Risk Register Analysis

From apppm
(Difference between revisions)
Jump to: navigation, search
(Responsibilities)
(Introduction)
Line 2: Line 2:
  
 
== Introduction ==
 
== Introduction ==
A risk register consists of three main elements. First and foremost it consists of the risk, secondly, it consists of the cause of the risk, and third it consist of the action of the risk. When building up a risk register these three elements will be covered by the following 4 steps. The first step is called the '''Identify''' phase. Here all possible risk will be identified. The second step is called the '''Assess''' phase. The possible risks identified must be evaluated regarding probability and impact on the PPP. The third step is called the '''Plan''' phase. The management response is planned to ensure the if a risk materializes, the PPP is not taken by surprise. The fourth step is called the '''implement''' phase. The risk register is implemented in the organization and response actions is monitored to ensure the correct line of actions is carried out. During the lifetime of a PPP, the risk register should be evaluated to ensure that new risk has not arrived, or already known risk has now changed.  
+
A risk register consists of three main elements. First and foremost it consists of the risk, secondly, it consists of the cause of the risk, and third it consist of the action of the risk. When building up a risk register these three elements will be covered by the following three steps. The first step is called '''Identify'''. Here all possible risk will be identified. The second step is called '''Assess'''. The possible risks identified must be evaluated regarding probability and impact on the PPP. The third step is called '''Plan'''. The management response is planned to ensure the if a risk materializes, the PPP is not taken by surprise.  
It is important that threats and opportunities are communicated to stakeholders. This is a continuous process during the lifecycle of the PPP, to ensure that every one involved knows how to respond if a risk materializes.
+
During the lifetime of a PPP, the risk register should be evaluated to ensure that new risk has not arrived, or already known risk has now changed. The register should as a minimum be evaluated just before the starting of a new phase of the PPP. 
 +
It is important that threats and opportunities are communicated to stakeholders. This is a continuous process during the lifecycle of the PPP, to ensure that everyone involved knows how to respond if a risk materializes.
  
 
== Identify ==
 
== Identify ==

Revision as of 21:51, 15 February 2018

Simple risk analisys.jpg
A Risk Register is a tool to keep track of risks to a "project, program or portfolio"(PPP). It is commonly used by the risk manager to maintain the simplest structure of possible events but can be used on every level of "project, program and portfolio management"(PPPM). The Risk register describes possible threats and opportunities to a PPP. [1] The simplest risk register consists of the cause of a risk, the event of a risk, and the effect of a risk. The register can be expanded to include the information critical to the PPP. The level of information is highly related to the scale of the PPP, where large complex PPP tends to have more information included in the risk register, then smaller and simpler project. The main reason for having a risk register is to have a standing register with action plans already established for known possible risk. If a risk occurs, the risk manager or risk owner(explained in the Implement section) can take action fast and effective to remove or reduce threats or maximize opportunities.

Contents

Introduction

A risk register consists of three main elements. First and foremost it consists of the risk, secondly, it consists of the cause of the risk, and third it consist of the action of the risk. When building up a risk register these three elements will be covered by the following three steps. The first step is called Identify. Here all possible risk will be identified. The second step is called Assess. The possible risks identified must be evaluated regarding probability and impact on the PPP. The third step is called Plan. The management response is planned to ensure the if a risk materializes, the PPP is not taken by surprise. During the lifetime of a PPP, the risk register should be evaluated to ensure that new risk has not arrived, or already known risk has now changed. The register should as a minimum be evaluated just before the starting of a new phase of the PPP. It is important that threats and opportunities are communicated to stakeholders. This is a continuous process during the lifecycle of the PPP, to ensure that everyone involved knows how to respond if a risk materializes.

Identify

Assess

Plan

Communicate

References

  1. Managing Successful Projects with PRINCE2. http://proquestcombo.safaribooksonline.com.proxy.findit.dtu.dk/9780113310593
Personal tools
Namespaces

Variants
Actions
Navigation
Toolbox