=='''Abstract'''==
 
 
The different types of activities are relevant to scheduling and forms of changing and crashing (accelerating) a schedule:
 
The different types of activities are relevant to scheduling and forms of changing and crashing (accelerating) a schedule:
  
=Resource-dependent activities=
+
=Resource-dependent activities=  
 
+
 
*Duration can be changed.
 
*Duration can be changed.
 
*The duration of the activity can be halved if the resources are doubled (experienced employees).
 
*The duration of the activity can be halved if the resources are doubled (experienced employees).
*Examples: programming, digging, drawing work
+
*Examples: programming, digging drawing work
 
*Speed up: add more people
 
*Speed up: add more people
  
 
=Process-dependent activities=
 
=Process-dependent activities=
  
*Activities where the duration is determined by a process that must be implemented to achieve the desired result.
+
*Activities where the duration is determined by a process that must be implemented to achieve the desired result
 
*Characterized by that it can't be rushed
 
*Characterized by that it can't be rushed
 
*Examples: pregnancy, curing of concrete, training and education of employees
 
*Examples: pregnancy, curing of concrete, training and education of employees

Latest revision as of 12:00, 1 March 2019

The different types of activities are relevant to scheduling and forms of changing and crashing (accelerating) a schedule:

Contents

[edit] Resource-dependent activities

  • Duration can be changed.
  • The duration of the activity can be halved if the resources are doubled (experienced employees).
  • Examples: programming, digging drawing work
  • Speed up: add more people

[edit] Process-dependent activities

  • Activities where the duration is determined by a process that must be implemented to achieve the desired result
  • Characterized by that it can't be rushed
  • Examples: pregnancy, curing of concrete, training and education of employees
  • Speed up example: Difficult, in some cases through e.g. change of equipment

[edit] Procedure-dependent activities

  • Activities where a certain procedure must be followed
  • The uncertainty related to the outcome of the procedure.
  • Examples: steering committee meetings, consultation of stakeholders
  • Speed up example: Ebola and the change on regulation

[edit] Problem-dependent activities

  • Activities to solve a problem.
  • Innovation is paramount. Can be difficult to estimate the duration
  • Examples: design tasks, development, creative tasks
  • Speed up example: difficult, through intermediary deadlines or forcing an end - 'time boxing'