Projects in Controlled Environments, a process-based approach for project management

From apppm
Revision as of 13:14, 15 September 2015 by S150905 (Talk | contribs)

Jump to: navigation, search

Project Management is a field based on a conspicuous level of uncertainty, the use of appropriate methods and tools influences the risk reduction of project failures. In this article we are going to illustrate the so-called PRINCE2 method, focused on process and expenditure control. The implementation of this methodology, apart from pledge to stay on time and within the budget, it is able to ensure a perfect control, coordination and implementation of the project. Making this possible through a close and continuous communication and a high integration for each part of the work. [1]

Contents

Overviews

First established in 1989 by the Central Computer and Telecommunication Agency (CCTA) [1], the second version of this PRoject IN Controlled Enviroment, hence PRINCE2, it is now owned by a stable public authority, the Office of Government Commerce (OGC), and is available free of charge in the public domain. It move its first step in UK standardizing the project management system of the government in order to improve delivery of their services; now it has become a valuable project tool for any type of organization. PRINCE2, apart from allow more efficient control of development resources, it gives controlled management of change by the business (its investment and ROI) and an active involvement of the final product's users throughout its development. This to ensure that the output of the project will meet the functional, service and management requirements of final users[2] [2] [1] [3] [4] [5] [6] [7]

The seven Principles

The method is grounded over seven principles. Everyone of them can be apply to every kind of project, they are also self-validating and they are empowering, so they are able to give at users the capacity to shape the management of the project. The sine qua non condition to turn a project into a PRINCE2 project is to adopt all of these principle to it. These are[8]:

  1. Continued business justification;
  2. Learn from experience;
  3. Defined roles and responsibilities;
  4. Manage by stages;
  5. Manage by exception;
  6. Focus on products;
  7. Tailored to suit the project environment.

Continued business justification

This principle is based on the assumption that a project should not start until it has a worthy Business Case behind, it must be aligned to the business objectives of the organization. A Business Case should be done by first from the moment that it will act as driver for the decision-making processes[8]. From the moment that a project must have continued business justification, if this change (it may occur event that vary the justification itself, for any kind of problem or obstacle encountered during the stages of the project) it’s essential that remain valid anyway. As just said, the Business Case is basic for the business justification of a project, it’s the main way in which the organization can control if the work fulfil this first principle.

Learn from experience

Project management should never consider a project as a new world, as something that can’t be applied to previous experience of the organization. It’s fundamental to learn lesson from the past and use them as a support for future works. Furthermore, it’s essential that every time something unexpected happened, lessons from this need to be recorded and acted upon all the life cycle of project, and used for the future ones: seek opportunities during the work of a project could implement improvement to it.

Defined roles and responsibilities

Projects involved people, PRINCE2 possesses well-defined and agreed responsibilities and roles within an organization structure that involve, together, user, business and supplier stakeholders interest. To ensure a positive output of the project the interests of all the three stakeholders must be represents effectively in the project management. This principle aim to create a solid management team for the project that can put together the various parties involve for the achievement of a common goal. The project, therefore, need to involve the right personalities over the organizations, if it doesn’t happen or if the people don’t understand the role they have each other it will end up in a failure[4]. Creating an effective organizational structure for the project is vital to its success.

Manage by stages

Derived from the consideration that, several time, happen that a project last longer than the time expected and calculate at its very beginning, this principle come also from the necessity to have, during its execution, key point for reviews[8]. These to allow the senior management to control if the progresses follow the prospect and if they are still on the idea of continuing the project. PRINCE2, thus, divided the project into stages; the duration (and, therefore, the number) of which may vary from different works: the shorter they are, they can offer much more control, the longer the can be mean less energy and participation from the board. In this way the management plans only the next stage from the output of the previous one, so to be able to be more specific and lower the risk and the possibility to fail. As outcome of every stage, a plan is presented and the Business Case updated, so to have a project monitored, planned and controlled stage-by-stage[4].

Manage by exception

A PRINCE2 project has specific tolerances for each objective, in order to establish boundary of the authority delegated. The method thus recognized different levels in the project management; each of them has different tolerances within which it can continue to run its power without ask the upper level’s intervention. Is possible to identified tolerances against six limit[8]:

  • Time: plus or minus an amount of time on the target completion dates.
  • Cost: plus or minus an amounts of planned budget.
  •  Quality: plus or minus degrees off a quality target.
  •  Scope: Permissible variation of the plan’s products.
  • Risk: Limits on any individual threats or on the plan’s aggregated risk.
  •  Benefit: plus or minus degrees off an improvement goal.

This principle allow a high reduction of problem referrals or superfluous meetings: as long as any tolerance doesn’t exceed its limit PRINCE2 let a management level to continue its work. The next level is involved only when there is a forecast of a tolerance being exceeded.

Focus on products

The product is the core of the project: every aspects from planning, risk management, responsibilities, configuration of the management, to control and quality requirement are product-based. Following this principle, a project need to be output-oriented instead of activity-oriented. Its purpose has to be to meet the interest and the expectation of the different stakeholders, together with the business justification. In order to make this possible a mutual awareness of the entire products required and them quality prospect is essential. The lack of such a fundamental principle can led the project to major risk like rework, uncontrolled change and user dissatisfaction.

Tailored to suit the project environment

PRINCE2 is a method tailored to suit all project’s aspects. The action of adapt the method to the specific situation thus has to be undertaken before its launch. The principle aim to ensure that the project management actions are associated to the specific environment where it takes place, and the project controls are built around its complexity, scale, competence, importance and risk. This assure the universal attitude of PRINCE2: it can be used for any project from the moment that the method is designed to be tailored to its specific needs[4].

The Structure

The method itself is form by three main parts[2]:

  • PRINCE2 offer a set of Processes that make its user able to have control over every stage of the project;
  • It possesses seven Themes that explain its way of acting throughout all the aspects of the project;
  • This method do not put emphasis on which Techniques need to be used; it offers only few of them and them use is optional, making exception for the “product-base planning” one.


Process

Thinking about a process as a structured set of activities design to accomplish a specific purpose[4], hence the process model consist in the main part of PRINCE2. It takes the user from the very beginning to the conclusion of the project through each stage of which is made of. [3] The structure sketch by processes are not linear: some of them will run in parallel and, very often, a block it’s repeated to ensure the better output possible. All of them are aligned to the management level of programming, directing, managing and delivering. Every project using PRINCE2 must to address to all the processes in some form. Doing so the main action is not to used them as standard ones, but tailoring each of them to the specific work environment. The steps of project management are defined by these processes:

Starting Up a Project

The purpose of this firs process is to ensure to have a viable and worthwhile project to work on, to find, thus, if it possess all the prerequisites it need to be opened. The activities of Starting Up are to[2]:

  • Appoint the Executive and the Project Manager who will form the PM team - the Executive should have strong links with the Board, he also might be part of it - this is essential to create the ideal working environment;
  • Understand if previous experiences in other projects might be applied to the new one for preventing possible mistakes;
  • Identifies the approach that will be used to evaluate the stage of the project and to find solutions to be provided to problems: the project approach will shape the duration and the costs of the project as well as its quality;
  • Prepare the Business Case in order to ensuring the the expense if the project is justified.
  • Identifies the customer’s quality expectations;
  • Create a Risk Log and fill it in with any risks already known or discovered;
  • Plan the initiation stage: this to create the foundation of the project and to prepare the document to get the approval for its start.

Initiating a Project

This process has purpose to understand the work that will be done to delivered the project’s outcome before committing to a weighty spend, the benefits that are expected from it and the associated risks. It need to ensure the all parties intended to achieve a common goal and how to achieved that specific goal, doing so, this process lay down the basis for a successful project. Initiating a Project is the union of different activities such as:

  • The definition of the strategy to cover the quality reviews and how it has to be made;
  • The plan for the project in its entirety, so when and how its outcomes will be delivered and at what cost, and how communication between all the interested actors will be established;
  • The definition of the people to be involved in the decision making and problem solving actions;
  • The outline of how every project’s progress will be checked and monitored;
  • The tailoring of corporate project management method for suiting the project.

This process end up with the draft of the Project Initiation Documentation, a collection of document that will be used in future stage to compare the performance against the original expectation.

Directing a Project

The process is aimed to the senior management team which are the final decision-makes[2]. It is, thus, really important that levels of authority need to be undoubtedly identified. Its purpose is to enable project board to be responsible for the project’s success while delegating day-to-day management to project manager: it has to authorized every step of the project (from the initial business justification to the control end of the work) and to direct and monitor it throughout its life so to assure its viable nature. PRINCE2 help the board doing so by adopting the principle of Management by exception: it control by a limited number of predetermined decision point, and they are inform from the lower level of exception that might occur. This process start as a conclusion of starting up and runs until its completion and it does[2]:

  • Authorization for project initiation;
  • Provides connection between corporate and program management;
  • Advises the Project Manager of any external business events that could cause variation in the project;
  • Approves Stage Plans and its conclusion;
  • Decides on changes to approved products;
  • Approves possible Exception Plans;
  • Gives ad hoc advice, in addition to direction, during the project;
  • Safeguards the customer’s interests as well as the one of the supplier;
  • Approves project closure.

Controlling Stage

This process aim to manage every stage from its approval to the completion. It assigns works and monitor them, and it face possible problem taking corrective actions towards them and, finally, report progresses to the Board. Controlling Stage guarantees that every work come together with its quality expectation, and its target, delivery and reporting dates. Every possible predictable source of issues is here checked. Furthermore, the process gathers information to update the plan for next stages in order to follow the actual progress and its connected quality. The final object of the process is to produce highlight report to be seen by the project board, thus to eliminate futile meetings.

Managing Product Delivery

Under the responsibility of the team management, this process agrees with work requirement with the project manager and actually does the work. It must report about progress and quality checking and when it has been accomplished the process need to confirm if it had respect the expectations.

Managing a Stage Boundary

It basically ensures that the approval for passing to the next stage subsist or if it necessary to open an exception plan; therefore it has to provide to the Board evidence for the ongoing viability of the project. It does so by enabling the Board to be provided with essential information from the project manager. So to review the correct execution of the current stage and to approve the stage after, confirming the business justification and risks’ tolerability. It can happens that a stage had exceeded the tolerance, here the Board may ask to repeat the same stage with a different planning from the original one. While if everything went properly the process need to prepare the plan for the next stage.

Closing a Project

When the project manager together with customer and supplier agreed that the project has accomplish all the objectives set out in the initial stage, it must be brought to a reasoned close. In this final process it’s checked if all the products required have been successfully delivered and if the first objectives have been met; it also reviews if and how the final performance differ from the original idea. The project close with the transfer of the ownership of the outcome to the customer, and expiration of the project management team responsibility.

Themes

What give strength to this method is the specific treatment that it provides to themes: they are wisely conceived to link together in the most effective way possible, and, consequently, all seven al always integrated. The actions of every themes involve almost every process of PRINCE2. As said before also in the case of themes they must be addressed to every specific project in a proper way, hence appears again the concept of tailoring according to specific characteristic ( scale, complexity and nature of the enviroment).

Business Case

Is the instrument used to continuously verify if the project possesses the request viability, prestige it had in its first steps. It ensure that the work remain achievable, in order to support for decision-making and its continued investment[4]: it has to be worth doing. The Business Case, as management products, is one of the most significant and it owns to the project Board. It outlines the reason behind a project, it foresees expected costs and benefits and it whole timescale; PRINCE2, following it product-based nature, focusses on the costumer’s Business Case. It also underline the main risks that the project might meet. On its inside it comprehends a document which explain when benefits will be measured, how and by whom. This need to be review firstly at the start of the project, at every stage boundaries and lastly at the project conclusion. Thus to constantly check if the work can to be justified.

Organization

This theme is aligned with “Defined roles and responsibilities” principle - as already said, build an effective organizational structure able to maintain its power throughout the project’s life, is fundamental for the success of a project. A project’s organization must represents the interest of the three parties involved: the business, the User and the Supplier [IMMAGINE PAGINA 32 MANAGING SUCCESFULL]. It also need to put together an effective strategy to manage the flow of communication between the three stakeholders. A PRINCE2 typical organization if made up by these figures:

  • Project Boar that provide and handle all the final decision-making power, therefore it’s responsible for the success of the project. The board approves every major plans and them possible deviations. Here the Executive, together with the Senior User and the Senior Supplier, are the principal responsibles for the project.
  • project manager
  • team manager
  • project assurance

Plans

Progress

Risk

Quality

Change

Techniques

PRINCE2 techniques are not mandatory. A company may already have, e.g., a quality checking technique, which it wishes to use in preference to the PRINCE2 quality review. Although it actually does not give more information about which technique to use and when, it put emphasis on two of them:

Product-base planning

It affirm that all the activities wich form a project are to be built upon the idea of the required product. This technique required the construction of a Product Breakdown Structure[2], which capture the hierarchy of the products that the project required to produce: on its top there is the final output of the project, and at every lower stage there are all the constituent parts of it, from the most important to the units. Product-based planning has three components:

  • Product Breakdown Structure: hierarchical structure of all the products that need to be produce or needed by the plan, at the top of which there is the final outcome;
  • Product Descriptions: every step in the previous hierarchical structure need a proper description of the product itself which underline its purpose, composition, the quality criteria and the quality method that need to be applied to it, and the derived products necessary for its construction. The description’s draft forces the management to consider if there is a sufficient knowledge to produce the product, and moreover, is a vital checklist to be used for the quality check of each stage.
  • Product Flow Diagram: map of the sequence in which the products have to be produced and the dependencies between them. It is the stage after the Product Breakdown Structure.

Quality Review

This technique doesn’t belong to this method but it’s one of the very few which PRINCE2 give information about. Quality review is based on fixed meeting that aim to find possible errors, and it does that through the check of paper-based output such as reports [3]. It is a team structured method of reviewing products by running a meeting on the review to ensure that all expectations are properly covered.   The technique made this possible by inspections of products in a planned, independent, controlled and documented manner and ensure that any errors are found as early as possible and are fixed[2]. As an indirect consequence, the quality review also spread knowledge of the product among those whose own products may interact with it.

Pros and cons

The truly generic nature of PRINCE2 it’s the first aspect that makes it one of the most used method in project management. This can be used for helping any type of project, no metter its dimension, its organization, its culture or geography. This is made possible through a focus of the proper aspect of the project itself and not to the management’s ones: the specialist aspect run in parallel and in integration with the method but they don’t affect directly it. This attribute give to the method the ability to be used, by any organization, as a standard to improve their maturity and capability over several areas of their business, from R&D to IT and so on. [4] PAG.23 succp

References

  1. 1.0 1.1 1.2 € Prince2 100 Success Secrets - The Missing Foundation and Practitioner Exam Training, Certification and Project Management Guide, 2008, Gerard Blokdijk, Emereo Pty Limited.
  2. 2.0 2.1 2.2 2.3 2.4 2.5 2.6 2.7 € PRINCE2™ A Pratical Handbook (Third Edition), 2010, Colin Bentler, Elsevier Ltd.
  3. 3.0 3.1 3.2 € PRINCE2 For Dummies, 2010, Nick Graham, Wiley.
  4. 4.0 4.1 4.2 4.3 4.4 4.5 4.6 € Managing Successful Project with PRINCE2™, 2009, Office of Government Commerce, TSO.
  5. ------Agile project management: running PRINCE2™ projects with DSDM™ Atern™, 2007, Keith Richards, ‎OGC - Office of Government Commerce, ‎Eksempelvisning.
  6. ---------Improving project performance using the PRINCE2 maturity model, 2007, Andy Murray, ‎Mike Ward, ‎Eksempelvisning.
  7. € Project Management with PRINCE2 Best Practice Handbook: Building, Running and Managing Effective Project Management - Ready to use supporting documents bringing PRINCE2 Theory into Practice, 2008, Jeff Reed, Emereo Publishing.
  8. 8.0 8.1 8.2 8.3 € PRINCE2™ Revealed (Second Edition), 2010, Colin Bentler, Elsevier Ltd.