Risk management strategy

From apppm
(Difference between revisions)
Jump to: navigation, search
Line 1: Line 1:
 
“When trouble is sensed well in advance in can be easily remedied; if you wait for it to show itself any medicine will be too late because the disease will have become incurable. As the doctors say of a wasting disease, to start with it is easy to cure but difficult to diagnose; after time… it becomes easy to diagnose but difficult to cure.” (Machiavelli, 1514)
 
“When trouble is sensed well in advance in can be easily remedied; if you wait for it to show itself any medicine will be too late because the disease will have become incurable. As the doctors say of a wasting disease, to start with it is easy to cure but difficult to diagnose; after time… it becomes easy to diagnose but difficult to cure.” (Machiavelli, 1514)
  
When dealing with a project, uncertainties are to be expected, whether the project is influenced by external or internal factors. If an unexpected event turns out to be harmful to the project it is considered to be a risk.  A risk can be defined as the product of the probability of the risk and the impact of the risk. Should a problem be very likely to happen, but have a little or no impact on the project there is little reason in prioritizing the mitigation of the problem. For a problem having a high impact, but very low probability the need to mitigate this problem is likewise not a priority. The impact of a risk is however more severe than the probability. For instance are smaller injuries, which happen often, easier to accept than heavier injuries, which happen more seldom. The probability of a problem should however not be neglected. A common way to illustrated this is by playing a small game:
+
When dealing with a project, uncertainties are to be expected, whether the project is influenced by external or internal factors. If an unexpected event turns out to be harmful to the project it is considered to be a risk.   
 +
A risk can be defined as the product of the probability of the risk and the impact of the risk. Should a problem be very likely to happen, but have a little or no impact on the project there is little reason in prioritizing the mitigation of the problem.  
 +
For a problem having a high impact, but very low probability the need to mitigate this problem is likewise not a priority. The impact of a risk is however more severe than the probability. For instance are smaller injuries, which happen often, easier to accept than heavier injuries, which happen more seldom.  
 +
The probability of a problem should however not be neglected. A common way to illustrated this is by playing a small game:
 +
 
 
In the construction business many factors must by in order for the project to move forward. Six people are given a dice and a problem. Whenever a person rolls a 1 a problem has occurred which delays the project. Thus the probability of a problem happening is 1/6. The probability of no problem happening is:
 
In the construction business many factors must by in order for the project to move forward. Six people are given a dice and a problem. Whenever a person rolls a 1 a problem has occurred which delays the project. Thus the probability of a problem happening is 1/6. The probability of no problem happening is:
  
Line 7: Line 11:
  
 
This means that only a third of the time, the project will progress.
 
This means that only a third of the time, the project will progress.
 +
 
If there is no certain way to determine a risk’s impact or probability or multiple risks are compared without having similar impact type (e.g. comparing human casualties against monetary loss) a qualitative approach can be used, where the risk is rated from 1-5. This way a prioritized list of risks can be produced. With this list it is possible to determine which risk to take care of first.
 
If there is no certain way to determine a risk’s impact or probability or multiple risks are compared without having similar impact type (e.g. comparing human casualties against monetary loss) a qualitative approach can be used, where the risk is rated from 1-5. This way a prioritized list of risks can be produced. With this list it is possible to determine which risk to take care of first.
 +
 
This article will examine ways to identify potential risks, rate their associated probabilities and impacts and process the new knowledge.
 
This article will examine ways to identify potential risks, rate their associated probabilities and impacts and process the new knowledge.
  

Revision as of 12:04, 17 November 2014

“When trouble is sensed well in advance in can be easily remedied; if you wait for it to show itself any medicine will be too late because the disease will have become incurable. As the doctors say of a wasting disease, to start with it is easy to cure but difficult to diagnose; after time… it becomes easy to diagnose but difficult to cure.” (Machiavelli, 1514)

When dealing with a project, uncertainties are to be expected, whether the project is influenced by external or internal factors. If an unexpected event turns out to be harmful to the project it is considered to be a risk. A risk can be defined as the product of the probability of the risk and the impact of the risk. Should a problem be very likely to happen, but have a little or no impact on the project there is little reason in prioritizing the mitigation of the problem. For a problem having a high impact, but very low probability the need to mitigate this problem is likewise not a priority. The impact of a risk is however more severe than the probability. For instance are smaller injuries, which happen often, easier to accept than heavier injuries, which happen more seldom. The probability of a problem should however not be neglected. A common way to illustrated this is by playing a small game:

In the construction business many factors must by in order for the project to move forward. Six people are given a dice and a problem. Whenever a person rolls a 1 a problem has occurred which delays the project. Thus the probability of a problem happening is 1/6. The probability of no problem happening is:

5/6*5/6*5/6*5/6*5/6*5/6=(5/6)^6=0,33

This means that only a third of the time, the project will progress.

If there is no certain way to determine a risk’s impact or probability or multiple risks are compared without having similar impact type (e.g. comparing human casualties against monetary loss) a qualitative approach can be used, where the risk is rated from 1-5. This way a prioritized list of risks can be produced. With this list it is possible to determine which risk to take care of first.

This article will examine ways to identify potential risks, rate their associated probabilities and impacts and process the new knowledge.


Contents

Risk identification

How is a potential risk identified? Which methods to use for identification.

Risk analysis

Methods for analyzing risks for further processing.

Risk assessment

Methods to assess identified risks.

Risk processing

Methods for mitigating an identified risk

Conclusion

Personal tools
Namespaces

Variants
Actions
Navigation
Toolbox