The Role of the Project Sponsor

From apppm
Jump to: navigation, search

Developed by Susan Tyrell


Contents

Abstract

Figure 1 - Roles of a Project Sponsor, based from PMI® Global Congress 2006

A sponsor is a person or group who provides resources and support for the project and is accountable for enabling success. The sponsor may be external or internal to the project manager's organization [1]. This is a critical role, as is focused on monitoring and controlling the project at a strategic level. It Is very common to associate the term “Project Sponsor” to a disconnect stakeholder from the project. On the contrary, a Project Sponsor can define the difference between success and failure. Moreover, one of the fundamentals reasons why a project fails is the absence of executive sponsorship and management [2]. The Sponsor owns the business case and leads the project through the initiating processes until formally authorized, and plays a significant role in the development of the initial scope and charter [3]. Therefore, it is vital to establish a close relationship between the Sponsor and the Project, Program, and Portfolio to ensure that the business case remains viable and it will deliver the stipulated goal and benefits. Moreover, there is a lack of understanding of the impact that a Project Sponsor can address the success of a project. The main goal of this article is defining the role and responsibility and identify the importance of a Project Sponsor in a project.

Introduction

The term “Project Sponsor” appears to have emerged at the end of the 1980s. In 1990, the term appears in the book “Project Leadership by Brines Geddes and Hastings, 1990”[4], defining the project sponsor as the “Project Manager boss”. In 1993, J. Rodney Turner[5] discussed the sponsor as the “owner” of the project, the person who paid for the work and controlled the flow of the money. Turner made the distinction between the sponsor as the owner and the champion as the project’s advocate. Regardless of the precise definition of the role, the term “project sponsor” has come into widespread use in the context of internal projects. On closer examination, it appears that the term and the role are more frequently used in the context of internal projects, projects where both the project owner or client and the project manager and project delivery team are within the same organization. The term is less widely used where the project is delivered to the client or owner by a separate organization through a contractual arrangement as is generally the case. The client or owner organization, may, however, appoint a project sponsor, responsible, on behalf of the client or owner organization, for the interface with the contracting organization delivering the project. This helps to explain the need for a project sponsor. The project sponsor role becomes relevant where there is a need to identify a person responsible for the project on behalf of an organisation and as Kerzner says: Project sponsorship has evolved into the best way that executives can provide support for a project regardless of whether internal or external[6].

The Project Sponsor

Definition and Responsibilities

According to the PMBOK® Guide, a sponsor is a person or group that provides the financial resources, in cash or kind, for the project. When a project is first conceived, the sponsor champions the project. This includes serving as spokesperson to a higher level of management to gather support throughout the organization and promote the benefits that the project will bring. The sponsor leads the project through the engagement or selection process until formally authorized, and plays a significant role in the development of the initial scope and charter. For matters that are beyond the control of the project manager, the sponsor serves as an escalation path. The sponsor may also be involved in other important issues such as authorizing changes in scope, phase-end reviews, and go/no-go decisions when risks are particularly high.[3]

In dissecting this definition we can extract the following responsibilities of a sponsor: [7]

  • Champion the project
  • Lead the project through the engagement or selection process until formally authorized
  • Provide a significant role in the development of the initial scope and charter
  • Serve as an escalation path
  • Authorize changes in scope
  • Provide go/no-go decisions.

A project sponsor is typically responsible for initiating, ensuring, approving, and establishing a series of key aspects in relation to the project, which can be summed up under categories of vision, governance, and value/benefits realization. Note that the categories are not mutually exclusive and most of the items can appear under more than one category (e.g., approving deliverables can be placed under each of the three categories):[8]

Vision

  • Ensure the validity of the business case and the viability of the business proposition
  • Ensure ongoing alignment with business objectives
  • Informally interact with the project team and other key stakeholders to stay informed of trends and events within the project (and ensure the project remains viable)
  • Define project success criteria that align with the business objectives

Governance

  • Prioritize the initiative and ensure it is launched and initiated properly
  • Serve as a voice for the project and ensure appropriate organizational priority is given to it throughout
  • Assemble and provide on-going support for the project organization
  • Identify roles and reporting structure
  • Serve as an escalation point for issues and other matters and obstacles that are beyond the control of the project manager
  • Provide financial resources for the project and approval on go/no-go decisions regarding progress and phases.

Value and Benefits

  • Ensure risks and changes are managed properly and sufficiently and make associated decisions
  • Ensure control mechanisms and reviews are in place
  • Ensure the project delivers the intended value
  • Evaluate progress and status
  • Approve deliverables
  • Make go/no-go decisions
  • Be responsible for the overall quality, value, and benefits of the project, from process to the end product.


The sponsor is also responsible for recognizing, addressing (proactively or reactively), and initiating appropriate action if and when business conditions and circumstances significantly change throughout the lifecycle of the project, so the project can remain viable and the project manager can continue to carry out the job of leading the project.[9]

General Role

The sponsor leads the project through the initiating processes until formally authorized, and plays a significant role in the development of the initial scope and charter. For issues that are beyond the control of the project manager, the sponsor serves as an escalation path [1]. The Project Sponsor Role is responsible for providing good governance for the project. This includes the following: [10]

Figure 2 - Framework of Project Sponsor Relationships, inspired by the book Realizing Strategy through Projects: The Executive's Guide - Lechtman, 2005
  • Maintaining a focus on the broader issues on behalf of the project / informing the project manager and team of organizational and environmental changes which might impact the project.
  • Establishing connections on behalf of the project, and supporting interfaces between the project team and the wider organization and external environment.
  • Advocating on behalf of the project with the senior executive and other key senior stakeholders.
  • Clearing pathways so that key resources can be obtained for the project.
  • Motivating the project team when times are difficult.
  • Objectively criticizing project performance.
  • Providing ad hoc support to the project manager and the project team, including mentoring.
  • Approving finance.

Role between the Project and the Organisation

The Project Sponsor often serves as the liaison between the project and the organization. The sponsor has different responsibilities towards different stakeholders[glossary 1] during different phases of the Project Life-Cycle[glossary 2]. These responsibilities are what ultimately determine the attributes required by the individual who will act in this role.[11] Figure 2 illustrated the framework (Lechtman, 2005[12]) for describing and analyzing the pivotal role with 360-degree relationships. It is clear that there are four main sets of relationships, namely vertical-up, horizontal internal, horizontal external and vertical-down.

Vertical-Up Relationship

This section relates to the senior managers, directors, and executives. Aligning the project with strategic objectives, ensuring good governance [glossary 3] and managing the relationship with senior management (Figure 3). The sponsor is mainly responsible for re-defining the existing way of doing business through innovation and new ideas and is, therefore, the idea originator. This is followed by selling the idea or project to the decision-making body and obtaining the necessary funding for it[11]. The project sponsor should understand the greater impact the project will have on the organization now and in the future. Ensuring that governance is maintained on the project through representing the project in governance structures within the organization. This means taking full accountability, responsibility, and ownership of the project, ensuring that it is correctly resourced with the right people, that it is funded properly and enjoys the correct priorities. Moreover, this role is expected to solve any senior management conflict that could compromise the evolution of the project.

Figure 3 - The Vertical-Up relationship, inspired by the book Realizing Strategy through Projects: The Executive's Guide - Lechtman, 2005.

The Horizontal Relationship

As shown in Figure 4, relates to the different internal stakeholders and business unit managers as well as external relationships with vendors, suppliers, and partners. From the internal relationship viewpoint, there is an expectation that the sponsor should understand what is expected from the project from a business perspective. The sponsor must ensure buy-in and cooperation from peers and all other stakeholders. Maintaining a good relationship with peers and stakeholders will assist with removing any obstacles that require hierarchical power. The external relationship viewpoint, the sponsor should liaise with and acquire support from all third party suppliers and vendors and ensure that all deliverable are appropriate. The sponsor should also ensure that the requirements of external partners, such as a holding company, are addressed through the project. The above can be summarized into two main responsibilities namely to build and maintain relationship with internal and external stakeholders, to facilitate an environment and political climate that is conducive to project success.[11]

Figure 4 - The Horizontal relationship, inspired by the book Realizing Strategy through Projects: The Executive's Guide - Lechtman, 2005.

The vertical-down relationship

The expectation from the project manager and team is that the sponsor should drive the implementation of the project and facilitate changes to the environment through supporting the change processes. The person in this role should provide leadership in the project and the business and make decisions on what is in the best interests of the organization. The sponsor should work very closely with and give direction to the project manager and team (Figure 5) and ensure the project remains on track by maintaining discipline. From the Project Team [glossary 4] point of view, the sponsor must assemble an efficient team and be involved in the guidance, support, and motivation of the team. Regular communication with the team should also take place to obtain their feedback. There are also task-related expectations of the sponsor that include prioritizing project requirements and the timely approval of changes according to the change management process. The sponsor must make decisions where they cannot be made by the team or project manager, and escalate problems that must be resolved.[11]

Figure 5 - The Vertical-Down relationship, inspired by the book Realizing Strategy through Projects: The Executive's Guide - Lechtman, 2005.

Project Sponsor, Stakeholders and Governance

Figure 6 - The Relationship between the Stakeholders and the Project, inspired by PMBOK® Guide, Fifth Edition.[1]

A stakeholder is an individual, group, or organization who may affect, be affected by, or perceive itself to be affected by a decision, activity, or outcome of a project. Stakeholders may be actively involved in the project or have interests that may be positively or negatively affected by the performance or completion of the project. [1] Project governance—the alignment of the project with stakeholders' needs or objectives—is critical to the successful management of stakeholder engagement and the achievement of organizational objectives. Project governance enables organizations to consistently manage projects and maximize the value of project outcomes and align the projects with business strategy [1]. These two provide the structure that a Project Manager and Sponsor need to address to satisfy all the requirement’s form the stakeholder.

Project Stakeholders

Stakeholders include all members of the project team as well as all interested entities that are internal or external to the organization. The project team identifies internal and external, positive and negative, and performing and advising stakeholders in order to determine the project requirements and the expectations of all parties involved. The project manager should manage the influences of these various stakeholders in relation to the project requirements to ensure a successful outcome[3]. Figure 6 illustrates the relationship between the project, the project team, and various stakeholders.

Stakeholders have different levels of responsibility and authority when contributing to a project and this change affects the course of the project's lifecycle. Identifying stakeholders, understanding their grade of impact on a project, and balancing their demands, requirements, and expectations are critical to the success of the project and failure to do so can lead to delays, cost increases, unexpected issues, and other harmful consequences including project annulment.

Just as stakeholders can positively or adversely impact a project's objectives, a project can be perceived by the stakeholders as having positive or negative results. For example, business leaders from a community who will benefit from an industrial expansion project will see positive economic benefits to the community in the form of additional jobs, supporting infrastructure, and taxes. In the case of stakeholders with positive expectations for the project, their interests are best served by making the project successful. In contrast, the interests of negatively affected stakeholders, such as nearby homeowners or small business owners who may lose property, be forced to relocate, or accept unwanted changes in the local environment, are served by impeding the project's progress. Overlooking negative stakeholder interests can result in an increased likelihood of failures, delays, or other negative consequences of the project.[3]

Accordingly, to the PMBOK® Guide, the following are some examples of project stakeholders:

  • Sponsor: The sponsor leads the project through the initiating processes until formally authorized, and plays a significant role in the development of the initial scope and charter.
  • Customers and users: Customers are the persons or organizations who will approve and manage the project's product, service, or result. Users are the persons or organizations who will use the project's product, service, or result. Customers and users may be internal or external to the performing organization
  • Sellers: vendors, suppliers, or contractors, are external companies that enter into a contractual agreement to provide components or services necessary for the project
  • Business partners: Business partners are external organizations that have a special relationship with the enterprise, sometimes attained through a certification process. Business partners provide specialized expertise or fill a specified role such as installation, customization, training, or support.
  • Organizational groups: Organizational groups are internal stakeholders who are affected by the activities of the project team. Examples of various business elements of an organization that may be affected by the project include marketing and sales, human resources, legal, finance, operations, manufacturing, and customer service.
  • Functional managers: Functional managers are key individuals who play a management role within an administrative or functional area of the business, such as human resources, finance, accounting, or procurement.
  • Other stakeholders: Additional stakeholders, such as procurement entities, financial institutions, government regulators, subject matter experts, consultants, and others, may have a financial interest in the project, contribute inputs to the project, or have an interest in the outcome of the project.

Project Sponsor vs Project Manager

Figure 7 Differences between Project Sponsor and Project Manager.

The relationship between the Project Sponsor and the Project Manager [glossary 5]is one of the main keys to project success. The establishment and development of the relationship start with the Sponsor, mainly because the sponsor is the more senior of the two and, essentially, it is the Sponsor who selects the Project Manager. Situational leadership is an important element in managing the relationship, along with expectations management, to ensure the building of trust and establishment of strong and collaborative working relations and open communication. The sponsor's style and approach should depend on the type of project at hand and the challenges it poses. The challenges are a factor of the project's overall complexity, including the project size, reach, value, overall importance, and risks.[8]

Beyond the “traditional” boundaries between the roles of the project manager and the sponsor, it is the sponsor who needs to initiate a change in the division of work, based on the project's state and the project manager's experience and performance. At the same time, the project manager should also keep an eye on the division of work to ensure that no gaps are created and that the sponsor provides the required support for the project. It is important to note that a gap may not even need to take place between the actual roles of the project manager and the sponsors; even a gap in the perceptions of one of the two in their counterpart's role may lead to project challenges.[8]

One of the most relevant differences between both roles is that the sponsor does not concern with the day-to-day running of the project (that is the responsibility of the project manager) and represents the 'buyer' of the project on behalf of the organization. It can be helpful to think about this in terms of the project manager working for the sponsor who is in turn working for the organization. The role of the Project Sponsor is to approve and fund the project, but not to get involved in day-to-day management or financial control. The Project Sponsor should appoint a Project Manager to take on the responsibility for delivering the project in accordance with its objectives

Discussion

In many projects, it appears that the sponsor is nowhere to be found (at times right from the start, or at some point in the project). In other situations, the project manager does not even know who the sponsor is, or what the project success criteria is. This is most often due to a misunderstanding by the project manager, and even the sponsors themselves, of what the project sponsorship role is about. Organizations are often reluctant to delegate project sponsorship and may keep it at the steering committee level. Project managers are often appointed to their role with no view of business objectives–—trying to complete the project with success criteria that are focused only on time and money. In addition, many project managers prefer that sponsors remain out of their way and do not interfere, or that the sponsor functions as a senior project manager for some project matters. Many sponsors are too busy to attend to their projects’ details, treating the projects as a hands-off mission that is in the hands of the project manager, and doing so without clarifying business objectives or properly empowering the project manager for the tasks on hand.[8]

Moreover, when looking for information about the role of the project sponsor, most of it includes lists of what the sponsor should do. However, it is hard to find information about what the sponsor needs to do to fulfill the sponsor's role effectively and to maximize the sponsor's contribution to project success. The sponsor's role is a difficult one: there are many pressures to contend with, especially at the higher levels of management and multiple priorities and causes compete for scarce organizational resources, capacity, funding, and focus. In addition, for promoting the project through these competitive conditions, the sponsor also has a day job and, possibly, other projects to support. Beyond ensuring the project's position on the organizational totem pole, the sponsor needs to be involved in the project to a sufficient extent based on the project's stakes, velocity, complexity, and the project's and project manager's changing needs.[8]

Glossary

  1. Stakeholder: A person, group or organization that has interest or concern in an organization. Stakeholders can affect or be affected by the organization's actions, objectives and policies.
  2. Project Life-Cycle: All projects can be mapped to the following simple life cycle structure: starting the project, organizing and preparing, carrying out the work, and closing the project. This is known as a four-phase life cycle and the phases are usually referred to initiation, planning, execution, and closure.
  3. Governance: refers to the set of policies, regulations, functions, processes, procedures, and responsibilities that define the establishment, management and control of projects, programmes and portfolios.
  4. Project Team: A project team is a team whose members usually belong to different groups, functions and are assigned to activities for the same project. A team can be divided into sub-teams according to need. Usually, project teams are only used for a defined period of time. They are disbanded after the project is deemed complete.
  5. Project Manager: the person in overall charge of the planning and execution of a particular project.

Annotated Bibliography

  • A Guide to the Project Management Body of Knowledge PMBOK® Guide, Fifth Edition

The PMBOK Guide is process-based, meaning it describes work as being accomplished by processes. Provides guidelines for managing individual projects and defines project management related concepts. It also describes the project management lifecycle and its related processes.

  • Tools for Complex Projects, CRC Press, 2016. Kaye Remington, Julien Pollack

This book combines the results of in-depth interviews with seventy successful leaders, a thorough review of existing sources and cogent analysis of both, to plot a successful course for the leader of complex projects.

  • Project Leadership. Briner, Wendy, Geddes, Michael, Hastings, Colin. 1996

This edition begins by explaining why the project way of working has been so widely and enthusiastically adopted and provides material on the role and key competencies of project leaders in a wide range of different organizations.

References

  1. 1.0 1.1 1.2 1.3 1.4 A Guide to the Project Management Body of Knowledge PMBOK® Guide, Fifth Edition, 2.2 Project Stakeholders and Governance
  2. KPMG New Zealand Project Management Survey 2010
  3. 3.0 3.1 3.2 3.3 A Guide to the Project Management Body of Knowledge PMBOK® Guide, Fifth Edition, 2.2.1 Project Stakeholders
  4. Project Leadership, Briner, Wendy, Geddes, Michael, Hastings, Colin. 1990
  5. Handbook of Project-based Management: Leading Strategic Change in Organizations, 1993, J. Rodney Turner
  6. In Search of Excellence in Project Management: Successful Practices in High-Performance Organizations, Harold R. Kerzner, 1998 – Page 471
  7. https://www.pmi.org/learning/library/project-sponsorship-collaborative-journey-6210. James, V. M. (2011). Project sponsorship: a collaborative journey. Paper presented at PMI® Global Congress 2011—North America, Dallas, TX. Newtown Square, PA: Project Management Institute
  8. 8.0 8.1 8.2 8.3 8.4 Project sponsorship: senior management's role in the successful outcome of projects. Paper presented at PMI® Global Congress 2015—EMEA, London, England. Newtown Square, PA: Project Management Institute
  9. https://www.pmi.org/learning/library/project-sponsorship-collaborative-journey-6210. James, V. M. (2011). Project sponsorship: a collaborative journey. Paper presented at PMI® Global Congress 2011—North America, Dallas, TX. Newtown Square, PA: Project Management Institute
  10. Tools for Complex Projects, CRC Press, 2016. Kaye Remington, Julien Pollack. Role definition, page 125
  11. 11.0 11.1 11.2 11.3 https://www.pmi.org/learning/library/exploring-role-executive-project-sponsor-8107. Labuschagne, L., Cooke-Davies, T., Crawford, L., Hobbs, J. B., & Remington, K. (2006). Exploring the role of the project sponsor. Paper presented at PMI® Global Congress 2006—North America, Seattle, WA. Newtown Square, PA: Project Management Institute.
  12. Lechtman, E. (2005). A Holistic Framework for Successfully Sponsored Projects

Personal tools
Namespaces

Variants
Actions
Navigation
Toolbox