Meeting strategies

From apppm
(Difference between revisions)
Jump to: navigation, search
(Too many meetings fail)
 
(80 intermediate revisions by one user not shown)
Line 1: Line 1:
 +
''Developed by Julie Laursen''
 +
 +
 
== Abstract ==
 
== Abstract ==
  
A meeting is a formal or informal event where individuals meet either face-to-face or virtually (by the use of audio or video conference tools). In projects, groups of people need to discuss, align, inform etc., hence there exist numerous purposes and needs for meetings. They are essential for collaboration and decision making in a project and revolve around key project management activities such as cost, scheduling and quality.
+
A meeting is a formal or informal event where individuals meet either face-to-face or virtually (by the use of audio or video conference tools). In projects, groups of people need to discuss, align, inform and to communicate for other reasons, hence there exists numerous purposes and needs for meetings. They are essential for collaboration and decision making in projects and they revolve around key project management activities such as cost, scheduling, and quality.
  
Research reveals that even though managers spend more than 50% of their time in meetings, many meetings fail<ref name=Romanco2001>Romanco, N. and Nunamaker, J. (2001). Meeting Analysis: Findings from Research and Practice. ''Proceedings of the 34th Annual Hawaii International Conference on System Science'', p 4. Available at: http://citeseerx.ist.psu.edu/viewdoc/download?doi=10.1.1.570.6650&rep=rep1&type=pdf [Accessed 19 Feb. 2018]</ref>.
+
Research reveals that even though managers spend more than 50% of their time in meetings, many meetings fail and cause big, unnecessary costs on wasted time.<ref name=Romanco2001>Romanco, N. and Nunamaker, J. (2001). Meeting Analysis: Findings from Research and Practice. ''Proceedings of the 34th Annual Hawaii International Conference on System Science'', p 4. Available at: http://citeseerx.ist.psu.edu/viewdoc/download?doi=10.1.1.570.6650&rep=rep1&type=pdf [Accessed 19 Feb. 2018]</ref>
Project managers often need to not only participate frequently in meetings, but also plan, facilitate and evaluate meetings throughout the entire project life cycle and especially during the execution phase. Project Managers can use this as an opportunity to implement strategies for creating and managing effective meetings.
+
Project managers often need to not only participate in meetings frequently but also plan, facilitate and evaluate meetings throughout the project's entire life cycle and especially during the execution phase, when project resources most often peak in numbers and cost. Project managers can use their responsibility as an opportunity to implement strategies for creating and managing effective meetings.
 
   
 
   
The purpose of this article is to provide a framework and guidelines for project managers to consider and implement in projects. In order to develop an in-dept framework, this article builds on state-of-the-art research and studies on meetings from leading universities and standards on project management from PMI's project management guide book <ref name=PMBOKguide2013>{{Project Management Institute. (2013). A guide to the Project Management Body of Knowledge (PMBOK® guide)- Fifth Edition, Pennsylvania: Project Management Institute, Inc., p.589}}</ref>.
+
The purpose of this article is to provide strategies in the form of guidelines for project managers to consider and implement in projects. In order to develop an in-depth understanding of the challenges and how to avoid them, this article builds on state-of-the-art research and studies on meetings from leading universities. It also relies on standards on project management from Project Management Institute's "A guide to the Project Management Body of Knowledge". <ref name=PMBOKguide2013>Project Management Institute. (2013). A guide to the Project Management Body of Knowledge (PMBOK® Guide)- Fifth Edition, Pennsylvania: Project Management Institute, Inc., p.589</ref>
 
+
Meeting guidelines and methodology is based on contributions and experience from the construction and pharmaceutical industries. Research is conducted through interviews and data provided by industry managers such as: construction managers, and project managers from both industries. Is it the aim of this article, that the methodology provided is applicable in other industries too.
+
  
The key benefit for a project manager when planning an approach to meetings is that it identifies the approach to communicate most effectively and efficiently, both internal in the project team and with stakeholders. Developing a strategy for meetings can save the project time and costs and on same time keep project team members motivated.
+
The key benefit for a project manager planning an approach to meetings is that it helps to identify how to communicate most effectively and efficiently, both internal in the project team and with stakeholders. Developing a strategy for meetings can save the project time and costs and on same time keep project team members motivated.
  
 
== Too many meetings fail ==
 
== Too many meetings fail ==
  
“Meetings are often unnecessary or badly run” claims the authors of “Kill bad meetings”<ref name=Hall2017>Hall, K. and Hall, A. (2017). Kill Bad Meetings. London: NB Books, p. 224.</ref>. They support this statement with industry research, scientific studies and conducted by the authors themselves.
+
“Meetings are often unnecessary or badly run” claims the authors of “Kill bad meetings”.<ref name=Hall2017>Hall, K. and Hall, A. (2017). Kill Bad Meetings. London: NB Books, p. 224.</ref> They support this statement with research from scientific studies and industry research conducted by the authors themselves.
  
'''Unnecessary meetings:''' They’ve found that up to half of the content in meetings is not relevant to participants or could be delivered in other, more simple ways.
+
'''Unnecessary meetings:''' they’ve found that up to half of the content in meetings is not relevant to participants or could be delivered in other, more simple ways.
  
'''Badly run meetings:''' many meetings that need to happen fail to deliver outcome effectively and does not encourage participation.
+
'''Badly run meetings:''' many meetings that need to happen fails to deliver outcome effectively and do not encourage participation.
  
When investigating the truth in this statement similar examples from other sources show similar results:
+
When investigating the relevance of this statement, examples from other sources show similar results:
- In a study made by Microsoft 69% of the 38.000 participants felt meetings weren't productive <ref name=Microsoft2005>Microsoft.com. (2005). Survey finds workers average only three productive days per week. Available at: https://news.microsoft.com/2005/03/15/survey-finds-workers-average-only-three-productive-days-per-week/ [Accessed 29 Jan. 2018]</ref>
+
* In a study made by Microsoft 69% of the 38.000 participants felt meetings weren't productive. 60% said they didn't have work-life balance, and the feeling of being unproductive contributed to this<ref name=Microsoft2005>Microsoft.com. (2005). Survey finds workers average only three productive days per week. Available at: https://news.microsoft.com/2005/03/15/survey-finds-workers-average-only-three-productive-days-per-week/ [Accessed 29 Jan. 2018]</ref>
 
   
 
   
- People spend an average of 2 days per week in meetings and 50% of it is wasted <ref name=Hall2017 />
+
* People spend an average of 2 days per week in meetings, and 50% of it is a waste of time<ref name=Hall2017 />
- A 2012 survey by salary.com found "too many meetings” to be the #1 timewaster at the office, with 47% of votes, up from #3 in 2008 <ref name=Hall2017 />
+
* Too many meetings is the #1 waste of time at the office, with 47% of votes, up from #3 in 2008<ref name=Hall2017 />
  
The last analysis points towards that either the quality of meetings is worsening, or that the amount of meetings is increasing. In the study "Collaborative Overload" claims the authors that over the last 20 years the time spent by people in collaborative activities (meetings, calls, emails etc.) has increased by 50% or more <ref name=Cross2016>Cross, R., Rebele, R., Grant, A. (2016). Collaborative Overload. ''Harvard Business Review'', January-February 2016, p. 74-79. Available at: https://hbr.org/2016/01/collaborative-overload [Accessed 19 Feb, 2018]</ref>
+
The last example points towards that either the quality of meetings worsens, or that the amount of meetings increases. In the study "Collaborative Overload" claims the authors that over the last 20 years, the time spent by people in collaborative activities (meetings, calls, emails etc.) was increased by 50% or more. <ref name=Cross2016>Cross, R., Rebele, R., Grant, A. (2016). Collaborative Overload. ''Harvard Business Review'', January-February 2016, p. 74-79. Available at: https://hbr.org/2016/01/collaborative-overload [Accessed 19 Feb, 2018]</ref>
  
  
The effect of bad meetings are many and can turn into inhibitors in projects:
+
There are many effects of bad meetings. They turn into barrages in projects:
- Meetings are huge costs in projects.
+
* Meetings are huge costs in projects.<br />Example: a managerial/professional person in Europe or in the USA costs around $100,000 to employ in 2017. $40,000 of this is spent directly on attending meetings.<ref name=Hall2017/> Preparation for meetings is not included in this. In addition, time spent in meetings is also time not spent on individual work. Many meetings and interruptions during a day can postpone important tasks for an individual and prolong tasks' delivery time.
Example: a managerial / professional person in Europe or the USA costs around $100,000 to employ (at 2017 prices). $40,000 of this is spent directly in attending meetings. Preparation for meetings is in addition to this, and internal meetings are also a major driver of business travel costs <ref name=Hall2017/>. In addition to this, time spent in meetings is also time not spent on individual work – many meetings and interruptions can postpone important tasks for an individual.
+
* People attending meetings perceived as ineffective are affected at the end of the workday and similarly, it affects their overall job satisfaction. Employees feel stressed, dissatisfied with their jobs and the study reveals that they are more likely to leave their job.<ref name=Rogelberg2007/>
- People attending meetings perceived as ineffective are affected at the end of the workday and it affects their overall job satisfaction. Employees feel stress, dissatisfied with their jobs and the study reveals that they are more likely to leave their job.“The Science and Fiction of Meetings”
+
These two reasons are big challenges for a project manager. Reaching overall goals: deliver projects on time and under budget within scope is threatened and the risk increases when there is no control.
+
  
'''Causes for bad meetings vary, but general causes include:'''
+
These two reasons can become big challenges for a project manager. Reaching overall goals: deliver projects on time and under budget within the scope is threatened and the risk increases when there is no control.
- In many project organizations, the whole field of “meetings” is unmanaged.
+
Who call, run and attend meetings and how often is often not agreed.
+
- Unmanaged meetings generate unmanaged costs.
+
In the example earlier, more than 40% of one resource’s cost and time is spent in meetings. Is less than 60% time enough to manage / work individually on a project?
+
- Today, development projects are becoming more complex within product and service development. Higher complexity often needs people with different specialties and big project organizations. This can also result in more unmanaged meetings. <ref name=Weck2011>Weck, O., Roos, D., Magee, C. (2011). Engineering Systems: meeting human needs in a complex technological world. Cambridge, Masssachusetts: Massachusetts Institute of Technology, p. 208.</ref>
+
  
= Project life cycle in phases =
 
  
[[File:figur1.png|thumb|right|651x418px|Figure 1: Example of project phases, inspired from PMBOK® Guide]]
+
Causes for bad meetings vary, but causes include:
 +
* In many project organizations, the whole field of “meetings” is unmanaged. <br />Who calls, run and attend meetings and how often, is often not agreed.
 +
* Unmanaged meetings generate unmanaged costs. <br />In the example stated above, more than 40% of one resource’s cost and time is spent on meetings. This leaves less than 60% time to manage/work individually on a project.
 +
* Today, projects are becoming more complex within product and service development. Higher complexity needs people with different specialties and large project organizations. This can generate more unmanaged meetings. <ref name=Weck2011>Weck, O., Roos, D., Magee, C. (2011). Engineering Systems: meeting human needs in a complex technological world. Cambridge, Massachusetts: Massachusetts Institute of Technology, p. 208.</ref>
  
Splitting up a project into phases allows project management to plan and control progress throughout a project life cycle. In this article, the partition of projects will simplify when the load is highest and when strategizing needs to be done, in order to succeed with managing meetings.
+
= Project life cycle phases =
  
A project manager will manage meetings throughout the whole project. Some meetings such as a project status meeting or budget meeting can be recurring from beginning to end. Other meetings are only relevant in one phase and some only happen once.
+
[[File:figur1.png|thumb|right|641x418px|Figure 1: Example of project phases, inspired by PMBOK® Guide]]
  
In order to prepare for meetings and assess impact, the manager identifies current challenges in one phase in relation to the achieving overall project goal. A useful method for this is to identify project phases.
+
Splitting up a project into phases allows project management to plan and control progress throughout a project's life cycle. The partition of a project shows when the load is highest and when it is reasonable to prepare the strategy, in order to succeed in managing meetings.
  
A project phase consists of related project activities sharing a goal. Completing activities will strive towards reaching the goal and entering next project phase. Project phases can occur iteratively. In some cases, new findings occur in the executing phase which demands project teams to make changes in scope and revisit the planning phase. There is no one-size-fits-all-model to describe project phases for every project. Projects are unique and various industries have various project models. However, most projects go through following four phases <ref name="PMBOKguide2013" />:
+
A project manager will facilitate meetings throughout the entire project. Some meetings such as a project status meeting or a budget meeting recur from beginning to end of the life cycle. Other meetings are only relevant in one phase and some happen once.
  
'''Initiation''' - Define new project/new phase of existing project - Define initial scope and finances - Stakeholders that influence overall outcome will be identified - PM will be selected - Project charter/mission statement including business case needs approval to complete this phase
+
In order to prepare for meetings and assess impact, the manager identifies current challenges in one phase in relation to achieving the overall project goal. A useful method for this is to identify project phases.
  
'''Planning''' - Scope is refined and objectives are found - Project (core) team is established - PM-plan and project plan are created - Shared documents and platforms within project are created including documents about: scope, time, cost, quality, communication, stakeholder engagement, risks, procurement, human resources etc. - Information related to project is gathered
+
A project phase consists of related project activities sharing a goal. Completing activities will strive towards reaching the goal and entering next project phase. Sometimes, project phases occur iteratively. In some cases, new findings occur during execution, which demands project teams to make changes in scope and revisit the planning phase. There is no one-size-fits-all model to describe project phases in every project. Projects are unique, and various industries use various project models. However, most projects go through following four phases with related project management activities: <ref name="PMBOKguide2013" />
  
'''Execution''' - Other project participants might be discovered - Work defined in plan made in previous phase is performed and completed, unless severe changes are discovered. In this case, there might be a need for an iteration back to the planning phase. - People and resources are coordinated, stakeholder expectations are managed, activites of project are integrated and performed in accordance with plan. Results requiring updates and needing to revisiting planning phase include: activity durations, pricing, unanticipated risks.
+
'''Initiation'''  
 +
* definition of new project or new start of existing project
 +
* initial scope and finances
 +
* identification of stakeholders that influence overall outcome and project manager
 +
* project charter or mission statement including business case approval completes this phase
  
'''Closing''' Completing of project include: - closing contracts - Archive data - Closeout procurement - Evaluate and note learnings and reviews.
+
'''Planning'''
 +
* refinement of scope and objectives
 +
* project (core) team establishment
 +
* project management plan and time schedule
 +
* creation of shared documents and platforms within project including: scope, time, cost, quality, communication, stakeholder engagement, risks, procurement, human resources
 +
* research and gathering of important information related to project
  
 +
[[File:Figur23.jpg|thumb|right|641x418px|Figure 2: Project activity measured in cost and staffing level over time, inspired by PMBOK® Guide]]
  
 +
'''Execution'''
 +
* other project participants might be discovered
 +
* performance of work defined in plan from the previous phase unless severe changes occur. In this case, there is a need to iterate and revisit the planning phase.
 +
* coordination of people and resources, stakeholder expectations management, the performance of activities in accordance with the plan.
  
 +
Results requiring updates and needing to revisiting planning phase include activities' duration, pricing, unanticipated risks.
  
== Project activity in phases ==
+
'''Closing'''
 +
* Completion of a project includes:
 +
** closing contracts
 +
** archive data
 +
** closeout procurement
 +
** evaluate and note learnings and reviews.
  
[[File:figur2.png|thumb|left|551x418px|Figure 2: Project activity measured in cost and staffing level over time, inspired from PMBOK® Guide]]
 
  
 +
<font size="4">'''Project activities in phases'''</font>
  
Figure 2 shows a generic, high-level view of how the cost and staffing level evolve across the project life cycle. Cost and staffing level are low at the start, increases when the project is carried out and decreases fast in the closing phase <ref name="PMBOKguide2013" />.
 
  
This indicates that throughout the whole execution phase, knowing how to structure time spent is of high importance, since many people are involved and costs are at the highest.
+
Figure 2 shows a generic, high-level view of how the cost and staffing level develop during the project's life cycle. Cost and staffing level are low at the start, increase when the project is carried out and decrease fast in the closing phase. <ref name="PMBOKguide2013" />
 +
 
 +
This indicates that throughout the whole execution phase, knowing how to structure time is of high importance since there are many people involved and costs are at the highest.
 
Creating structure and a plan for meeting management early in the project (prior to execution) helps to maintain focus and efficiency when costs are high.
 
Creating structure and a plan for meeting management early in the project (prior to execution) helps to maintain focus and efficiency when costs are high.
  
 
= Meeting strategies =
 
= Meeting strategies =
  
Successful communication in a project underpins accurate message deliveries, sufficient communication to stakeholders, higher level of employee involvement and the ultimate success of any project.  
+
Successful communication in a project underpins accurate message deliveries, sufficient communication to stakeholders, a higher level of employee involvement and the ultimate success of any project.  
  
In most projects, planning communication occurs early in the planning phase and can be included in the project management plan. This allows the manager to appropriately consider resources, such as time and costs in communication activities.
+
In most projects, communication planning occurs early in the planning phase and can be included in the project management plan. This allows the manager to appropriately consider resources, such as time and costs in communication activities.
  
Listed below are suggestions for meeting strategies for the project manager to consider. Research relies on several scientific studies.
+
Listed below are suggestions for meeting strategies for the project manager to consider. To each suggestion belongs a primarily relevant project phase. The research relies on several scientific studies providing different knowledge-based methods and guidelines.
  
 
== Avoiding unnecessary meetings with effective communication ==
 
== Avoiding unnecessary meetings with effective communication ==
  
In projects, effective communication is when information is provided in right format, at the right time, to the right audience, and with the right impact. <ref name="PMBOKguide2013" />
+
In projects, effective communication is when information is provided in the right format, at the right time, to the right audience, and with the right impact. <ref name="PMBOKguide2013" />
Setting up guidelines in projects for when it is ok to invite to a meeting is one strategy to avoid the meetings not creating value in projects. Indicators for when there is a need for a meeting are listed here:
+
Setting up guidelines in projects for when it is acceptable to call a meeting is one way to avoid unnecessary meetings that do not create value. Indicators for when a meeting is needed are listed here:
- when unresolved issues are inhibiting the progress of a project or interdependent projects.<ref name=Rogelberg2007>{{Rogelberg, S., Scott, C. Kello, J. (2007). The Science and Fiction of Meetings. ''MIT Sloan Management Review'', Volume 48(2), p. 18-21. Available at: https://orgscience.uncc.edu/sites/orgscience.uncc.edu/files/media/Rogelberg%20et%20al.%20-%202007%20-%20The%20science%20and%20fiction%20of%20meetings.pdf [Accessed 19 Feb, 2018]}}</ref>
+
*when unresolved issues are inhibiting the progress of a project or interdependent projects<ref name=Rogelberg2007>Rogelberg, S., Scott, C. Kello, J. (2007). The Science and Fiction of Meetings. ''MIT Sloan Management Review'', Volume 48(2), p. 18-21. Available at: https://orgscience.uncc.edu/sites/orgscience.uncc.edu/files/media/Rogelberg%20et%20al.%20-%202007%20-%20The%20science%20and%20fiction%20of%20meetings.pdf [Accessed 19 Feb, 2018]</ref>
- a big decision needs to be made
+
* decision making
- idea generation
+
* idea generation
- a compelling agenda is distributed prior to the meeting
+
* distribution of a compelling agenda prior to the meeting
- celebration of reaching a milestone
+
* celebration of reaching a milestone
  
In other cases, communication is needed but not in meetings. This can often be identified as the type of communication where only one person needs to speak. Examples are:
+
In other cases, there exists a need for communication, but not in a meeting. This can often be identified as the type of communication where only one person needs to speak. Examples are:
- Updates
+
* updates
- Delivery of information
+
* delivery of information
- Presentations
+
* presentations
  
 
All the above can often be delivered in an email, via a phone call or in an informal meeting with only two people.
 
All the above can often be delivered in an email, via a phone call or in an informal meeting with only two people.
Information can often be found in existing repositories (reports/internal knowledge sharing portals). When a person chooses to invite other(s) to a meeting to deliver information they could have found themselves, the meeting becomes costly mismanaged time for all involved. This is an example of one bad effect, when meetings aren’t managed.
+
In some cases, information is in existing repositories (reports/internal knowledge sharing portals). When a person chooses to invite other(s) to a meeting to deliver information which they could have found themselves, the meeting becomes costly, misused time for all involved. This is an example of one bad effect when meetings aren’t managed.
  
In some projects, meeting free days are introduced where participants have to reject meetings occurring on their meeting free day. In other projects it is allowed for participants to select amongst meetings to attend. When selecting, a small checklist similar to figure 3 can be used (MANGLER FIGUR)
+
In some projects, meeting free days are introduced where participants have to reject meetings occurring on their meeting free day. In other projects, it is allowed for participants to select among which meetings to attend. When selecting, using a small checklist similar to the table below, helps to understand what to look for.
 +
 
 +
{| class="wikitable"
 +
|-
 +
! Meetings to attend
 +
! Meetings to decline
 +
|-
 +
| Live interaction required for topic to succeed
 +
| No clear outcome stated in advance
 +
|-
 +
| Your expertise needs to be shared to make decision
 +
| Matters have low relevance
 +
|-
 +
| Negotiation, resolve conflicts
 +
| Objective would be delivered better other ways
 +
|-
 +
| Building relationships
 +
| Wrong people are attending
 +
|}
 +
 
 +
'''Implementation phase'''<br />
 +
This mindset towards meetings will work most efficiently when implemented at the very beginning, the initiation phase. The project manager can use all tools him/herself and share the mindset with the rest of the core group to create a unilateral approach.
  
 
== Creating valuable meetings ==
 
== Creating valuable meetings ==
  
 
Being the creator of a meeting means that one needs to determine who needs to participate and how to keep participants interested and involved during a meeting.
 
Being the creator of a meeting means that one needs to determine who needs to participate and how to keep participants interested and involved during a meeting.
Following is a checklist for the meeting creators. Answering these questions gives an overview and frames the purpose of the meeting.
+
Following is a checklist for the meeting creators. Answering these questions gives an overview and frames the purpose of the meeting:
- Who do I need?
+
- Why do we need to meet?
+
- Be specific(???)
+
- What is the outcome?
+
  
Segment between core group and peripheral project members: only involve last part when their input is very critical.
 
  
== Planning meetings in advance to maximize efficiency ==
+
{| class="wikitable"
 +
|-
 +
! Questions
 +
! Outcome
 +
|-
 +
| Who do I need?
 +
| Different people have different roles and competencies
 +
|-
 +
| Why do we need to meet?
 +
| being aware of the cause is sometimes challenging, but the manager needs to know before inviting
 +
|-
 +
| How can I be specific?
 +
| Challenges to change perspective or/and aware of time and importance
 +
|-
 +
| What is the outcome?
 +
| What/who will benefit and realizing goal
 +
|-
 +
|}
  
In projects, efficient communication means providing only the information that is needed<ref name="PMBOKguide2013" />.
 
  
It is agreed in literature used in this article<ref name="Rogelberg2007" /><ref name="PMBOKguide2013" /><ref name="Hall2017" /><ref name=Perlow2017>{{Perlow, L., Hadley, C., Eun, E. (2017). Stop the Meeting Madness. ''Harvard Business Review'', July-August 2017, p. 62-69. Available at: https://hbr.org/2017/07/stop-the-meeting-madness [Accessed 23 Feb, 2018]}}</ref> that creating a compelling agenda and sending relevant material to meeting participants is a time saving action.
+
'''Implementation phase'''<br />
In some cases, the agenda shows time estimates for the different topics. This gives participants an understanding of the important tasks in the meeting and signals when there is time for discussion and when there is not. An agenda also helps participants to know if they need to join the meeting or not.
+
This becomes relevant especially in the execution phase, where the number of participants is highest. There should be a segmentation between core group and peripheral project members. The last group should only be invited when their input is very important.
The agenda needs to be relatable. Topics like: “business review” does not fall into this category and can either be elaborated or phrased differently.
+
  
The purpose of the agenda is to give meeting participants an introduction to the meeting, then they know if their participation is needed and how to prepare. To avoid the meeting from becoming a habit, the agenda can include supporting information. Sending out agenda prior to meeting allows participants to contribute, which makes the contemporary agenda relevant.
+
== Planning meetings in advance to maximize efficiency ==
  
== Participation during meeting ==
+
In projects, efficient communication means providing only the information that is needed.<ref name="PMBOKguide2013" />
  
Often when people give meetings bad reviews, it is because the meeting doesn’t seem relevant to them. People are motivated, when purpose/success criteria relates to their role and tasks in a project. Having an important role during the meeting creates purpose for them to participate, therefore encouraging active participation, delegating actions before, during or after meeting will encourage participants.
+
It is agreed in literature used in this article<ref name="Rogelberg2007" /><ref name="PMBOKguide2013" /><ref name="Hall2017" /><ref name=Perlow2017>Perlow, L., Hadley, C., Eun, E. (2017). Stop the Meeting Madness. ''Harvard Business Review'', July-August 2017, p. 62-69. Available at: https://hbr.org/2017/07/stop-the-meeting-madness [Accessed 23 Feb, 2018]</ref> that creating a compelling agenda and sending relevant material to meeting participants is a time saving action.
  
 +
In some cases, the agenda shows time estimates for the different topics. This gives participants an understanding of the important tasks in the meeting and structures discussion: when there is time and when there is not. The agenda needs to be relatable. Topics such as: “business review” does not fall into this category and can either be elaborated or phrased differently.
  
== Meeting techniques and locations ==
+
The purpose of the agenda is to provide an introduction of the meeting to participants. Then they understand why their participation is important and how to prepare. To avoid the meeting from becoming a habit, the agenda can include supporting information. Sending out agenda prior to the meeting allows participants to contribute, which makes the contemporary agenda relevant.
  
Previously, creating a compelling agenda was recommended. It is just as important to know how to use the agenda. In some cases, derivatives from the topics on the agenda can be the most valuable part of the meeting. Participants are engaged and new solutions/organizational knowledge is created. In order to do this and still manage a valuable meeting, the manager’s focus need to be on the output rather than sticking to the agenda. Hall<ref name=Hall2017 /> suggests following five questions:
+
'''Implementation phase'''<br />
 +
As soon as possible. The beginning of a project is also when risks and uncertainties are highest. <ref name=PMBOKguide2013 /> When the project manager invites to meetings about scope, schedule and cost, it is extremely important that everyone needed participates in meetings about interrelated topics to minimize risks, add their contribution and get to know each other.
  
- What outcome do we want from this topic?
+
== Participation during meeting ==
 +
 
 +
Often when people give meetings bad reviews, it is because the meeting doesn’t seem relevant to them and/or because they do not know how to participate. People are motivated when purpose/success criteria relate to their role and tasks in a project. Having an important role during the meeting creates a purpose for them to participate, therefore encouraging active participation, delegating actions before, during or after the meeting will encourage participants.
 +
 
 +
Stated previously, creating a compelling agenda help clearing meeting goal. It is just as important to know how to use the agenda. In some cases, derivatives from the topics on the agenda can be the most valuable part of the meeting. Participants are engaged and new solutions/organizational knowledge is created. In order to do this and still manage a valuable meeting, the manager’s focus needs to be on the output rather than sticking to the agenda. Hall<ref name=Hall2017 /> suggests following five questions:
  
- What process will we need to deliver this outcome?
 
  
- Which participants need to be involved?
 
  
- How much time is worth spending on this?
+
{| class="wikitable"
 +
|-
 +
! Questions
 +
! Supporting questions
 +
|-
 +
| What outcome do we want on this topic?
 +
| In order to do what?
 +
|-
 +
| What process will we need to deliver this outcome?
 +
| How do we get there?
 +
|-
 +
| Which participants need to be involved?
 +
| Who will contribute?
 +
|-
 +
| How much time is worth spending on this?
 +
| How much time from schedule can we use on this compare to other tasks?
 +
|-
 +
|}
  
- To avoid meetings from becoming a habit?
 
  
  
( MANGLER Purpose model from PMBOK??)
+
Rogelberg<ref name=Rogelberg2007 /> suggests to experiment with new techniques and locations in order to stimulate participation and ideas. For meetings including many people and where decision making is important, it is sometimes helpful to split the crowd up into smaller groups. Similarly, facilitate meetings where everyone are standing up or in new environments often helps creativity and breaking up habits.
  
Rogelberg<ref name=Rogelberg2007 /> suggests to experiment with new techniques and locations in order to stimulate participation and ideas. For meetings including many people and where decision making is important, it is sometimes helpful to split the crowd up in smaller groups. Similarly, holding meetings standing up or in new environments often helps creativity and breaking up habits.
+
'''Implementation phase'''<br />
 +
Encouragement of participation is important throughout all phases. Breaking up with habits in meetings will become relevant if/when people start to lose motivation. If project management pays attention to the outcome of the recurring meetings, needs for changes in style will be easy to discover. Meeting participants can help with acting when they experience that meetings they attend start to lose value.
  
 
== Meeting minutes as a strategic tool ==
 
== Meeting minutes as a strategic tool ==
  
[[File:figur4.png|thumb|left|451x518px|Figure 5: Meeting minutes example, inspired from construction industry]]
+
[[File:figur4.png|thumb|right|351x418px|Figure 3: Meeting minutes example, inspired from construction industry]]
  
Important information and actions from meetings are often stored in minutes and saved in the project management plan(PMIBOK). Information kept in minutes should follow a structure and be maintained in an organized manner.  
+
Important information and actions from meetings are often stored in minutes and saved in the project management plan.<ref name=PMBOKguide2013 /> Information kept in minutes follows a structure and is maintained in an organized manner.
Minutes can also be used strategically as a “meeting timeline”. For recurring, weekly meetings, such as a project status meeting or steering committee meeting, minutes from the previous week including important concerns, questions and actions can be used as an outcome driven agenda (ref: industry).
+
Minutes can also be used strategically as a “meeting timeline”. For recurring, weekly meetings, such as a project status meeting or steering committee meeting, minutes from the previous week including important concerns, questions and actions can be used as an outcome driven agenda.<ref name=Industry2018>Model inspired by industry practice from construction industry.</ref>
  
See figure 5 as an industry example.
+
See figure 3 as an example inspired by the construction industry.
  
= Monitor Effects =
+
'''Implementation phase'''<br />
 +
Meeting minutes should always be conducted, also when using another structure. When closing project (and after) the meeting minutes can in some cases work as the project library including milestones and real-time project history. In cases where projects end up with lawsuits meeting minutes can become very important legal documents. In more fortunate cases, the project manager needs the minutes during the evaluation.
  
There are several ways to monitor how the application of meeting strategies affects the project’s progress. A few are listed below.
+
= Monitor effects =
  
- Survey core group: an open survey with room for respondents to suggest their improvements.
+
There are several ways to monitor how the application of meeting strategies affects the project’s development.
  
- KPI: Key performance indicators can either measure progress or achievement of operational goal. For monitoring meeting the success of strategies suggested in this article, relevant KPI’s are stakeholder satisfaction (for stakeholder meetings), project profitability (difference between revenue generated by a project and cost of delivering work), project success rate (percentage of projects delivered on time and under budget)
+
'''Survey core group:''' an open survey with room for respondents to suggest their improvements.
  
- Pulse-checks: informal, focused conversations with employees to understand how they approach their work.
+
'''KPI''': Key performance indicators can either measure progress or achievement of the operational goal. For monitoring meetings' success when implementing strategies suggested in this article, relevant KPIs include:  stakeholder satisfaction (for stakeholder meetings), <br />project profitability (difference between revenue generated by a project and cost of delivering work), project success rate (percentage of projects delivered on time and under budget)
 +
 
 +
'''Pulse-checks:''' informal, focused conversations with employees to understand how they approach their work.
 +
 
 +
'''When to implement'''
 +
The monitoring is important during the planning and executing phase where most activities need to be solved, hence there will be many meetings. The project manager can monitor the progress or use a resource for this task.
  
 
= Meetings as a basis for change =
 
= Meetings as a basis for change =
  
As previously stated, meeting culture can have a great impact in a project and in organizations. If succeeding with strategizing meetings in one project, the application in other projects or programs can be considered. A goal for changing meetings is to create new organizational culture with improved communication, productivity and integration of the work. Increased job satisfaction and work/life balance is another perk, therefore, better meetings – better work lives<ref name=Perlow2017 />
+
Meeting culture can have a great impact on a project and in organizations. If succeeding with creating strategies for meetings in one project, the application in other projects or programs can be considered. A goal for changing meetings is to create a new organizational culture with improved communication, productivity, and integration of the work. Increased job satisfaction and work/life balance is another perk. Therefore, better meetings – better work lives.<ref name=Perlow2017 />
  
 
Implementation of protocols and changing behaviors take time. Sustaining momentum is an even bigger challenge and can often not be considered as a process but more likely an ongoing activity needing consistent attention. However, if successful there is no reason for the meeting strategy not to scale up and become a supporting act to the organizational strategy.
 
Implementation of protocols and changing behaviors take time. Sustaining momentum is an even bigger challenge and can often not be considered as a process but more likely an ongoing activity needing consistent attention. However, if successful there is no reason for the meeting strategy not to scale up and become a supporting act to the organizational strategy.
Line 175: Line 250:
 
= Limitations =
 
= Limitations =
  
There are several limitations to strategies suggested as meetings vary a lot in different organizations, even within different projects. However, this article deals with well known, generic problems and challenges. Limitations are following:
+
There are several limitations to the strategies suggested, as meetings vary a lot in different organizations, even within different projects. However, this article deals with well known, generic problems and challenges. Limitations are following:
  
- Having too many meetings can be a symptom of a deeper, underlying corporate and cultural beliefs and practices. Therefore, reducing the number of meetings and sorting meetings in relevance may not improve working conditions for the team. Instead there is a chance that another activity will fill in the empty time slot. Too many meetings can be the tip of the iceberg of deeper underlying challenges in an organization, the action of sorting in meetings itself will not resolve this.
+
* Having too many meetings can be a symptom of a deeper, underlying corporate and cultural belief and practice. Therefore, reducing the number of meetings and sorting meetings in relevance may not improve working conditions for the team. Instead, <br />there is a chance that another activity will fill in the new, empty time slot. Too many meetings can be the tip of the iceberg of underlying challenges in an organization, the action of sorting in meetings itself will not resolve this.
 +
* Working with changing meetings can be costly itself. It may not be suitable for all companies because the revenue created is not directly viewed on the bottom line. At least not in the beginning.
 +
* Changing meeting culture is a team effort. One manager cannot perform severe changes without support from the team and upper management.
  
- Working with changing meetings can be costly itself. It may not be suitable for all companies, because the revenue created is not directly to view on the bottom-line. At least not in the beginning.
+
= Annotated bibliography =
  
- Changing meeting culture is a team effort. One manager cannot perform severe changes without encouragement from team and upper management.
+
'''Project Management Institute. "A Guide to the Project Management Body of Knowledge (PMBOK® Guide)". Fifth edition, 2013'''<ref name="PMBOKguide2013" />
  
= References =
+
The concept of dividing a project’s life cycle into phases is described in PMBOK as well is the project communications management. Chapter 10 illustrates how communication is planned, distributed and documented. The book contains an investigation of challenges, guidelines, and tools used in project management industry.
<references/>
+
  
= Annotated bibliography =
+
'''Rogelberg, S., Scott, C. Kello, J. “The Science and Fiction of Meetings” 2007'''<ref name="Rogelberg2007" />
'''PMIBOK'''
+
The concept of dividing a project’s lifecycle up into phases is outlined in PMIBOK as well is the project communications management. Chapter 10 illustrates how communication is planned, distributed and documented.
+
  
'''MIT Sloan: “The Science and Fiction of Meetings” 2007 Rogelberg et al'''
+
This article evolves around employees spending an increasing amount of time in meetings and also complaining about them. But these employees see meetings as a tool for productivity and there is a need for companies learning to use this tool (meetings) better. The article provides examples and has statistics over how much time is spent in meetings.
Bla bla
+
  
'''Kevan Hall, Alan Hall: Kill Bad Meetings 2017:'''
+
'''Hall, K., Hall, A. "Kill Bad Meetings" 2017'''<ref name="Hall2017" />
The book is based on industry research as well as the author’s own experience as former CEO’s in large organizations. The book aims to improve meeting culture worldwide by providing tools for managers to introduce in their own (project) organization. The book also covers cross cultural meetings, dealing with different time zones as well as facilitating a conference: a meeting for a lot of people. However, it is important to note that the book is published from consultants, why the purpose aren’t completely objective.
+
 
 +
The book is based on industry research as well as the authors own experiences as former CEOs in big organizations. The book aims to improve meeting culture worldwide by providing tools for managers to introduce in their own project and/or organization. The book also covers cross-cultural meetings, dealing with different time zones as well as facilitating a conference: a meeting for a lot of people.
 +
 
 +
= References =
 +
<references/>

Latest revision as of 19:18, 16 November 2018

Developed by Julie Laursen


Contents

[edit] Abstract

A meeting is a formal or informal event where individuals meet either face-to-face or virtually (by the use of audio or video conference tools). In projects, groups of people need to discuss, align, inform and to communicate for other reasons, hence there exists numerous purposes and needs for meetings. They are essential for collaboration and decision making in projects and they revolve around key project management activities such as cost, scheduling, and quality.

Research reveals that even though managers spend more than 50% of their time in meetings, many meetings fail and cause big, unnecessary costs on wasted time.[1] Project managers often need to not only participate in meetings frequently but also plan, facilitate and evaluate meetings throughout the project's entire life cycle and especially during the execution phase, when project resources most often peak in numbers and cost. Project managers can use their responsibility as an opportunity to implement strategies for creating and managing effective meetings.

The purpose of this article is to provide strategies in the form of guidelines for project managers to consider and implement in projects. In order to develop an in-depth understanding of the challenges and how to avoid them, this article builds on state-of-the-art research and studies on meetings from leading universities. It also relies on standards on project management from Project Management Institute's "A guide to the Project Management Body of Knowledge". [2]

The key benefit for a project manager planning an approach to meetings is that it helps to identify how to communicate most effectively and efficiently, both internal in the project team and with stakeholders. Developing a strategy for meetings can save the project time and costs and on same time keep project team members motivated.

[edit] Too many meetings fail

“Meetings are often unnecessary or badly run” claims the authors of “Kill bad meetings”.[3] They support this statement with research from scientific studies and industry research conducted by the authors themselves.

Unnecessary meetings: they’ve found that up to half of the content in meetings is not relevant to participants or could be delivered in other, more simple ways.

Badly run meetings: many meetings that need to happen fails to deliver outcome effectively and do not encourage participation.

When investigating the relevance of this statement, examples from other sources show similar results:

  • In a study made by Microsoft 69% of the 38.000 participants felt meetings weren't productive. 60% said they didn't have work-life balance, and the feeling of being unproductive contributed to this[4]
  • People spend an average of 2 days per week in meetings, and 50% of it is a waste of time[3]
  • Too many meetings is the #1 waste of time at the office, with 47% of votes, up from #3 in 2008[3]

The last example points towards that either the quality of meetings worsens, or that the amount of meetings increases. In the study "Collaborative Overload" claims the authors that over the last 20 years, the time spent by people in collaborative activities (meetings, calls, emails etc.) was increased by 50% or more. [5]


There are many effects of bad meetings. They turn into barrages in projects:

  • Meetings are huge costs in projects.
    Example: a managerial/professional person in Europe or in the USA costs around $100,000 to employ in 2017. $40,000 of this is spent directly on attending meetings.[3] Preparation for meetings is not included in this. In addition, time spent in meetings is also time not spent on individual work. Many meetings and interruptions during a day can postpone important tasks for an individual and prolong tasks' delivery time.
  • People attending meetings perceived as ineffective are affected at the end of the workday and similarly, it affects their overall job satisfaction. Employees feel stressed, dissatisfied with their jobs and the study reveals that they are more likely to leave their job.[6]

These two reasons can become big challenges for a project manager. Reaching overall goals: deliver projects on time and under budget within the scope is threatened and the risk increases when there is no control.


Causes for bad meetings vary, but causes include:

  • In many project organizations, the whole field of “meetings” is unmanaged.
    Who calls, run and attend meetings and how often, is often not agreed.
  • Unmanaged meetings generate unmanaged costs.
    In the example stated above, more than 40% of one resource’s cost and time is spent on meetings. This leaves less than 60% time to manage/work individually on a project.
  • Today, projects are becoming more complex within product and service development. Higher complexity needs people with different specialties and large project organizations. This can generate more unmanaged meetings. [7]

[edit] Project life cycle phases

Figure 1: Example of project phases, inspired by PMBOK® Guide

Splitting up a project into phases allows project management to plan and control progress throughout a project's life cycle. The partition of a project shows when the load is highest and when it is reasonable to prepare the strategy, in order to succeed in managing meetings.

A project manager will facilitate meetings throughout the entire project. Some meetings such as a project status meeting or a budget meeting recur from beginning to end of the life cycle. Other meetings are only relevant in one phase and some happen once.

In order to prepare for meetings and assess impact, the manager identifies current challenges in one phase in relation to achieving the overall project goal. A useful method for this is to identify project phases.

A project phase consists of related project activities sharing a goal. Completing activities will strive towards reaching the goal and entering next project phase. Sometimes, project phases occur iteratively. In some cases, new findings occur during execution, which demands project teams to make changes in scope and revisit the planning phase. There is no one-size-fits-all model to describe project phases in every project. Projects are unique, and various industries use various project models. However, most projects go through following four phases with related project management activities: [2]

Initiation

  • definition of new project or new start of existing project
  • initial scope and finances
  • identification of stakeholders that influence overall outcome and project manager
  • project charter or mission statement including business case approval completes this phase

Planning

  • refinement of scope and objectives
  • project (core) team establishment
  • project management plan and time schedule
  • creation of shared documents and platforms within project including: scope, time, cost, quality, communication, stakeholder engagement, risks, procurement, human resources
  • research and gathering of important information related to project
Figure 2: Project activity measured in cost and staffing level over time, inspired by PMBOK® Guide

Execution

  • other project participants might be discovered
  • performance of work defined in plan from the previous phase unless severe changes occur. In this case, there is a need to iterate and revisit the planning phase.
  • coordination of people and resources, stakeholder expectations management, the performance of activities in accordance with the plan.

Results requiring updates and needing to revisiting planning phase include activities' duration, pricing, unanticipated risks.

Closing

  • Completion of a project includes:
    • closing contracts
    • archive data
    • closeout procurement
    • evaluate and note learnings and reviews.


Project activities in phases


Figure 2 shows a generic, high-level view of how the cost and staffing level develop during the project's life cycle. Cost and staffing level are low at the start, increase when the project is carried out and decrease fast in the closing phase. [2]

This indicates that throughout the whole execution phase, knowing how to structure time is of high importance since there are many people involved and costs are at the highest. Creating structure and a plan for meeting management early in the project (prior to execution) helps to maintain focus and efficiency when costs are high.

[edit] Meeting strategies

Successful communication in a project underpins accurate message deliveries, sufficient communication to stakeholders, a higher level of employee involvement and the ultimate success of any project.

In most projects, communication planning occurs early in the planning phase and can be included in the project management plan. This allows the manager to appropriately consider resources, such as time and costs in communication activities.

Listed below are suggestions for meeting strategies for the project manager to consider. To each suggestion belongs a primarily relevant project phase. The research relies on several scientific studies providing different knowledge-based methods and guidelines.

[edit] Avoiding unnecessary meetings with effective communication

In projects, effective communication is when information is provided in the right format, at the right time, to the right audience, and with the right impact. [2] Setting up guidelines in projects for when it is acceptable to call a meeting is one way to avoid unnecessary meetings that do not create value. Indicators for when a meeting is needed are listed here:

  • when unresolved issues are inhibiting the progress of a project or interdependent projects[6]
  • decision making
  • idea generation
  • distribution of a compelling agenda prior to the meeting
  • celebration of reaching a milestone

In other cases, there exists a need for communication, but not in a meeting. This can often be identified as the type of communication where only one person needs to speak. Examples are:

  • updates
  • delivery of information
  • presentations

All the above can often be delivered in an email, via a phone call or in an informal meeting with only two people. In some cases, information is in existing repositories (reports/internal knowledge sharing portals). When a person chooses to invite other(s) to a meeting to deliver information which they could have found themselves, the meeting becomes costly, misused time for all involved. This is an example of one bad effect when meetings aren’t managed.

In some projects, meeting free days are introduced where participants have to reject meetings occurring on their meeting free day. In other projects, it is allowed for participants to select among which meetings to attend. When selecting, using a small checklist similar to the table below, helps to understand what to look for.

Meetings to attend Meetings to decline
Live interaction required for topic to succeed No clear outcome stated in advance
Your expertise needs to be shared to make decision Matters have low relevance
Negotiation, resolve conflicts Objective would be delivered better other ways
Building relationships Wrong people are attending

Implementation phase
This mindset towards meetings will work most efficiently when implemented at the very beginning, the initiation phase. The project manager can use all tools him/herself and share the mindset with the rest of the core group to create a unilateral approach.

[edit] Creating valuable meetings

Being the creator of a meeting means that one needs to determine who needs to participate and how to keep participants interested and involved during a meeting. Following is a checklist for the meeting creators. Answering these questions gives an overview and frames the purpose of the meeting:


Questions Outcome
Who do I need? Different people have different roles and competencies
Why do we need to meet? being aware of the cause is sometimes challenging, but the manager needs to know before inviting
How can I be specific? Challenges to change perspective or/and aware of time and importance
What is the outcome? What/who will benefit and realizing goal


Implementation phase
This becomes relevant especially in the execution phase, where the number of participants is highest. There should be a segmentation between core group and peripheral project members. The last group should only be invited when their input is very important.

[edit] Planning meetings in advance to maximize efficiency

In projects, efficient communication means providing only the information that is needed.[2]

It is agreed in literature used in this article[6][2][3][8] that creating a compelling agenda and sending relevant material to meeting participants is a time saving action.

In some cases, the agenda shows time estimates for the different topics. This gives participants an understanding of the important tasks in the meeting and structures discussion: when there is time and when there is not. The agenda needs to be relatable. Topics such as: “business review” does not fall into this category and can either be elaborated or phrased differently.

The purpose of the agenda is to provide an introduction of the meeting to participants. Then they understand why their participation is important and how to prepare. To avoid the meeting from becoming a habit, the agenda can include supporting information. Sending out agenda prior to the meeting allows participants to contribute, which makes the contemporary agenda relevant.

Implementation phase
As soon as possible. The beginning of a project is also when risks and uncertainties are highest. [2] When the project manager invites to meetings about scope, schedule and cost, it is extremely important that everyone needed participates in meetings about interrelated topics to minimize risks, add their contribution and get to know each other.

[edit] Participation during meeting

Often when people give meetings bad reviews, it is because the meeting doesn’t seem relevant to them and/or because they do not know how to participate. People are motivated when purpose/success criteria relate to their role and tasks in a project. Having an important role during the meeting creates a purpose for them to participate, therefore encouraging active participation, delegating actions before, during or after the meeting will encourage participants.

Stated previously, creating a compelling agenda help clearing meeting goal. It is just as important to know how to use the agenda. In some cases, derivatives from the topics on the agenda can be the most valuable part of the meeting. Participants are engaged and new solutions/organizational knowledge is created. In order to do this and still manage a valuable meeting, the manager’s focus needs to be on the output rather than sticking to the agenda. Hall[3] suggests following five questions:


Questions Supporting questions
What outcome do we want on this topic? In order to do what?
What process will we need to deliver this outcome? How do we get there?
Which participants need to be involved? Who will contribute?
How much time is worth spending on this? How much time from schedule can we use on this compare to other tasks?


Rogelberg[6] suggests to experiment with new techniques and locations in order to stimulate participation and ideas. For meetings including many people and where decision making is important, it is sometimes helpful to split the crowd up into smaller groups. Similarly, facilitate meetings where everyone are standing up or in new environments often helps creativity and breaking up habits.

Implementation phase
Encouragement of participation is important throughout all phases. Breaking up with habits in meetings will become relevant if/when people start to lose motivation. If project management pays attention to the outcome of the recurring meetings, needs for changes in style will be easy to discover. Meeting participants can help with acting when they experience that meetings they attend start to lose value.

[edit] Meeting minutes as a strategic tool

Figure 3: Meeting minutes example, inspired from construction industry

Important information and actions from meetings are often stored in minutes and saved in the project management plan.[2] Information kept in minutes follows a structure and is maintained in an organized manner. Minutes can also be used strategically as a “meeting timeline”. For recurring, weekly meetings, such as a project status meeting or steering committee meeting, minutes from the previous week including important concerns, questions and actions can be used as an outcome driven agenda.[9]

See figure 3 as an example inspired by the construction industry.

Implementation phase
Meeting minutes should always be conducted, also when using another structure. When closing project (and after) the meeting minutes can in some cases work as the project library including milestones and real-time project history. In cases where projects end up with lawsuits meeting minutes can become very important legal documents. In more fortunate cases, the project manager needs the minutes during the evaluation.

[edit] Monitor effects

There are several ways to monitor how the application of meeting strategies affects the project’s development.

Survey core group: an open survey with room for respondents to suggest their improvements.

KPI: Key performance indicators can either measure progress or achievement of the operational goal. For monitoring meetings' success when implementing strategies suggested in this article, relevant KPIs include: stakeholder satisfaction (for stakeholder meetings),
project profitability (difference between revenue generated by a project and cost of delivering work), project success rate (percentage of projects delivered on time and under budget)

Pulse-checks: informal, focused conversations with employees to understand how they approach their work.

When to implement The monitoring is important during the planning and executing phase where most activities need to be solved, hence there will be many meetings. The project manager can monitor the progress or use a resource for this task.

[edit] Meetings as a basis for change

Meeting culture can have a great impact on a project and in organizations. If succeeding with creating strategies for meetings in one project, the application in other projects or programs can be considered. A goal for changing meetings is to create a new organizational culture with improved communication, productivity, and integration of the work. Increased job satisfaction and work/life balance is another perk. Therefore, better meetings – better work lives.[8]

Implementation of protocols and changing behaviors take time. Sustaining momentum is an even bigger challenge and can often not be considered as a process but more likely an ongoing activity needing consistent attention. However, if successful there is no reason for the meeting strategy not to scale up and become a supporting act to the organizational strategy.

[edit] Limitations

There are several limitations to the strategies suggested, as meetings vary a lot in different organizations, even within different projects. However, this article deals with well known, generic problems and challenges. Limitations are following:

  • Having too many meetings can be a symptom of a deeper, underlying corporate and cultural belief and practice. Therefore, reducing the number of meetings and sorting meetings in relevance may not improve working conditions for the team. Instead,
    there is a chance that another activity will fill in the new, empty time slot. Too many meetings can be the tip of the iceberg of underlying challenges in an organization, the action of sorting in meetings itself will not resolve this.
  • Working with changing meetings can be costly itself. It may not be suitable for all companies because the revenue created is not directly viewed on the bottom line. At least not in the beginning.
  • Changing meeting culture is a team effort. One manager cannot perform severe changes without support from the team and upper management.

[edit] Annotated bibliography

Project Management Institute. "A Guide to the Project Management Body of Knowledge (PMBOK® Guide)". Fifth edition, 2013[2]

The concept of dividing a project’s life cycle into phases is described in PMBOK as well is the project communications management. Chapter 10 illustrates how communication is planned, distributed and documented. The book contains an investigation of challenges, guidelines, and tools used in project management industry.

Rogelberg, S., Scott, C. Kello, J. “The Science and Fiction of Meetings” 2007[6]

This article evolves around employees spending an increasing amount of time in meetings and also complaining about them. But these employees see meetings as a tool for productivity and there is a need for companies learning to use this tool (meetings) better. The article provides examples and has statistics over how much time is spent in meetings.

Hall, K., Hall, A. "Kill Bad Meetings" 2017[3]

The book is based on industry research as well as the authors own experiences as former CEOs in big organizations. The book aims to improve meeting culture worldwide by providing tools for managers to introduce in their own project and/or organization. The book also covers cross-cultural meetings, dealing with different time zones as well as facilitating a conference: a meeting for a lot of people.

[edit] References

  1. Romanco, N. and Nunamaker, J. (2001). Meeting Analysis: Findings from Research and Practice. Proceedings of the 34th Annual Hawaii International Conference on System Science, p 4. Available at: http://citeseerx.ist.psu.edu/viewdoc/download?doi=10.1.1.570.6650&rep=rep1&type=pdf [Accessed 19 Feb. 2018]
  2. 2.0 2.1 2.2 2.3 2.4 2.5 2.6 2.7 2.8 Project Management Institute. (2013). A guide to the Project Management Body of Knowledge (PMBOK® Guide)- Fifth Edition, Pennsylvania: Project Management Institute, Inc., p.589
  3. 3.0 3.1 3.2 3.3 3.4 3.5 3.6 Hall, K. and Hall, A. (2017). Kill Bad Meetings. London: NB Books, p. 224.
  4. Microsoft.com. (2005). Survey finds workers average only three productive days per week. Available at: https://news.microsoft.com/2005/03/15/survey-finds-workers-average-only-three-productive-days-per-week/ [Accessed 29 Jan. 2018]
  5. Cross, R., Rebele, R., Grant, A. (2016). Collaborative Overload. Harvard Business Review, January-February 2016, p. 74-79. Available at: https://hbr.org/2016/01/collaborative-overload [Accessed 19 Feb, 2018]
  6. 6.0 6.1 6.2 6.3 6.4 Rogelberg, S., Scott, C. Kello, J. (2007). The Science and Fiction of Meetings. MIT Sloan Management Review, Volume 48(2), p. 18-21. Available at: https://orgscience.uncc.edu/sites/orgscience.uncc.edu/files/media/Rogelberg%20et%20al.%20-%202007%20-%20The%20science%20and%20fiction%20of%20meetings.pdf [Accessed 19 Feb, 2018]
  7. Weck, O., Roos, D., Magee, C. (2011). Engineering Systems: meeting human needs in a complex technological world. Cambridge, Massachusetts: Massachusetts Institute of Technology, p. 208.
  8. 8.0 8.1 Perlow, L., Hadley, C., Eun, E. (2017). Stop the Meeting Madness. Harvard Business Review, July-August 2017, p. 62-69. Available at: https://hbr.org/2017/07/stop-the-meeting-madness [Accessed 23 Feb, 2018]
  9. Model inspired by industry practice from construction industry.