Planning Methods - 3 Levels of Project Planning

From apppm
Revision as of 11:33, 19 February 2021 by Jeyad (Talk | contribs)

Jump to: navigation, search

Developed by Jeyad M. Baig

Planning methods is a key feature in Project Management and helps to create an overview and structure in projects[1]. Planning gives the Project Manager control over the amount of time spent on activities, particularly to improve efficiency for a better project schedule. Depending on the specific tasks and their complexity, the planning can be done at 3 different levels: Network Planning, Gantt Chart and Cyclogram Planning.

The 3 project planning methods differentiate in the number of dimensions and represent a sequence of activities (1 dimensional), duration of activities (2 dimensional) and location of activities (3 dimensional). The goal of all 3 planning methods is to show a path from the beginning to the end of the project, but the difference lies in how the path is visualized and planned. The first two planning methods are part of the Critical Path Method (CPM) and the last planning method is Location-Based Scheduling (LBS).

The following article gives an insight into how the 3 Planning Methods benefits Project Management and focus on similarities and differences between the methods depending on the project.


Contents

Background and purpose

Project Planning Methods

Critical Path Method (CPM)

CPM is one of the most common project management scheduling techniques used since it was introduced in the late 1950s[2].

Network Planning 1D

Tasks.png

Gantt Chart 2D

Location-Based Scheduling (LBS)

Cyclogram Planning 3D

Application of the methods

Similarities

Differences

Annotated Bibliography

[3] [4] [5]

References

  1. Barron, M. & Barron, A., Watt A. 8. Overview of Project Planning. Opentextbc.ca. Published August 14, 2014. Accessed February 18, 2021."Overview of Project Planning"
  2. BYG·DTU, Andersson, N., & Christensen, K. (2007). Location-based Scheduling. Vurdering af LBS-metodens anvendelse i byggeprojekter. Technical University of Denmark (DTU). "Location-based Scheduling"
  3. Slate, A. Critical Path Method: A Project Management Essential. Wrike.com. Published 2018. Accessed February 19, 2021. "Critical Path Method"
  4. Mubarak, S. (2010). Construction project sheduling and control. New jersey: Jhon wiley and sons.
Personal tools
Namespaces

Variants
Actions
Navigation
Toolbox