Work Breakdown Structure

From apppm
(Difference between revisions)
Jump to: navigation, search
(Description of the WBS features)
Line 15: Line 15:
 
A project is made more manageable by breaking it down into individual components that together are known as a ''Work Breakdown Structure'' or ''WBS''. Such a structure defines unique work elements that can be arranged and completed in the order defined by the network diagram: sequentially, in parallel, or in the specific order necessary to accomplish the project outcomes. Furthermore, it facilitates other project management processes such as estimating, scheduling, resource allocation, risk analysis, and measurement and control of the project. This tool is a representation of a clear description of the project’s deliverables and scope. In addition, the ''WBS'' method is not a description of a process or schedule that defines how or when the deliverables will be produced, but rather is specifically limited to describing and detailing the project’s outcome or scope.<ref>Project Management Institute. “Practice Standard for Work Breakdown Structures”- Second Edition, 2011.</ref> Moreover, it organizes and defines the total scope of the project, and represents the work specified in the current approved project scope statement. The planned work is contained within the lowest level of ''WBS'' components, which are called work packages. A work package can be used to group the activities where work is scheduled and estimated, monitored, and controlled. In the context of the ''WBS'', work refers to work products or deliverables that are the result of activity and not to the activity itself.<ref name="multiple" />
 
A project is made more manageable by breaking it down into individual components that together are known as a ''Work Breakdown Structure'' or ''WBS''. Such a structure defines unique work elements that can be arranged and completed in the order defined by the network diagram: sequentially, in parallel, or in the specific order necessary to accomplish the project outcomes. Furthermore, it facilitates other project management processes such as estimating, scheduling, resource allocation, risk analysis, and measurement and control of the project. This tool is a representation of a clear description of the project’s deliverables and scope. In addition, the ''WBS'' method is not a description of a process or schedule that defines how or when the deliverables will be produced, but rather is specifically limited to describing and detailing the project’s outcome or scope.<ref>Project Management Institute. “Practice Standard for Work Breakdown Structures”- Second Edition, 2011.</ref> Moreover, it organizes and defines the total scope of the project, and represents the work specified in the current approved project scope statement. The planned work is contained within the lowest level of ''WBS'' components, which are called work packages. A work package can be used to group the activities where work is scheduled and estimated, monitored, and controlled. In the context of the ''WBS'', work refers to work products or deliverables that are the result of activity and not to the activity itself.<ref name="multiple" />
 
==Big Idea==
 
==Big Idea==
===Description of the WBS features===
+
===Description of the WBS framework===
 +
 
 
===Purpose===
 
===Purpose===
 
==Application==
 
==Application==

Revision as of 19:21, 16 February 2018

Contents

Abstract

It is beyond any reasonable doubt that the Work Breakdown Structure (WBS) is the foundation of planning, estimating, scheduling, and monitoring any kind of activities. With its contribution an outline of common reference for all schedules and better estimates is ensured.[1] A Work Breakdown Structure (WBS) is the process of subdividing project deliverables and project work into smaller, more manageable components. More specifically, it is a hierarchical decomposition of the total scope of work to be carried out by the project team to accomplish the project objectives and create the required deliverables.[2]

The purpose of this wiki-article is not only to thoroughly describe the capabilities and restrains of this method but also to provide guidance concerning the techniques that can be used for the effective implementation of project Work Breakdown Structures.

Introduction

Historical Retrospection

The first forms of Work Breakdown Structure (WBS) were developed by the U.S. Department of Defense with a view to improving their missile systems at mid-1960s. The fundamental concept of the WBS and the practices around its use were initially established by the U.S. Department of Defense (DoD) and National Aeronautics and Space Administration (NASA) for the purpose of planning and regulating broad procurement projects whose primary objective was the development and delivery of weapons and space systems respectively. These projects generally involved a lot of industrial contractors each with responsibility for independent segments of the system and were also managed by a central administrative office. In this environment, the WBS was used to “…ensure that the total project is fully planned and that all derivative plans contribute directly to the desired objectives” (NASA, 1962).[3]

Work Breakdown Structure Definition

A project is made more manageable by breaking it down into individual components that together are known as a Work Breakdown Structure or WBS. Such a structure defines unique work elements that can be arranged and completed in the order defined by the network diagram: sequentially, in parallel, or in the specific order necessary to accomplish the project outcomes. Furthermore, it facilitates other project management processes such as estimating, scheduling, resource allocation, risk analysis, and measurement and control of the project. This tool is a representation of a clear description of the project’s deliverables and scope. In addition, the WBS method is not a description of a process or schedule that defines how or when the deliverables will be produced, but rather is specifically limited to describing and detailing the project’s outcome or scope.[4] Moreover, it organizes and defines the total scope of the project, and represents the work specified in the current approved project scope statement. The planned work is contained within the lowest level of WBS components, which are called work packages. A work package can be used to group the activities where work is scheduled and estimated, monitored, and controlled. In the context of the WBS, work refers to work products or deliverables that are the result of activity and not to the activity itself.[2]

Big Idea

Description of the WBS framework

Purpose

Application

Limitations

References

  1. Dr. Parviz F. Rad, PE CCE. “Advocating a Deliverable-Oriented Work Breakdown Structure”, Cost Engineering - December 31, 1999.
  2. 2.0 2.1 Project Management Institute. “A Guide to the Project Management Body of Knowledge (PMBOK® Guide)”- Fifth Edition, 2013.
  3. Eric S. Norman, Shelly A. Brotherton, Robert T. Fried. “Work Breakdown Structures: The Foundation for Project Management Excellence”- John Wiley & Sons, 2008.
  4. Project Management Institute. “Practice Standard for Work Breakdown Structures”- Second Edition, 2011.

Annotated Bibliography

Dr. Parviz F. Rad, PE CCE. “Advocating a Deliverable-Oriented Work Breakdown Structure”, Cost Engineering - December 31, 1999.

Annotation: This article presents the rationale and methods for modifying the traditional breakdown structure philosophy in order to obtain a WBS that is focused on deliverables.

Project Management Institute. “A Guide to the Project Management Body of Knowledge (PMBOK® Guide)”- Fifth Edition, 2013.

Annotation: This book provides guidelines for managing individual projects and defines project management related concepts. It also describes the project management life cycle and its related processes, as well as the project life cycle.

Eric S. Norman, Shelly A. Brotherton, Robert T. Fried. “Work Breakdown Structures: The Foundation for Project Management Excellence”- John Wiley & Sons, 2008.

Annotation: This book is intended to be a beginning step in filling the information gap that exists between what is currently written about Work Breakdown Structures and what the authors have learned is needed by program and project managers today.

Project Management Institute. “Practice Standard for Work Breakdown Structures”- Second Edition, 2011.

Annotation: This book provides guidance in the initial generation, subsequent development, and application of the WBS. It also includes information derived from accepted project management industry sources.