The Critical Path Method in project planning

From apppm
Revision as of 13:24, 15 September 2016 by Chalidaj (Talk | contribs)

Jump to: navigation, search

The Critical Path Method is a step by step technique that is used to schedule a set of project activities. It analysis what activities are least flexible and the project duration is predicted based on the activities that fall along the critical path. The critical path is the longest sequence of activities in a project plan which must be completed on time in order for the project to complete on the predetermined scheduled date [1]. By delaying an activity on the critical path leads to a delay on the completion time of the entire project as these activities have no slack. Activities along the path cannot start until the predecessor activity is completed. When using CPM to plan a project a graphical diagram is often represented showing how each activity is related to the others [2]. This method is one of several tools that is important to keep the project on track and is convenient for all forms of projects, including research projects, product development, construction industry, maintenance and many more.

A joint venture between the Dupont chemical company and computer firm Remington Rand Univac led to a development of the Critical Path Method in the 1956 to tackle the interrelationships of separate activities within a project schedule [3].

In this article the Critical Path Method (CPM) is described, a step by step guidance on how to apply the method is discussed and the tradeoff between cost and time are analyzed. Furthermore, a comparison to other project management techniques is performed and its limitations and advantages are addressed.


Contents

Overview

Introduction and purpose of CPM

History

General methodology

Application

CPM graph box layout

CPM network creation

Forward pass

Backward pass

Slack calculation

CPM graph and critical path

Time-Cost Trade-Off

Figure x: setja heimild

The aim of the time-cost trade-off analysis is to reduce the original project duration, determined from the CPM, to meet a specific deadline, with the least cost. In general, there is a trade-off between the time and the direct cost to complete an activity, the less expensive the resource the larger duration they take to complete an activity. Shortening the duration on an activity will normally increase its direct cost. A simple version of the relationship between the duration of an activity and its direct cost can be seen in Figure x. The normal cost is the least direct cost required to complete an activity, and the corresponding duration is called the normal duration. The crash duration is the shortest duration required to complete the activity and the corresponding cost is called the crash cost.


To solve the time-cost trade-off problem several heuristic approaches can be used, such as the cost slope method. The step by step procedure for that method is summarized as follow:

  1. Apply the CPM technique as mentioned in the Application section to identify the critical path.
  2. Compute the cost slope for each activity by applying following equation: Cost slope = (crash cost – normal cost) / (normal duration – crash duration)
  3. Shorten the activity duration on the critical path that has the least cost slope and has not been shortened to its crash duration.
  4. Keep reducing the duration of the activities on the critical path that have the lowest cost slope until its crash duration is reached or until the critical path changes.
  5. In some cases, multiple critical paths are involved. The activity(ies) to shorten is determined by comparing the cost slope of the activity on all critical paths with the sum of cost slope for a group of activities.
  6. Once a critical path is shortened the duration of the activities and the slack should be adjusted.
  7. The cost increase is calculated by multiplying the cost slope with the shortening time of the activities.
  8. This heuristic approach should be continued until no further shortening is possible and the crash point is reached.

To get an deeper understanding of how application of this method works a detailed example will be shown in here below.


Example of the time-cost trade-off calculation

The example of this computation was retrieved from….

The aim is to crash the project duration to 110 days. As mentioned in the Application section, the normal project duration is 140 days and the critical path is B-C-D-E. Project total normal cost is the sum the normal cost in Table x, which is 48.300.

Figure x: setja heimild


The cost slope in Figure x is calculated by inserting relevant values into the cost slope equation. For example, for activity C the cost slope is (22,000-16,000) / (40-30) = 600. Activity D on the critical path has the lowest cost slope and can be crashed by 10 days. The timing for activities that follow activity D must then be adjusted.


Figure x: setja heimild

Comparison to related project management techniques

There are several project management techniques that are related to CPM, e.g. Project Management and Review Technique(PERT) and Critical Chain Method(CCM). These methods are used for management of projects with the aim to finish on time and within budget. Nevertheless, there are many differences between all these methods which will be discussed in this section.

CPM and PERT are often used in conjunction with each other to manage projects in a successful way. One of their difference between these methods is that PERT is a project management technique where planning, scheduling, organising, coordinating and controlling of uncertain activities is done, while CPM is a statistical technique of project management in which planning, scheduling, organising, coordination and control of well-defined activities takes place. Another difference is that PERT is a technique of planning and control of time while CPM is a method to control cost and time. Furthermore, the focus is in events when PERT is applied. Unlike CPM, where the focus is on activities. Lastly, to shorten project duration with least additional cost a cashing technique can be applied to CPM, however the crashing concept is not applicable to PERT. There are many more differences between these methods which will not be discussed further in this article. [4]

Moving on to the CCM which is built on CPM. Both methods are “Critical” and as their name suggest there are similarities and differences among the two of them. The main differences are that CPM involves the calculation of ES, EF, LS, LF and SL through forwards and backward passes in the project and focuses on the sequence of activities and the estimated duration of individual task in a straight forward manner. Task buffers are added to each task. On the other hand, CCM just put tasks together in a chain by considering the minimal time needed for individual tasks. An overall project buffer is combined to the end of the project chain. [5]

Advantages and disadvantages/limitations of CPM

CPM tool has proved to be very valuable and beneficial when it comes to managing projects. Advantages of using this method are many and the list could get rather long. Listed here below are few of the advantages that organisations could gain by using CPM: [6]


  • The greatest advantage of CPM can be seen in the planning stage, were the user is required to think through a project logically and with sufficient detail to establish form, clear project objectives, activities and specification. This helps preventing the chance of overlooking necessary activities and goals of a project.
  • CPM provides a realistic and disciplined method for determining how to attain the project objectives and for communicating and documenting the project plans, schedules, time and cost performance clearly and concisely in the scheduling stage, where a time chart is constructed for each activity.
  • In the monitoring stage, CPM identifies the most critical elements in the plan making the managers focusing on the activities that are most constraining on the scheduling. CPM will generate new schedules when there are changes in the durations of the activities. And as technical or procedural changes are considered, CPM provides an easy method for evaluating the effects these changes have on the overall project schedule.

Disadvantages and limitations of CPM

Conclusion

References

  1. Critical Path, BusinessDictionary, 2016.
  2. Critical Path Method, webopedia, 2016.
  3. History of the Critical Path Method, Kielmas, Maria, 2016.
  4. Surbni, S. (2015), ‘’Differences Between PERT and CPM‘’. Retrieved September 5, 2016, from http://keydifferences.com/difference-between-pert-and-cpm.html#Definition.
  5. Chung, E. (2016), ‘Critical Path Method vs Critical Chain Method for PMP Exam’. Retrieved September 5, 2016, from http://edward-designer.com/web/critical-path-method-vs-critical-chain-method-for-pmp-exam/.
  6. Anderson, E. B. & Hales, S. T. (1986), 'Critical Path Method Applied to Research Project Planning: Fire Economics Evaluation System (FEES)'. Pp. 1-2. Retrieved September 8, 2016, from http://citeseerx.ist.psu.edu/viewdoc/download?doi=10.1.1.115.6122&rep=rep1&type=pdf.