Milestones in Project Planning

From apppm
Revision as of 19:01, 2 March 2019 by RikkeK (Talk | contribs)

Jump to: navigation, search

Contents

Abstract

A good and balanced project plan is a crucial success factor for a project, as insufficient resource planning and unrealistic schedules count for 30 % of the reason when looking at why projects fail [1]. There is a wide range of different approaches and tools used for project planning. This article clarifies milestone planning and how to use it in project management.

According to Managing Successful projects with PRINCE2 is a milestone defined as "an event on a schedule which marks the completion of key activities" [2]. Milestones are a tool used in project management to mark the completion of a major phase in a project. Milestone planning is results-oriented and a milestone should present what is supposed to be achieved at a given time in the project. Milestones may influence the way activities in a project are sequenced. Milestones are targets in the project phase, it does not have a duration, but they need to be completed at before a given date. A milestone list for a project is used to estimate activities duration as well as develop the project schedule [3].

This article will contain two main parts, one with a focus on how to set milestones and a second with a focus on how to implement milestones in the project schedule. The first part of this article will also contain an introduction to project planning and milestones in general. While the second part will contain an example of a milestone chart and how to incorporate it in the project schedule displayed in a Gantt chart.

Introduction

Figure 1: The different inputs needed to complete a project schedule. Illustration based on information from A Guide to the Project Management Body of Knowledge (PMBOK® Guide) [3], made by Rikke Louise Kjær Knudsen.

A project schedule is used to obtain a clear overview who and when the project will deliver the products, services or results. According to Project Management: A guide to the Project Management Body of Knowledge (PMBOK guide) Project schedule management consists of six processes [3]:

  • Plan Schedule Management
  • Define Activities
  • Sequence Activities
  • Estimate Activities Durations
  • Develop Schedule
  • Control Schedule

Depending on the size of the project will some of these processes be linked tightly.

There are different scheduling methods, it is the project management team job to determine which method to use, the two most common are critical path or an agile approach. When the project management team has conducted the project-specific data into the six processes, it is possible to create the project schedule by entering the data into a scheduling tool, this is illustrated in figure 1. When a project schedule has been created it should be presented graphically. Often this is done by an Activity list, a Bar/Gantt Chart or a Network Diagram.

Milestone planning

Milestone planning is a way of planning a project on a basis of milestones. A milestone is defined as "an event on a schedule which marks the completion of key activities."[2] Milestones are described as a desired condition or state in the project at a certain point in the timeline of the project. As milestones can be understood by non-experts, is it a good and easy way to keep stakeholders updated and satisfied. As stakeholders can see how the project is developing as more and more milestones are reached [4]. The milestone planning approach differs from traditional project planning, as the focus is on achieving the set goals, instead of executing activities and tasks. When a project is planned from milestones the road to the desired state is not planned. Therefore will it be possible to achieve the state for a milestone in a variety of ways.

When using milestone planning, the mentality of the project team needs to switch from activity-oriented thinking and planning to result-oriented thinking and planning. This is done by answering the question "what should be achieved?" before "how should it be achieved?". The desired results the project management team would like to achieve should be discussed and determined, from this, a milestone plan should be created. A milestone plan should consist of both the desired end result as well as interminate results and indicators.

Milestones in project stages

The milestones have to be decided early in the project stage. The following list contains the phases of project management were milestones figure in.

  1. Starting up a project - Prepare the outline business case.
    Project manager determines the key milestones.
  2. Directing a project
    • Authorize initiation - The project definition is confirmed by the project board. This should include the confirmation of key milestones.
    • Authorize the project - The project plan is validated and the achievability of the project plan and milestones should be approved.
  3. Initiating a project - Create the project plan
    The project is reviewed, the deliverables and predetermined milestones are checked, they should match the project brief.
  4. Controlling a stage - Authorize a work package
    The work there has to be done during the project is set into packages. For each package is the milestones, their tolerances, effort, cost, and end date defined.

How to implement milestones in projects

Annotated bibliography

A Guide to the Project Management Body of Knowledge (PMBOK® Guide), Project Management Institute, 6th Edition - 2017 | Chapter 6

Annotation: The reference is a Standard by Project Management Institute (PMI). Its focus in chapter 6 is Project Schedule Management and tools to manage project schedules. This reference describes which inputs and outputs is needed to develop a project schedule.


Andersen, E. S. (1996). Warning: activity planning is hazardous to your project's health! International Journal of Project Management, 14(2), 89-94.

Annotation: This paper argues against the planning method Network and Activity Planning. The paper focuses on a result-orientated way of planning a project, where milestones are used as results there should be achieved during a project. The writer argues that a project manager does not have the necessary information at the beginning of the project to do activity planning, this often leads to miserable results. While milestone planning makes it possible to wait until til milestone is starting before activities are chosen. This reference does not referee to other references that back up the opinion that activity planning is hazardous to projects. Why the reference not can stand alone.


References

  1. The Standish Group International, Inc. (2015). CHAOS REPORT 2015. [online] Available at: https://www.standishgroup.com/sample_research_files/CHAOSReport2015-Final.pdf [Accessed 1 Mar. 2019].
  2. 2.0 2.1 The Standard for Project Management, Managing Successful Projects with PRINCE2, The Stationery Office Ltd, 6th Edition - 2017 | Chapter 9
  3. 3.0 3.1 3.2 A Guide to the Project Management Body of Knowledge (PMBOK® Guide), Project Management Institute, 6th Edition - 2017 | Chapter 6
  4. Andersen, E. S. (2006). Milestone planning—a different planning approach. Paper presented at PMI® Global Congress 2006—Asia Pacific, Bangkok, Thailand. Newtown Square, PA: Project Management Institute.