==Abstract==
+
''Developed by Johannes Michael Bührmann''
'''''WORK IN PROGRESS'''''
+
:''main article: [http://apppm.man.dtu.dk/index.php/Risk_management Risk Management]''
+
Since risk analysis is a subpart of risk management, several correlations will be present between the two.
+
This article will attempt to describe different approaches to analysing the risk when managing projects, portfolios and programs.
+
  
Several tools will be mentioned and explained briefly, but (in order to allow the full use of the wiki) not be described in detail.
+
:main article: [http://apppm.man.dtu.dk/index.php/Risk_management Risk Management]
 +
==Summary==
  
Risk analysis essentially chooses the most appropriate method(s) for calculating the given information and delivers a collective overview of the situation, as an artisan chooses the right tool for the job and produces the individual parts for the product. Using “known knowns” and “known unknowns” '' (from [http://apppm.man.dtu.dk/index.php/The_Cynefin_Framework the Cynefin framework]) '' along with estimates made by either extrapolation based on prior knowledge or by experts, the analysis generates a better understanding enabling the user to conduct a valid risk evaluation.
+
This article will describe the element of risk analysis within risk management, what it is used for and list several elements which can be used in the process of managing risk in projects, portfolios and programs..  
 +
Since risk analysis is a subpart of [http://apppm.man.dtu.dk/index.php/Risk_management Risk Management], several correlations might be present between the two.
  
==Definition==
+
Several methods used for Risk Analysis will be mentioned and explained briefly, but (in order to allow the full use of the wiki) not be described in detail. Some of them might not seem directly applicable but can all be used during the possible iterations within the analysis.
Before defining risk analysis the understanding of risk as a term needs to be established. Risk is mostly defined as a probability of losing something of a specific value, mathematically speaking; the probability of the event occurring multiplied by the potential value-loss = the risk.
+
  
In order to compute this risk the analysis must receive information on the probability and the value of the potential loss. Looking at the definition of risk analysis, the ISO Guide 73-2009 states that it is the ''“Process to comprehend the nature of risk and to determine the level of risk”'' and the ISO 31000 standard describes it as the process which ''“provides an input to risk evaluation and to decisions on whether risks need to be treated, and on the most appropriate risk treatment strategies and methods” ''.
+
The user of risk analysis essentially choose the most appropriate method(s) for calculating the given information and delivers a collective overview of the situation, as an artisan chooses the right tool for the job and produces the individual parts for the product. Using “known knowns” and “known unknowns” '' (from [http://apppm.man.dtu.dk/index.php/The_Cynefin_Framework the Cynefin framework]) '' along with estimates made by either extrapolation based on prior knowledge or by experts, the analysis generates a better understanding enabling the user to conduct a valid risk evaluation.
  
Both are correct since the process mentioned is the computational part of risk management where different aspects, variables and factors are used to estimate the risk involved with a specific feature, action, decision, condition etc. The outcome of this computation is a quantified number or percentage which can then be used as an evaluation criterion, determining either which option to select or if it is safe to proceed down the investigated path.
+
==Definition==
 +
[[File:Risk Analysis from ISO31000.JPG|500px|thumb|right|Risk Analysis]]
 +
Risk analysis lies at the heart of [http://apppm.man.dtu.dk/index.php/Risk_management Risk Management] and functions very much like the Central Processing Unit (CPU) of a computer.
  
==Main features of risk analysis==
+
The term "Risk" is most often defined as a probability of losing something of a specific value.
There are three different analysis method groupings within risk analysis; Qualitative, Semi-quantitative and quantitative.
+
Mathematically speaking; the probability of an event occurring multiplied by the potential value-loss = the risk.
  
*Qualitative:
+
In order to compute this risk the person(s) doing the analysis must as a minimum receive information on the probability of an event occurring and the value of the potential loss.
 +
The definition of risk analysis, as defined by the International Organisation for Standardization is as follows:
  
Qualitative analysis methods are based on opinions and estimates. They compute the risk scenario based on few numbers and many interpretations. Outcome of these methods are usually given in levels of significance like “high”, “medium” and “low” or other word scales which are not specifically determining any actual number.
+
In their [http://www.iso.org/iso/catalogue_detail?csnumber=44651 ISO Guide 73-2009], it is stated as the ''“Process to comprehend the nature of risk and to determine the level of risk”''
 +
In the [http://www.iso.org/iso/catalogue_detail?csnumber=43170 ISO 31000] standard it is described as the process which ''“provides an input to risk evaluation and to decisions on whether risks need to be treated, and on the most appropriate risk treatment strategies and methods” ''.
  
*Semi-quantitative:
+
Both are correct since the process mentioned is the computational part of [http://apppm.man.dtu.dk/index.php/Risk_management Risk Management] where different aspects, variables and factors are used to estimate the risk involved with a specific feature, action, decision, condition etc. The outcome of this computation is a quantified number or percentage which can then be used as an evaluation criterion, determining either which option to select or if it is safe to proceed down the investigated path.
  
The outcomes of the semi-quantitative analysis methods are based on numeric ratings using evaluation scales for probability and consequence and usually combining them using a formula, resulting in a comparable value for the risk level.  
+
==Main features of risk analysis==
 +
There are three different analysis method groupings within risk analysis; Qualitative, Semi-Quantitative and Quantitative.
  
*Quantitative:
+
;Qualitative:
 +
:Qualitative analysis methods are based on opinions and estimates. They compute the risk scenario based on few numbers and many interpretations. Outcome of these methods are usually given in levels of significance like “high”, “medium” and “low” or other "word scales" which are not specifically determining any actual number. An example of a qualitative result is the risk of terror when travelling abroad, made by the ministry of foreign affairs.
  
The quantitative analysis uses estimates of probability and consequence values to generate an approximation of the risk involved, represented by one specific value. The specific values, depending on the method of gathering, from different analysis can then be combined into one overall risk factor.
+
;Semi-quantitative:
----
+
:The outcomes of the semi-quantitative analysis methods are based on numeric ratings using evaluation scales for probability and consequence and usually combining them using a formula, resulting in a comparable value for the risk level.
As risk analysis works like a processor it needs to receive some information as input before it can calculate an output which depicts reality.
+
 
+
These input are:
+
----
+
:Purpose
+
The purpose is the reason for analysing the risk; it assists with determining the boundaries of the analysis.
+
 
+
:Type of risk
+
Choice of models depends on the type of risk in question.
+
 
+
:Information available
+
Determines whether it is possible to conduct the analysis right away or information has to be gathered.
+
 
+
:Existing control features
+
 
+
:Consequences
+
The consequences can be both positive and negative, and reflect the impact of events defined in the analysis
+
 
+
:Likelihood / Probabilities
+
 
+
:Risk criteria
+
 
+
:Effectiveness of existing control features
+
  
:Causes of risk
+
;Quantitative:
 +
:The quantitative analysis uses estimates of probability and consequence values to generate an approximation of the risk involved, represented by one specific value. The specific values, depending on the method of gathering, from different analysis can then be combined into one overall risk factor.
  
:Sources of risk
 
  
:Factors influencing any of the above
 
Weights which scale the severity of the quantities are part of this input, as well as uncertainties and sensitivities.
 
  
:Interrelations / Interdependence
+
Because risk analysis works much like the processor in a computer it needs to receive a minimum of information as input before it can calculate an output which allows the user to gain a better overview and basis for making changes or taking decisions. A risk analysis is often generated for the sake of factual argumentation and credibility of decisions.
The network of relational aspects between different risks
+
Normally input are generated in the step before the analysis; "Risk identification" but some can also be derivatives generated during the analysis. Many of the models described later can be used to generate input during the identification stage.
 +
Output of the analysis step is usually used within the "Risk evaluation" in order to understand the risk in question.
  
 +
{| class="wikitable"
 +
|+Risk Analysis
 +
|-
 +
|'''Input:'''
 +
|'''Output:'''
 +
|-
 +
|;Purpose
 +
:The purpose is the reason for analysing the risk; it assists in determining the boundaries of the analysis.
 +
|rowspan="4"|;Assessment of the risk with the following aspects
 +
:Description of methods used and known control features impact on the risk
 +
:Combined Likelihood / probability depending on the description of original risk
 +
:Consequences of different scenarios
 +
|-
 +
|;Type of risk
 +
:Choice of models depends on the type of risk in question.
 +
|-
 +
|;Information available
 +
:Determines whether it is possible to conduct the analysis right away or information has to be gathered.
 +
|-
 +
|;Existing control features
 +
:The features that are already in place to influence the risk and outcome of the analysis.
 +
|-
 +
|;Effectivity of existing control features
 +
:How effective the control features are. This information can also reveal if there is room for improvements.
 +
|rowspan="4"|;Description of the confidence in:
 +
:The assessment of the risk (the result of the analysis)
 +
:The sensitivity of the result to preconditions and assumptions
 +
:Information Uncertainty
 +
:Information Availability
 +
:Information Quality
 +
:Information Quantity
 +
:Ongoing relevance of information (how relevant will the analysis be in the future)
 +
|-
 +
|;Consequences
 +
:The consequences can be both positive and negative, and reflect the impact of events defined in the analysis.
 +
|-
 +
|;Likelihood / Probabilities
 +
:Estimates, guesstimates, statistics and assumptions on the probability of an event happening.
 +
|-
 +
|;Risk criteria
 +
:Terms against which the risk significance is evaluated, often based on context (internal/external) and objectives of the organisation.
 +
|-
 +
|;Causes of risk
 +
:The reasons why an event takes place.
 +
|rowspan="4"|;Limitations
 +
:Demarcation description.
 +
|-
 +
|;Sources of risk
 +
:The objects which affects the risk.
 +
|-
 +
|;Factors influencing any of the above
 +
:Weights which scale the severity of the quantities are part of this input, as well as uncertainties and sensitivities.
 +
|-
 +
|;Interrelations / Interdependence
 +
:The network of relational aspects between different risks
 +
|}
  
Output:
 
 
----
 
----
:Assessment of the risk with the following aspects
 
  
::Description of methods used and known control features impact on the risk
 
  
::Combined Likelihood / probability depending on the description of original risk
 
  
::Consequences of different scenarios
 
  
:Description of confidence in:
 
::The assessment of the risk (the result of the analysis)
 
  
::The sensitivity of the result to preconditions and assumptions
 
 
::Information Uncertainty
 
 
::Information Availability
 
 
::Information Quality
 
 
::Information Quantity
 
 
::Ongoing relevance of information
 
 
:Limitations
 
  
 
==Benefits of analysing risk==
 
==Benefits of analysing risk==
 +
Analysing risk has become an integrated part of working with forecasts as well as decisions in projects, programs and portfolios, simply because it generates the big picture needed to make an informed decision.
 +
The drivers of analysing risk are the focus on lowering costs and expenses, avoiding loss of anything valuable and reducing variability in outcomes.
 +
The reason why risk is analysed with so many different methods to choose from, is because several different categories of risk exist, and yet there is a universal consensus that risk is best avoided, mitigated, minimised or negated.
  
==Different models used when analysing risk==
+
==Models used in order to analyse risk==
The following models are all described in Annex B of the ISO 31010 standard.
+
All but one of the following models are described in Annex B of the ISO 31010 standard.
 
+
  
 
*'''[http://en.wikipedia.org/wiki/Brainstorming Brainstorming]:'''
 
*'''[http://en.wikipedia.org/wiki/Brainstorming Brainstorming]:'''
Brainstorming is a very intuitive method which uses associations and connections made by possibly several people around a central subject to uncover problematic and opportunistic aspects affecting the subject. This qualitative information is then used to gather as much quantitative information as possible in order to complete the further analysis.
+
::Brainstorming is a very intuitive method which uses associations and connections made by possibly several people around a central subject to uncover problematic and opportunistic aspects affecting the subject. This qualitative information is then used to gather as much quantitative information as possible in order to complete the further analysis. It can e.g. be used to imagine future risks or possible control features to known risks.
 
+
  
 
*'''[http://en.wikipedia.org/wiki/Structured_interview Structured] or [http://en.wikipedia.org/wiki/Semi-structured_interview semi-structured] interviews:'''
 
*'''[http://en.wikipedia.org/wiki/Structured_interview Structured] or [http://en.wikipedia.org/wiki/Semi-structured_interview semi-structured] interviews:'''
The structured or semi-structured interview can be used for gathering information from numerous sources. These interviews do not have to be done face to face since questionnaires are also considered within this model.
+
::The structured or semi-structured interview can be used for gathering information from numerous sources. These interviews do not have to be done face to face since questionnaires are also considered within this model. Applicable in the phases before and after Risk Analysis.
 
+
  
 
*'''[http://en.wikipedia.org/wiki/Delphi_method Delphi technique]:'''
 
*'''[http://en.wikipedia.org/wiki/Delphi_method Delphi technique]:'''
The Delphi technique is essentially a brainstorming process where the participants are kept anonymous but are able to see the collected work of all participating in the process. It is used to reach some kind of consensus around the subject in question.
+
::The Delphi technique is essentially a brainstorming process where the participants are kept anonymous but are able to see the collected work of all participating in the process. It is used to reach some kind of consensus around the subject in question. Applicable in the phases before and after Risk Analysis.
  
 +
*'''Check-lists:'''
 +
::Check-lists are built from previous experiences and often list known risks, control features and/or hazards gathered through prior assessments or lessons learned.
  
:'''Check-lists:'''
+
*'''[http://en.wikipedia.org/wiki/Hazard_analysis Preliminary hazard analysis (PHA)]:'''
Check-lists are built from previous experiences and often list known risks, control features and/or hazards gathered through prior assessments or lessons learned.
+
::PHA is used when there is little information available and as the name states normally in the beginning of e.g. a project, in order to uncover potential hazards influencing the further development.
  
----
+
*'''[http://en.wikipedia.org/wiki/Hazard_and_operability_study Hazard and operability study (HAZOP)]:'''
:'''[http://en.wikipedia.org/wiki/Hazard_analysis Preliminary hazard analysis (PHA)]:'''
+
::HAZOP is a qualitative method which studies the current activities in order to access the risk involved. It usually examines existing operations like procedures and products as well as processes and the system around them.
PHA is used when there is little information available and as the name states normally in the beginning of e.g. a project, in order to uncover potential hazards influencing the further development.
+
  
----
+
*'''[http://en.wikipedia.org/wiki/Hazard_analysis_and_critical_control_points Hazard analysis and critical control points (HACCP)]:'''
:'''[http://en.wikipedia.org/wiki/Hazard_and_operability_study Hazard and operability study (HAZOP)]:'''
+
::HACCP is mainly used in the industry which produces items for consumption where infections are of vital importance. The critical control points are then indicating areas within the production where errors can lead to loss of quality or worse.
HAZOP is a qualitative method which studies the current activities in order to access the risk involved. It usually examines existing operations like procedures and products as well as processes and the system around them.
+
  
----
+
*'''Toxicity assessment:'''
:'''[http://en.wikipedia.org/wiki/Hazard_analysis_and_critical_control_points Hazard analysis and critical control points (HACCP)]:'''
+
::Toxicity assessment is used when looking at risk related to the environment and how the introduction of a source of harm affects it.
HACCP is mainly used in the industry which produces items for consumption where infections are of vital importance. The critical control points are then indicating areas within the production where errors can lead to loss of quality or worse.
+
  
----
+
*'''[http://en.wikipedia.org/wiki/Structured_What_If_Technique Structured “What-If” Technique (SWIFT)]:'''
:'''Toxicity assessment:'''
+
::SWIFT is normally used at workshops by the facilitator to make the participants introduce risk into their chain of thought by using a set of specific questioning words along with the catchphrase “what if?” .  
Toxicity assessment is used when looking at risk related to the environment and how the introduction of a source of harm affects it.
+
  
----
+
*'''[http://en.wikipedia.org/wiki/Scenario_analysis Scenario analysis]:'''
:'''[http://en.wikipedia.org/wiki/Structured_What_If_Technique Structured “What-If” Technique (SWIFT)]:'''
+
::When conducting a scenario analysis, one or several future scenarios are developed based on the participants’ thoughts and ideas on where the future might bring us. Then doing back-casting in order to determine the events needed to reach the scenario and evaluating the risks of these events.
SWIFT is normally used at workshops by the facilitator to make the participants introduce risk into their chain of thought by using a set of specific questioning words along with the catchphrase “what if?” .  
+
  
----
+
*'''Business impact analysis (BIA):'''
:'''[http://en.wikipedia.org/wiki/Scenario_analysis Scenario analysis]:'''
+
::The BIA investigates the risks capable of disrupting the organisation’s operations as well as the current controls in place and how well they will handle the disruption.
When conducting a scenario analysis, one or several future scenarios are developed based on the participants’ thoughts and ideas on where the future might bring us. Then doing back-casting in order to determine the events needed to reach the scenario and evaluating the risks of these events.
+
  
----
+
*'''[http://en.wikipedia.org/wiki/Root_cause_analysis Root cause analysis (RCA)]:'''  
:'''Business impact analysis (BIA):'''
+
::RCA is often used after an event has taken place with the aim of preventing it from happening again.
The BIA investigates the risks capable of disrupting the organisation’s operations as well as the current controls in place and how well they will handle the disruption.
+
::By constantly questioning for the reason why an event occurred, turning the reason into an event and repeating the question the RCA attempts to discover the fatal event which set several chains of actions into motion.
  
----
+
*'''[http://en.wikipedia.org/wiki/Failure_mode_and_effects_analysis Failure modes and effects analysis (FMEA)] / [http://en.wikipedia.org/wiki/Failure_mode,_effects,_and_criticality_analysis failure modes and effects and criticality analysis (FMECA)]:'''
:'''[http://en.wikipedia.org/wiki/Root_cause_analysis Root cause analysis (RCA)]:'''  
+
::FMEA is essentially an error tool attempting to map out the different possible ways for processes, systems or components are able to fail and thus not fulfil the designed purpose.
RCA is often used after an event has taken place with the aim of preventing it from happening again.
+
::FMECA expands FMEA by ranking the outcomes against each other and thereby identifying the most critical failures.
By constantly questioning for the reason why an event occurred, turning the reason into an event and repeating the question the RCA attempts to discover the fatal event which set several chains of actions into motion.
+
  
----
+
*'''[http://en.wikipedia.org/wiki/Fault_tree_analysis Fault tree analysis (FTA)]:'''
:'''[http://en.wikipedia.org/wiki/Failure_mode_and_effects_analysis Failure modes and effects analysis (FMEA)] / [http://en.wikipedia.org/wiki/Failure_mode,_effects,_and_criticality_analysis failure modes and effects and criticality analysis (FMECA)]:'''
+
::FTA is a method used to develop your typical trouble shooting guide where it is possible to locate the cause of an undesired event by deductive reasoning.
FMEA is essentially an error tool attempting to map out the different possible ways for processes, systems or components are able to fail and thus not fulfil the designed purpose.
+
FMECA expands FMEA by ranking the outcomes against each other and thereby identifying the most critical failures.
+
  
----
+
*'''[http://en.wikipedia.org/wiki/Event_tree_analysis Event tree analysis (ETA)]:'''
:'''[http://en.wikipedia.org/wiki/Fault_tree_analysis Fault tree analysis (FTA)]:'''
+
::ETA can be used to generate the probability of the control features working or not working with regards to a specific event happening. Contrary to the FTA, the ETA can be used before the event has actually happened as a hypothetical reasoning method. It can be used both quantitative and qualitative.
FTA is a method used to develop your typical trouble shooting guide where it is possible to locate the cause of an undesired event by deductive reasoning.
+
  
----
+
*'''Cause-consequence analysis:'''
:'''[http://en.wikipedia.org/wiki/Event_tree_analysis Event tree analysis (ETA)]:'''
+
::Cause-consequence analysis is combining FTA and ETA in order to analyse the various paths possible within a system following a critical event. It is used within critical safety systems as a reliability tool.
ETA can be used to generate the probability of the control features working or not working with regards to a specific event happening. Contrary to the FTA, the ETA can be used before the event has actually happened as a hypothetical reasoning method. It can be used both quantitative and qualitative.
+
  
----
+
*'''[http://en.wikipedia.org/wiki/Ishikawa_diagram Cause-and-effect analysis]:'''
:'''Cause-consequence analysis:'''
+
::Cause-and-effect analysis identifies potential causes of an event or problem by looking at the possible contributing factors and organising them in either a fishbone or tree diagram in order to consider all possible hypotheses.
  
 +
*'''Layers of protection analysis (LOPA):'''
 +
::LOPA analyses if the required control features are present to mitigate an undesired event or scenario. It is a semi-qualitative method used to provide a baseline when specifying independent protection layers.
  
----
+
*'''[http://en.wikipedia.org/wiki/Decision_tree Decision tree analysis]:'''
:'''[http://en.wikipedia.org/wiki/Ishikawa_diagram Cause-and-effect analysis]:'''
+
::Decision tree analysis can be used as a forecast tool, assisting the decision makers with understanding the consequences and follow-up decisions to an initial event. It resembles a tool usable for career path decisions where you start with a lot of options and by deciding on one path, still having several options open.
  
----
+
*'''[http://en.wikipedia.org/wiki/Human_reliability Human reliability assessment (HRA)]:'''
:'''Layers of protection analysis (LOPA):'''
+
::HRA is mainly used to evaluate the human influence on performance of systems or the human error factor.
 +
::It is usable both quantitatively and qualitatively.
  
----
+
*'''[http://en.wikipedia.org/wiki/Bowtie_(sequence_analysis) Bow tie analysis]:'''
:'''[http://en.wikipedia.org/wiki/Decision_tree Decision tree analysis]:'''
+
::The bow tie analysis generates a graphical representation which assists in generating the full picture of what has to happen prior to an event (causes) and what can happen afterwards (consequences). It is mostly generated in a brainstorming session.
  
----
+
*'''[http://en.wikipedia.org/wiki/Reliability_centered_maintenance Reliability centered maintainance (RCM)]:'''
:'''[http://en.wikipedia.org/wiki/Human_reliability Human reliability assessment (HRA)]:'''
+
::RCM identifies policies which need to be implemented in order to achieve the required safety by managing failures effectively and efficiently.
  
----
+
*'''Sneak analysis (SA) / [http://en.wikipedia.org/wiki/Sneak_circuit_analysis sneak circuit analysis (SCI)]:'''
:'''[http://en.wikipedia.org/wiki/Bowtie_(sequence_analysis) Bow tie analysis]:'''
+
::SA and SCI are used for identifying design errors which may cause harm to production or personnel or just generate an undesired outcome.
  
----
+
*'''[http://en.wikipedia.org/wiki/Markov_chain Markov analysis]:'''
:'''[http://en.wikipedia.org/wiki/Reliability_centered_maintenance Reliability centered maintainance]:'''
+
::The Markov analysis is used when the future state depends only on present state of a system. It is a quantitative method which can be described with discrete or continuous states.
  
----
+
*'''[http://apppm.man.dtu.dk/index.php/Monte_Carlo_Simulation_of_Risk Monte Carlo simulation]:'''
:'''Sneak analysis (SA) / [http://en.wikipedia.org/wiki/Sneak_circuit_analysis sneak circuit analysis (SCI)]:'''
+
::Simulating complex systems can be the only way to grasp how uncertainties affect them. The Monte Carlo simulation is used for this.
  
----
+
*'''[http://en.wikipedia.org/wiki/Bayesian_inference Bayesian statistics] and[http://en.wikipedia.org/wiki/Bayesian_network  Bayes Nets]:'''
:'''[http://en.wikipedia.org/wiki/Markov_chain Markov analysis]:'''
+
::This is a probability theory using Bayes Theorem to sum up several probabilities in to one.
  
----
+
*'''FN curves:'''
:'''[http://apppm.man.dtu.dk/index.php/Monte_Carlo_Simulation_of_Risk Monte Carlo simulation]:'''
+
::These curves are used in relation with casualties in a specified population affected by an event.
  
----
+
*'''Risk indices:'''
:'''[http://en.wikipedia.org/wiki/Bayesian_inference Bayesian statistics] and[http://en.wikipedia.org/wiki/Bayesian_network  Bayes Nets]:'''
+
::This semi-quantitative measure generates a risk index derived from scorings of normal scales, and is used as a classification system.
  
----
+
*'''Consequence/probability matrix:'''
:'''FN curves:'''
+
::As the name suggests it is a matrix combining qualitative or semi-qualitative consequences with probabilities in order to generate a risk rating. This matrix can then be used to rank different risks treatments or risk sources.
  
----
+
*'''[http://en.wikipedia.org/wiki/Cost%E2%80%93benefit_analysis Cost/benefit analysis (CBA)]:'''
:'''Risk indices:'''
+
::The CBA is often used to see if it is worth it to go ahead with changes to status quo, and mainly on a financial level.
  
----
+
*'''[http://en.wikipedia.org/wiki/Multiple-criteria_decision_analysis Multi-criteria decision analysis (MCDA)]:'''
:'''Consequence/probability matrix:'''
+
::By using several different criteria the MCDA assesses the overall positive value of a set of options, transparently and objectively. It aims to sort the options in order of preference.
  
----
+
*'''Fuzzy synthetic evaluation (FSE) approach: '''
:'''[http://en.wikipedia.org/wiki/Cost%E2%80%93benefit_analysis Cost/benefit analysis (CBA)]:'''
+
::Described in the International journal of Project Management 31 (2013) it is an intuitive method which starts out identifying the risk factors, evaluating a specific risk using both quantitative and qualitative values and by combining them generating a matrix of numeric risk values. After determining the evaluation criteria each criteria is given a weight which is combined with the risk matrix into a fuzzy evaluation matrix. The risk index is then calculated and the overall risk evaluated after each risk is given a weight of it’s own.
 
+
----
+
:'''[http://en.wikipedia.org/wiki/Multiple-criteria_decision_analysis Multi-criteria decision analysis (MCDA)]:'''
+
  
 
==Reference==
 
==Reference==
ISO Guide 73-2009 – Risk Management Vocabulary
+
[http://www.iso.org/iso/catalogue_detail?csnumber=44651 ISO Guide 73-2009 – Risk Management Vocabulary (2009)]
  
ISO 31000 - Risk management - Principles and guidelines
+
[http://www.iso.org/iso/catalogue_detail?csnumber=43170 ISO 31000 - Risk management - Principles and guidelines (2009)]
  
ISO 31010 - Risk management
+
[http://www.iso.org/iso/catalogue_detail?csnumber=51073 ISO 31010 - Risk management (2009)]
  
 
International Journal of Project Management 32 (2014) - Vahid Khodakarami , Abdollah Abdi - Project cost risk analysis: A Bayesian networks approach for modelling dependencies between cost items
 
International Journal of Project Management 32 (2014) - Vahid Khodakarami , Abdollah Abdi - Project cost risk analysis: A Bayesian networks approach for modelling dependencies between cost items
 +
 +
International Journal of Project Management 31 (2013) - Jialin Liu, Quanxi Li, Yuhan Wang - Risk analysis in ultra deep scientific drilling project – a fuzzy synthetic evaluation approach
 +
 +
Project Management Journal (April 2013) - Juliane Teller - Portfolio Risk Management and Its Contribution to Project Portfolio Success: An Investigation of Organization, Process, and Culture
  
 
==Links==
 
==Links==

Latest revision as of 13:21, 20 December 2018

Developed by Johannes Michael Bührmann

main article: Risk Management

Contents

[edit] Summary

This article will describe the element of risk analysis within risk management, what it is used for and list several elements which can be used in the process of managing risk in projects, portfolios and programs.. Since risk analysis is a subpart of Risk Management, several correlations might be present between the two.

Several methods used for Risk Analysis will be mentioned and explained briefly, but (in order to allow the full use of the wiki) not be described in detail. Some of them might not seem directly applicable but can all be used during the possible iterations within the analysis.

The user of risk analysis essentially choose the most appropriate method(s) for calculating the given information and delivers a collective overview of the situation, as an artisan chooses the right tool for the job and produces the individual parts for the product. Using “known knowns” and “known unknowns” (from the Cynefin framework) along with estimates made by either extrapolation based on prior knowledge or by experts, the analysis generates a better understanding enabling the user to conduct a valid risk evaluation.

[edit] Definition

Risk Analysis

Risk analysis lies at the heart of Risk Management and functions very much like the Central Processing Unit (CPU) of a computer.

The term "Risk" is most often defined as a probability of losing something of a specific value. Mathematically speaking; the probability of an event occurring multiplied by the potential value-loss = the risk.

In order to compute this risk the person(s) doing the analysis must as a minimum receive information on the probability of an event occurring and the value of the potential loss. The definition of risk analysis, as defined by the International Organisation for Standardization is as follows:

In their ISO Guide 73-2009, it is stated as the “Process to comprehend the nature of risk and to determine the level of risk” In the ISO 31000 standard it is described as the process which “provides an input to risk evaluation and to decisions on whether risks need to be treated, and on the most appropriate risk treatment strategies and methods” .

Both are correct since the process mentioned is the computational part of Risk Management where different aspects, variables and factors are used to estimate the risk involved with a specific feature, action, decision, condition etc. The outcome of this computation is a quantified number or percentage which can then be used as an evaluation criterion, determining either which option to select or if it is safe to proceed down the investigated path.

[edit] Main features of risk analysis

There are three different analysis method groupings within risk analysis; Qualitative, Semi-Quantitative and Quantitative.

Qualitative
Qualitative analysis methods are based on opinions and estimates. They compute the risk scenario based on few numbers and many interpretations. Outcome of these methods are usually given in levels of significance like “high”, “medium” and “low” or other "word scales" which are not specifically determining any actual number. An example of a qualitative result is the risk of terror when travelling abroad, made by the ministry of foreign affairs.
Semi-quantitative
The outcomes of the semi-quantitative analysis methods are based on numeric ratings using evaluation scales for probability and consequence and usually combining them using a formula, resulting in a comparable value for the risk level.
Quantitative
The quantitative analysis uses estimates of probability and consequence values to generate an approximation of the risk involved, represented by one specific value. The specific values, depending on the method of gathering, from different analysis can then be combined into one overall risk factor.


Because risk analysis works much like the processor in a computer it needs to receive a minimum of information as input before it can calculate an output which allows the user to gain a better overview and basis for making changes or taking decisions. A risk analysis is often generated for the sake of factual argumentation and credibility of decisions. Normally input are generated in the step before the analysis; "Risk identification" but some can also be derivatives generated during the analysis. Many of the models described later can be used to generate input during the identification stage. Output of the analysis step is usually used within the "Risk evaluation" in order to understand the risk in question.

Risk Analysis
Input: Output:
;Purpose
The purpose is the reason for analysing the risk; it assists in determining the boundaries of the analysis.
;Assessment of the risk with the following aspects
Description of methods used and known control features impact on the risk
Combined Likelihood / probability depending on the description of original risk
Consequences of different scenarios
;Type of risk
Choice of models depends on the type of risk in question.
;Information available
Determines whether it is possible to conduct the analysis right away or information has to be gathered.
;Existing control features
The features that are already in place to influence the risk and outcome of the analysis.
;Effectivity of existing control features
How effective the control features are. This information can also reveal if there is room for improvements.
;Description of the confidence in:
The assessment of the risk (the result of the analysis)
The sensitivity of the result to preconditions and assumptions
Information Uncertainty
Information Availability
Information Quality
Information Quantity
Ongoing relevance of information (how relevant will the analysis be in the future)
;Consequences
The consequences can be both positive and negative, and reflect the impact of events defined in the analysis.
;Likelihood / Probabilities
Estimates, guesstimates, statistics and assumptions on the probability of an event happening.
;Risk criteria
Terms against which the risk significance is evaluated, often based on context (internal/external) and objectives of the organisation.
;Causes of risk
The reasons why an event takes place.
;Limitations
Demarcation description.
;Sources of risk
The objects which affects the risk.
;Factors influencing any of the above
Weights which scale the severity of the quantities are part of this input, as well as uncertainties and sensitivities.
;Interrelations / Interdependence
The network of relational aspects between different risks




[edit] Benefits of analysing risk

Analysing risk has become an integrated part of working with forecasts as well as decisions in projects, programs and portfolios, simply because it generates the big picture needed to make an informed decision. The drivers of analysing risk are the focus on lowering costs and expenses, avoiding loss of anything valuable and reducing variability in outcomes. The reason why risk is analysed with so many different methods to choose from, is because several different categories of risk exist, and yet there is a universal consensus that risk is best avoided, mitigated, minimised or negated.

[edit] Models used in order to analyse risk

All but one of the following models are described in Annex B of the ISO 31010 standard.

Brainstorming is a very intuitive method which uses associations and connections made by possibly several people around a central subject to uncover problematic and opportunistic aspects affecting the subject. This qualitative information is then used to gather as much quantitative information as possible in order to complete the further analysis. It can e.g. be used to imagine future risks or possible control features to known risks.
The structured or semi-structured interview can be used for gathering information from numerous sources. These interviews do not have to be done face to face since questionnaires are also considered within this model. Applicable in the phases before and after Risk Analysis.
The Delphi technique is essentially a brainstorming process where the participants are kept anonymous but are able to see the collected work of all participating in the process. It is used to reach some kind of consensus around the subject in question. Applicable in the phases before and after Risk Analysis.
  • Check-lists:
Check-lists are built from previous experiences and often list known risks, control features and/or hazards gathered through prior assessments or lessons learned.
PHA is used when there is little information available and as the name states normally in the beginning of e.g. a project, in order to uncover potential hazards influencing the further development.
HAZOP is a qualitative method which studies the current activities in order to access the risk involved. It usually examines existing operations like procedures and products as well as processes and the system around them.
HACCP is mainly used in the industry which produces items for consumption where infections are of vital importance. The critical control points are then indicating areas within the production where errors can lead to loss of quality or worse.
  • Toxicity assessment:
Toxicity assessment is used when looking at risk related to the environment and how the introduction of a source of harm affects it.
SWIFT is normally used at workshops by the facilitator to make the participants introduce risk into their chain of thought by using a set of specific questioning words along with the catchphrase “what if?” .
When conducting a scenario analysis, one or several future scenarios are developed based on the participants’ thoughts and ideas on where the future might bring us. Then doing back-casting in order to determine the events needed to reach the scenario and evaluating the risks of these events.
  • Business impact analysis (BIA):
The BIA investigates the risks capable of disrupting the organisation’s operations as well as the current controls in place and how well they will handle the disruption.
RCA is often used after an event has taken place with the aim of preventing it from happening again.
By constantly questioning for the reason why an event occurred, turning the reason into an event and repeating the question the RCA attempts to discover the fatal event which set several chains of actions into motion.
FMEA is essentially an error tool attempting to map out the different possible ways for processes, systems or components are able to fail and thus not fulfil the designed purpose.
FMECA expands FMEA by ranking the outcomes against each other and thereby identifying the most critical failures.
FTA is a method used to develop your typical trouble shooting guide where it is possible to locate the cause of an undesired event by deductive reasoning.
ETA can be used to generate the probability of the control features working or not working with regards to a specific event happening. Contrary to the FTA, the ETA can be used before the event has actually happened as a hypothetical reasoning method. It can be used both quantitative and qualitative.
  • Cause-consequence analysis:
Cause-consequence analysis is combining FTA and ETA in order to analyse the various paths possible within a system following a critical event. It is used within critical safety systems as a reliability tool.
Cause-and-effect analysis identifies potential causes of an event or problem by looking at the possible contributing factors and organising them in either a fishbone or tree diagram in order to consider all possible hypotheses.
  • Layers of protection analysis (LOPA):
LOPA analyses if the required control features are present to mitigate an undesired event or scenario. It is a semi-qualitative method used to provide a baseline when specifying independent protection layers.
Decision tree analysis can be used as a forecast tool, assisting the decision makers with understanding the consequences and follow-up decisions to an initial event. It resembles a tool usable for career path decisions where you start with a lot of options and by deciding on one path, still having several options open.
HRA is mainly used to evaluate the human influence on performance of systems or the human error factor.
It is usable both quantitatively and qualitatively.
The bow tie analysis generates a graphical representation which assists in generating the full picture of what has to happen prior to an event (causes) and what can happen afterwards (consequences). It is mostly generated in a brainstorming session.
RCM identifies policies which need to be implemented in order to achieve the required safety by managing failures effectively and efficiently.
SA and SCI are used for identifying design errors which may cause harm to production or personnel or just generate an undesired outcome.
The Markov analysis is used when the future state depends only on present state of a system. It is a quantitative method which can be described with discrete or continuous states.
Simulating complex systems can be the only way to grasp how uncertainties affect them. The Monte Carlo simulation is used for this.
This is a probability theory using Bayes Theorem to sum up several probabilities in to one.
  • FN curves:
These curves are used in relation with casualties in a specified population affected by an event.
  • Risk indices:
This semi-quantitative measure generates a risk index derived from scorings of normal scales, and is used as a classification system.
  • Consequence/probability matrix:
As the name suggests it is a matrix combining qualitative or semi-qualitative consequences with probabilities in order to generate a risk rating. This matrix can then be used to rank different risks treatments or risk sources.
The CBA is often used to see if it is worth it to go ahead with changes to status quo, and mainly on a financial level.
By using several different criteria the MCDA assesses the overall positive value of a set of options, transparently and objectively. It aims to sort the options in order of preference.
  • Fuzzy synthetic evaluation (FSE) approach:
Described in the International journal of Project Management 31 (2013) it is an intuitive method which starts out identifying the risk factors, evaluating a specific risk using both quantitative and qualitative values and by combining them generating a matrix of numeric risk values. After determining the evaluation criteria each criteria is given a weight which is combined with the risk matrix into a fuzzy evaluation matrix. The risk index is then calculated and the overall risk evaluated after each risk is given a weight of it’s own.

[edit] Reference

ISO Guide 73-2009 – Risk Management Vocabulary (2009)

ISO 31000 - Risk management - Principles and guidelines (2009)

ISO 31010 - Risk management (2009)

International Journal of Project Management 32 (2014) - Vahid Khodakarami , Abdollah Abdi - Project cost risk analysis: A Bayesian networks approach for modelling dependencies between cost items

International Journal of Project Management 31 (2013) - Jialin Liu, Quanxi Li, Yuhan Wang - Risk analysis in ultra deep scientific drilling project – a fuzzy synthetic evaluation approach

Project Management Journal (April 2013) - Juliane Teller - Portfolio Risk Management and Its Contribution to Project Portfolio Success: An Investigation of Organization, Process, and Culture

[edit] Links

Only the following links are internal in the APPPM-wiki, All others are to Wikipedia.org and may be replaced when the APPPM-pages has been written, and added to this list.

Once all links are internal, this section can be deleted.

Risk Management

the Cynefin framework

Monte Carlo simulation

Personal tools
Namespaces

Variants
Actions
Navigation
Toolbox