Network Planning in Project Management
EmmaEgelund (Talk | contribs) (→CPM) |
EmmaEgelund (Talk | contribs) (→Application of Network Planning) |
||
Line 30: | Line 30: | ||
As mentioned earlier, some information is needed in order to use network theory for planning a project: | As mentioned earlier, some information is needed in order to use network theory for planning a project: | ||
+ | |||
+ | - Activity information: the project must be broken down into individual activities | ||
+ | - Precedence relationships: find immediate predecessor(s) for each activity | ||
+ | - Time information: know/estimate the duration of each activity | ||
===CPM/PERT Example=== | ===CPM/PERT Example=== |
Revision as of 20:10, 19 February 2023
Contents |
Abstract
Planning is a big part of project management, and the success of it is highly dependent on this step. The method Network planning will be used to reduce possible complexity of a project and smoothen the execution of the project planning. A project of a large scale that require coordination of multiple activities is a challenging task for a project manager. Succeeding a project is about simple forms of working and organising regardless the size of the project. The method will therefore be used as an integration approach where the different activities are separated to get an overview of the process. Understanding the dependencies of the project and setting up millstones is also ideal to motivate the employees involved in the project.
Project networking is investigating a project as sets of interconnected activities with the purpose of assisting in planning, managing, and controlling projects. This article will mainly focus on the most well know network planning techniques: the Critical path method (CPM) and the Program evaluation and review technique (PERT). CPM and PERT was developed in the 1950’s and has since that been used widely in operation research . The goal of the tool is to manage a project, meeting its deadlines with a minimum total cost. The tools will help organising the project, getting an overview of the activities and estimate the total length of the project. There can be multiple paths to the end of the project, but those tools can help the manager find the most effective one. Initially the methods will need three types of information to describe the project: activity, precedence, and time . This will be elaborated in the article followed by a description of the tool, an example of how to use the tool, other alternative planning tools and the limitations of the tool.
This article will stand out from the other network planning articles by elaborating the theory behind network/graphs and the focus on the comparison of different planning tools that are not focused on network planning specifically.
Network Theory
The first section will describe the terminology of network planning.
Graph Theory
A graph that consists of multiple nodes and arcs are considered a network. This means that a network consists of nodes that are connected through arcs. In this article the exploration of networks will be centered around project planning, which means that the nodes correspond to the events in the project. The arcs correspond to the connection between the events and can be either directed or undirected. When an arc is directed, for example for A to B, it means that the network can only go from A to B and not from B to A. An example of a network is illustrated below.
Spanning Tree
Consider a network with a number of nodes \textit{n} and no initially arcs. By adding one arc at a time between the nodes, a tree will appear. The first arc can be between any of the nodes in the network, but along the way, an arc cannot be placed if it creates a cycle. A network of nodes connected through arcs are referred to as a spanning tree. A network therefore differs between being cyclic or acyclic
CPM/PERT
The goal of this method is to find a path between the nodes from the start node to the finish nodes with the minimum amount of costs. Other than that, it is possible to estimate the amount of time that the project will take to complete. This method accounts for the fact that some of the activities may be carried out simultaneously.
The method will start by addressing when the activities can start and finish if no delays occur.
Critical Path
Application of Network Planning
As mentioned earlier, some information is needed in order to use network theory for planning a project:
- Activity information: the project must be broken down into individual activities - Precedence relationships: find immediate predecessor(s) for each activity - Time information: know/estimate the duration of each activity
CPM/PERT Example
How to use the methods
Other alternative tools
Limitations
References
1. F. S. Hillier & G. J. Lieberman. (2015). Introduction to operation research.
2. J. Geraldi, C. Thuesen, & J. Oehmen. (2017). Doing Projects - Nordic flavour to managing projects.
3. Rand, Graham K. & Tavares, Luis Valadares. (2005). Network Planning: Encyclopedia of Operations Research and Management Science.