforeseen uncertainty'''
 +
This level of uncertainty can also be described as "unknown unknowns," as famously stated by former US Secretary of Defense, Donald Rumsfeld. Unknown inadequacies refer to risks that are not accounted for in any plans or strategies because they are completely unexpected and are near-impossible to plan against.
  
- Briefly Uncertainty and environmental learning (Wynne, 1992)
+
To manage unforeseen uncertainty, an organisation should be both agile and continuously learning (Meyer et al., 2002). Robustness of projects and companies can also be found in their partnerships and with diversity in the project portfolio.
  
- Risk: Know the odds
+
'''Chaos'''
 +
The final level in Meyer’s ontology is managing chaos. In chaos, the outcome of a project ends up being so far from the initial project scope that it has little to no application for it. This can mean project failure, or a completely unforeseen secondary benefit. An example being the invention and market introduction of Viagra, which was firstly intended as heart (or kidney) medication (Meyer et al., 2002).
  
- Uncertainty: Know the parameters
+
Managing chaos can seem like a paradox, but to do it, nonetheless, requires a high degree of autonomy for project managers and an iterative approach to the project work. R&D are often prone to work in chaotic environments and rapid prototyping is an effective way to do this. To allow working in chaos, companies must, however, also be ruthless in killing projects when the chances for success become too small.
  
- Ignorance: Unknown unknowns
 
  
- Indeterminacy: Causal chains or networks open
+
== What are we uncertain about?/Uncertainty based on source (5 levels)  ==
  
- Wynne views the levels as “one on the other”, rather than “one or the other”, so that they overlap and expand
+
Uncertainty can be classified based on its source, and there are five levels of uncertainty according to Riesch (2013). The source of uncertainty can also be formulated as the answer to the question: “What are we uncertain about?”.
  
== Uncertainty based on source (5 levels) ((Riesch, 2013)) ==
+
'''Level 1: Uncertainty of the outcome'''
 +
The first level is the uncertainty of the outcome, which is often expressed as a measurable probability. This means that we know what we have done, we know the model, and we know the likelihood of a particular outcome occurring (Riesch, 2013). The uncertainty of the outcome is limited to an aleatoric uncertainty in Riesch’s model, as all is known, and the epistemic uncertainties thereby have been removed. An example here is again the rolling of a dice.
  
1. Uncertainty of the outcome:
+
Managing the uncertainty of outcome in this sense, should refer to business decisions: Is the risk worth it based on cost, time, quality, etc.?
a. Measurable probability (E.g. ”We know what we have done, we know the model, and we know that there is X% chance of this outcome”)
+
  
2. Uncertainty of the parameters:
+
'''Level 2: Uncertainty of the parameters'''
a. Can be a lack of information. Once information is retrieved, we can predict outcome with probability, P
+
The second level is the uncertainty of the parameters, which can result from a lack of information. The idea is, to say “once we retrieve the necessary information, we can predict the outcome with a probability, P”. This level is thus, a sort of epistemic uncertainty that refers to the external factors to the project.
  
3. Uncertainty about the model itself:
+
'''Level 3: Uncertainty about the model itself'''
a. Different risk assessment models exist, but it can be interpreted as trust in the processes themselves. Often the client of the risk assessment will transfer how much they trust the experts delivering the assessment into how much they trust the model
+
The third level is uncertainty about the model itself. An example of this can be the trust that the client has in the experts who are delivering the risk assessment. Different risk assessment models exist, but the client's level of trust in the process can determine how much they trust the model. This is uncertainty of the internal factors in the organisation and of the project work. This uncertainty is, thus, unquantifiable and relates to the human and emotional aspects of managing uncertainty.
  
4. Uncertainty about acknowledged inadequacies and implicitly made assumptions:
+
'''Level 4: Uncertainty about acknowledged inadequacies and implicitly made assumptions'''
a. Pitfalls (ignoring what we cannot measure, optimism bias)
+
The fourth level is uncertainty about acknowledged inadequacies and implicitly made assumptions. These assumptions are often based on past experiences or established conventions and can lead to blind spots in our risk assessments. For example, a company might assume that a certain market trend will continue, without considering the possibility of disruptive innovations or changes in consumer behavior. [Source]
  
5. Unknown inadequacies:
+
One example of acknowledged inadequacies is the challenge of dealing with uncertainties associated with extreme events, also known as tail risk. These events are rare and have a low probability of occurrence but can have a significant impact on outcomes. Many risk models are not designed to handle tail risk effectively, and as a result, they may underestimate the potential impact of such events. [Source]
a. Unknown unknowns (Rumsfeld)
+
  
== Discussion on the merits of each ontology ==
+
This level of uncertainty is complex to handle and relates heavily to the human and emotional aspect of uncertainty management. Further, human biases can cause that these uncertainties are overlooked until execution has begone. So far, the levels of uncertainty proposed by Riesch (2013), has referred to an analysis stage, in which a decision is yet to be made. Now, they appear as unpleasant surprises during project execution.
• Levels based on severity or area of uncertainty
+
  
• When to use which type of categorisation
+
'''Level 5: Unknown inadequacies'''
 +
The fifth level of uncertainty in Riesch’s (2013) framework also refers to the ‘unknown unknowns’ in Rumsfeld’s terminology. Like Meyer et al. (2002), Riesch (2013) describes this level of uncertainty as the most difficult to manage. Because we cannot predict what we do not know, we must focus on building resilient systems that can withstand a range of potential scenarios. This involves designing systems that are flexible and adaptable, with redundancies and fallback options built-in. It also means fostering a culture of innovation and continuous learning, where new ideas and approaches can be tested and evaluated (Riesch, 2013).
  
• Project, program, and portfolio management perspectives
 
  
== Strategies for mitigation ==
+
== Discussion on the merits of each ontology ==
- Address mode of action for each level
+
Each of the proposed frameworks clearly has merit and addresses different types of uncertainty. As the ontologies overlap, they can expand on the understanding of each other as well. The two inherent levels of epistemic vs. aleatory uncertainty are, for example, present verbatim in levels one, two, and three of Riesch’s ontology, and similarly are Meyer and Riesch not mutually exclusive. Thus, uncertainty can refer to the external parameters (Riesch Level 2) and be caused by variation in the project (Meyer level 1). This view of combining the frameworks are also present within the ontologies themselves. Riesch and fellow uncertainty researcher Wynne [source] both argue, that the levels can be applied ‘on top of each other’, rather than be assessed in a stepwise approach.
 
+
- Rapid Knowledge Development (RKD) for Project Managers (Maybe not so great after all)  (Kerzner & Saladis, 2009)
+
 
+
- Uncertainty-based management (Meyer et al., 2002)
+
 
+
- Managing variation:
+
- Critical path method (CPM)
+
- Buffers
+
- Comes with cases
+
 
+
- Managing foreseen uncertainty:
+
- Risk management (PRM)
+
- Contingency plan
+
 
+
- Managing unforeseen uncertainty:
+
- “To deal with unforeseen uncertainty, project managers must move from troubleshooting to opportunistic orchestrating and networking”
+
- Comes with many cases
+
 
+
- Managing chaos:
+
- The need for flexibility and iteration obliges project managers to cope with constant change.
+
- team managers must have a high degree of autonomy.
+
- Rapid prototyping is one way to support such an experimental approach
+
- Companies must be ruthless in cutting projects when the chance of success becomes too small
+
  
 
== Examples ==
 
== Examples ==
Line 137: Line 114:
  
 
Geraldi, J., Thuesen, C., Oehmen, J., & Stingl, V. (2017). Doing Projects. A Nordic Flavour to Managing Projects: DS-handbook 185:2017. Dansk Standard.
 
Geraldi, J., Thuesen, C., Oehmen, J., & Stingl, V. (2017). Doing Projects. A Nordic Flavour to Managing Projects: DS-handbook 185:2017. Dansk Standard.
 +
 +
Kiureghian, A. Der, & Ditlevsen, O. (2009). Aleatory or epistemic? Does it matter? Structural Safety, 31(2), 105–112. https://doi.org/https://doi.org/10.1016/j.strusafe.2008.06.020
  
 
Kerzner, H., & Saladis, F. P. (2009). Bringing the PMBOK guide to life : a companion for the practicing project manager. In Bringing the Pmbok® Guide To Life: a Companion for the Practicing Project Manager. Wiley.
 
Kerzner, H., & Saladis, F. P. (2009). Bringing the PMBOK guide to life : a companion for the practicing project manager. In Bringing the Pmbok® Guide To Life: a Companion for the Practicing Project Manager. Wiley.

Revision as of 18:35, 10 April 2023

Contents

Abstract

Uncertainty is a common challenge in project, program, and portfolio management. It can arise from a variety of sources, including unforeseen risks and challenges in project scope, budget, or timeline. In the understanding by Knight that uncertainty diverts from risk, by being non-quantifiable, the level of uncertainty can be used by managers to prepare and adapt to the unforeseen events.

This article will explore various parameters for classifying levels of uncertainty, such as knowledge, severity, and source, and provide guidance on when to appropriately utilize each. Additionally, effective strategies for managing uncertainty at different levels in project, program, and portfolio management will be provided.

The article concludes by highlighting the importance of adopting a systematic approach to uncertainty management and will provide valuable insights for project-, program-, and portfolio managers, as well as anyone involved in the planning and delivery of projects, programs, and portfolios.

Introduction

Uncertainty is a fact of life that we all must contend with. From personal decisions to corporate strategies, uncertainty is an ever-present challenge that can affect the outcomes of our choices. When it comes to managing uncertainty, there are various levels of uncertainty that managers can use to identify the threats, that lie up ahead. Poor uncertainty management at any of these levels can lead to consequences that range from minor inconveniences to severe financial losses or even personal harm. In this wiki-article, we will explore the different levels of uncertainty, as well as strategies for effectively managing uncertainty at each level.

The right indentation of uncertainty levels has many different roots within different fields. Therefore, there is no “one size fits all” way to assess uncertainty but uncertainty management must be seen as a collection of methods that can be applied to different situations (Riesch, 2012). Levels of uncertainty can, thus, be described based on knowledge, severity, or the source of uncertainty. When each is applicable and how to mitigate the uncertainty, will be described further in this article.

Nature of uncertainty

Key challenges with managing uncertainty When uncertainty is mismanaged project performance is at great risk. One of the most common mistakes, when it comes to uncertainty, is to underestimate or ignore what cannot be measured. This is most often done either because of a lack of awareness or because of an optimism bias in the project. In the way that unmeasurable challenges probably not are that big a deal, and through the idea that “Of course this team can overcome any obstacle”. Lastly, uncertainties can be downplayed and used as a deliberate way of overselling projects (Geraldi et al., 2017).

Uncertainty management vs. risk management When managing uncertainty, there is an important distinction to be made between risk and uncertainty. Risk refers to specific events rather than general sources of uncertainty (Petit, 2012) and is thereby measurable. Efforts to do this is included in general project risk management (Wiki: PRM). Examples of PRM are easy to grasp as most have tried to estimate the odds that some process fails and planned what to do in the case, that it does. Uncertainty management must also consider unforeseeable events and non-quantifiable uncertainties. And as you may think about it, what really is certain? Not much is. Uncertainty management is therefore more about being adaptive and quick on your feet, as too much rigidity in project planning can cause fragility in the project in the face of unforeseen happenings (Geraldi et al., 2017).

Uncertainty management also diverts from risk management by dealing with more than just disruptions to the project (or possible disruptions to the project). As uncertainty contains a big personal and emotional aspect as well. This is to say, that stakeholder engagement in the project can vary on the specific stakeholder’s perception of the risk (Geraldi et al., 2017). Managing expectations and minimizing threats in an unforeseeable landscape is exactly what levels of uncertainty is for.


Why are we uncertain?/Uncertainty based on knowledge (2 levels)

One way of creating levels of uncertainty is to consider the knowledgebase for the uncertainty. This reveals two inherent levels of uncertainty, as some concerns can be diminished by doing more research, and some are caused by internal randomness of the phenomena (Wiki: Epistemic vs. aleatory uncertainty)

Epistemic uncertainty Epistemic uncertainty refers to uncertainty arising from a lack of knowledge or information about a particular system, process, or event. It is a type of uncertainty that can be reduced through gathering more data, improving models or theories, and enhancing our understanding of the underlying mechanisms (Kiureghian & Ditlevsen, 2009).

Effective management of epistemic uncertainty involves identifying and addressing knowledge gaps, building robust models and decision-making frameworks, and continuously monitoring and updating assumptions as new information becomes available (van Asselt & Rotmans, 2002). Aleatoric uncertainty Aleatory uncertainty refers to inherent randomness or variability in a particular system, process, or event that cannot be reduced or eliminated through additional information or analysis. This type of uncertainty is often associated with natural phenomena, such as weather patterns, seismic activity, or the behavior of complex systems. A simple dice is also a perfect example of aleatory uncertainty, in which the internal randomness of the outcome cannot be altered, even though the odds are known (Kiureghian & Ditlevsen, 2009).

Effective management of aleatory uncertainty involves understanding and quantifying the range of potential outcomes, building robust systems that can withstand a range of potential scenarios, and implementing appropriate risk management strategies to minimize the impact of adverse events (van Asselt & Rotmans, 2002).


How critical is the uncertainty?/Uncertainty based on severity (4 levels)

Authors such as Meyer et al. (2002) propose a different framework for assessing levels of uncertainty. They propose four levels based on the severity of the situation (Meyer et al., 2002).

Variation Activities such as worker sickness, that push the critical path of a project (Wiki: CPM) and similar occurrences can be seen as variation in a project (Meyer et al., 2002). Events on this level can further be compared to what Millet (2002) describes as uncertainty within a near-term future (Millett, 2002).

To manage variation, including buffers in a Critical Path strategy to catch up on delays, can be recommended.

Foreseen uncertainty Meyer’s take on foreseen uncertainty is very similar to what have previously been described as risk management in this article. Foreseen uncertainties are identifiable influences that may or may not occur.

To manage foreseen uncertainty, the tools in Project Risk Management can be applied as well as doing contingency plans for the project.

Unforeseen uncertainty This level of uncertainty can also be described as "unknown unknowns," as famously stated by former US Secretary of Defense, Donald Rumsfeld. Unknown inadequacies refer to risks that are not accounted for in any plans or strategies because they are completely unexpected and are near-impossible to plan against.

To manage unforeseen uncertainty, an organisation should be both agile and continuously learning (Meyer et al., 2002). Robustness of projects and companies can also be found in their partnerships and with diversity in the project portfolio.

Chaos The final level in Meyer’s ontology is managing chaos. In chaos, the outcome of a project ends up being so far from the initial project scope that it has little to no application for it. This can mean project failure, or a completely unforeseen secondary benefit. An example being the invention and market introduction of Viagra, which was firstly intended as heart (or kidney) medication (Meyer et al., 2002).

Managing chaos can seem like a paradox, but to do it, nonetheless, requires a high degree of autonomy for project managers and an iterative approach to the project work. R&D are often prone to work in chaotic environments and rapid prototyping is an effective way to do this. To allow working in chaos, companies must, however, also be ruthless in killing projects when the chances for success become too small.


What are we uncertain about?/Uncertainty based on source (5 levels)

Uncertainty can be classified based on its source, and there are five levels of uncertainty according to Riesch (2013). The source of uncertainty can also be formulated as the answer to the question: “What are we uncertain about?”.

Level 1: Uncertainty of the outcome The first level is the uncertainty of the outcome, which is often expressed as a measurable probability. This means that we know what we have done, we know the model, and we know the likelihood of a particular outcome occurring (Riesch, 2013). The uncertainty of the outcome is limited to an aleatoric uncertainty in Riesch’s model, as all is known, and the epistemic uncertainties thereby have been removed. An example here is again the rolling of a dice.

Managing the uncertainty of outcome in this sense, should refer to business decisions: Is the risk worth it based on cost, time, quality, etc.?

Level 2: Uncertainty of the parameters The second level is the uncertainty of the parameters, which can result from a lack of information. The idea is, to say “once we retrieve the necessary information, we can predict the outcome with a probability, P”. This level is thus, a sort of epistemic uncertainty that refers to the external factors to the project.

Level 3: Uncertainty about the model itself The third level is uncertainty about the model itself. An example of this can be the trust that the client has in the experts who are delivering the risk assessment. Different risk assessment models exist, but the client's level of trust in the process can determine how much they trust the model. This is uncertainty of the internal factors in the organisation and of the project work. This uncertainty is, thus, unquantifiable and relates to the human and emotional aspects of managing uncertainty.

Level 4: Uncertainty about acknowledged inadequacies and implicitly made assumptions The fourth level is uncertainty about acknowledged inadequacies and implicitly made assumptions. These assumptions are often based on past experiences or established conventions and can lead to blind spots in our risk assessments. For example, a company might assume that a certain market trend will continue, without considering the possibility of disruptive innovations or changes in consumer behavior. [Source]

One example of acknowledged inadequacies is the challenge of dealing with uncertainties associated with extreme events, also known as tail risk. These events are rare and have a low probability of occurrence but can have a significant impact on outcomes. Many risk models are not designed to handle tail risk effectively, and as a result, they may underestimate the potential impact of such events. [Source]

This level of uncertainty is complex to handle and relates heavily to the human and emotional aspect of uncertainty management. Further, human biases can cause that these uncertainties are overlooked until execution has begone. So far, the levels of uncertainty proposed by Riesch (2013), has referred to an analysis stage, in which a decision is yet to be made. Now, they appear as unpleasant surprises during project execution.

Level 5: Unknown inadequacies The fifth level of uncertainty in Riesch’s (2013) framework also refers to the ‘unknown unknowns’ in Rumsfeld’s terminology. Like Meyer et al. (2002), Riesch (2013) describes this level of uncertainty as the most difficult to manage. Because we cannot predict what we do not know, we must focus on building resilient systems that can withstand a range of potential scenarios. This involves designing systems that are flexible and adaptable, with redundancies and fallback options built-in. It also means fostering a culture of innovation and continuous learning, where new ideas and approaches can be tested and evaluated (Riesch, 2013).


Discussion on the merits of each ontology

Each of the proposed frameworks clearly has merit and addresses different types of uncertainty. As the ontologies overlap, they can expand on the understanding of each other as well. The two inherent levels of epistemic vs. aleatory uncertainty are, for example, present verbatim in levels one, two, and three of Riesch’s ontology, and similarly are Meyer and Riesch not mutually exclusive. Thus, uncertainty can refer to the external parameters (Riesch Level 2) and be caused by variation in the project (Meyer level 1). This view of combining the frameworks are also present within the ontologies themselves. Riesch and fellow uncertainty researcher Wynne [source] both argue, that the levels can be applied ‘on top of each other’, rather than be assessed in a stepwise approach.

Examples

- The lottery (Hauke Riesch) - Climate change (Hauke Riesch) - (More to come)

Limitations

- Of this article - Of the uncertainty theory used

Further reading

- Other paradigms - Other wiki-articles

Bibliography

Geraldi, J., Thuesen, C., Oehmen, J., & Stingl, V. (2017). Doing Projects. A Nordic Flavour to Managing Projects: DS-handbook 185:2017. Dansk Standard.

Kiureghian, A. Der, & Ditlevsen, O. (2009). Aleatory or epistemic? Does it matter? Structural Safety, 31(2), 105–112. https://doi.org/https://doi.org/10.1016/j.strusafe.2008.06.020

Kerzner, H., & Saladis, F. P. (2009). Bringing the PMBOK guide to life : a companion for the practicing project manager. In Bringing the Pmbok® Guide To Life: a Companion for the Practicing Project Manager. Wiley.

Meyer, A. de, Loch, C. H., & Meyer, D. (2002). Managing project uncertainty: From variation to chaos Managing project uncertainty. MIT Sloan Management Review, 43(2), 60–67. https://ink.library.smu.edu.sg/lkcsb_research

Millett, S. M. (2002). Four levels of uncertainty. Strategy and Leadership, 30(2). https://doi.org/10.1108/sl.2002.26130bae.001

Petit, Y. (2012). Project portfolios in dynamic environments: Organizing for uncertainty. International Journal of Project Management, 30(5), 539–553. https://doi.org/https://doi.org/10.1016/j.ijproman.2011.11.007

Riesch, H. (2013). Levels of Uncertainty. In Springerbriefs in Philosophy (pp. 29–56). Springer Science and Business Media B.V. https://doi.org/10.1007/978-94-007-5455-3_2

van Asselt, M. B. A., & Rotmans, J. (2002). Uncertainty in Integrated Assessment Modelling. Climatic Change, 54(1), 75–105. https://doi.org/10.1023/A:1015783803445

Wynne, B. (1992). Uncertainty and environmental learning: Reconceiving science and policy in the preventive paradigm. Global Environmental Change, 2(2), 111–127. https://doi.org/https://doi.org/10.1016/0959-3780(92)90017-2

Personal tools
Namespaces

Variants
Actions
Navigation
Toolbox