Risk Management in Renewable Energy Projects
Line 1: | Line 1: | ||
+ | TRisk Management in Renewable Energy Projects | ||
The needed of introduce renewable energy in the grid system is a clear reality. Traditional energy sources like fossil fuels or nuclear energy carry complex risks which has been evaluated and optimized in the last decades. Meanwhile, renewable energy project outlines new risk that has to be taken into consideration. Some of these problems are not well address yet, increasing the uncertainty in some of these technologies. Wind energy is not total stable, for the discontinuity of the wind. Solar energy policies are not clear in many countries, changing continuously depending of the government. Or biomass energy, which addresses the shortage and supply chain problem. Risk is a key part of all these technologies and how to manage it is a challenge which is going to be faced for the global society in the following years. Energy Project Managers has to the responsibility of this changes in order to reach success and transform both the energy sector and the society <ref name=" Management of Portfolios "> Office of Government Commerce (2011). Management of Portfolios. TSO. 978-0-11-331294-8 </ref> <ref name=" Managing Successful Projects "> Office of Government Commerce (2009). Managing Successful Projects with PRINCE2™. TSO. 978-0-11-331059-3</ref>. | The needed of introduce renewable energy in the grid system is a clear reality. Traditional energy sources like fossil fuels or nuclear energy carry complex risks which has been evaluated and optimized in the last decades. Meanwhile, renewable energy project outlines new risk that has to be taken into consideration. Some of these problems are not well address yet, increasing the uncertainty in some of these technologies. Wind energy is not total stable, for the discontinuity of the wind. Solar energy policies are not clear in many countries, changing continuously depending of the government. Or biomass energy, which addresses the shortage and supply chain problem. Risk is a key part of all these technologies and how to manage it is a challenge which is going to be faced for the global society in the following years. Energy Project Managers has to the responsibility of this changes in order to reach success and transform both the energy sector and the society <ref name=" Management of Portfolios "> Office of Government Commerce (2011). Management of Portfolios. TSO. 978-0-11-331294-8 </ref> <ref name=" Managing Successful Projects "> Office of Government Commerce (2009). Managing Successful Projects with PRINCE2™. TSO. 978-0-11-331059-3</ref>. | ||
Line 24: | Line 25: | ||
This process has different stages for different author but it could be sum up as “loop of control2, proposed by International Project Management Journal in 1999 <ref name="PM Journal"> PMI (199). International Project Management Journal. Project Management Association Finland. Vol. 5, No.1 1999. ISSN 1455-4186 </ref>: | This process has different stages for different author but it could be sum up as “loop of control2, proposed by International Project Management Journal in 1999 <ref name="PM Journal"> PMI (199). International Project Management Journal. Project Management Association Finland. Vol. 5, No.1 1999. ISSN 1455-4186 </ref>: | ||
− | [[File: Loop_of_control.png |500px|thumb|center|Figure | + | [[File: Loop_of_control.png |500px|thumb|center|Figure 1: Loop_of_control <ref name="PM Journal"> PMI (199). International Project Management Journal. Project Management Association Finland. Vol. 5, No.1 1999. ISSN 1455-4186 </ref>]] |
Line 105: | Line 106: | ||
Finally, both risk impact and risk probability should be combined into the Risk Matrix <ref name="PMBOK"> PMI (2000). PMBOK Guide. Project Management Institute. Newton Square, Pennsylvania USA </ref>. In this case it is a standard 5x5 matrix, but it is used other types too. For example, a 3x3 matrix with the external vs immediate project risks. <ref name="Risk matrix PMI article "> Datta, S. & Mukherjee, S. K. (2001). Developing a risk management matrix for effective project planning – an empirical study. Project Management Journal, 32(2), 45–57.</ref>. It is important have a proper evaluation to get a good risk matrix in order to develop a proper Portfolio Risk Response which addressed the risks by priority and incorporates the corresponding resources and activities in the budget, schedule and portfolio management plan. <ref name="Standard Portfolio"> PMI (2008). The Standard for Portfolio Management. Project Management Institute. ISBN-13: 978-1-933890-53-1 </ref | Finally, both risk impact and risk probability should be combined into the Risk Matrix <ref name="PMBOK"> PMI (2000). PMBOK Guide. Project Management Institute. Newton Square, Pennsylvania USA </ref>. In this case it is a standard 5x5 matrix, but it is used other types too. For example, a 3x3 matrix with the external vs immediate project risks. <ref name="Risk matrix PMI article "> Datta, S. & Mukherjee, S. K. (2001). Developing a risk management matrix for effective project planning – an empirical study. Project Management Journal, 32(2), 45–57.</ref>. It is important have a proper evaluation to get a good risk matrix in order to develop a proper Portfolio Risk Response which addressed the risks by priority and incorporates the corresponding resources and activities in the budget, schedule and portfolio management plan. <ref name="Standard Portfolio"> PMI (2008). The Standard for Portfolio Management. Project Management Institute. ISBN-13: 978-1-933890-53-1 </ref | ||
− | [[File:Risk_matrix_EP.png |500px|thumb|center|Figure | + | [[File:Risk_matrix_EP.png |500px|thumb|center|Figure 2: Risk matrix]] |
== Case Analysis: Wind Energy== | == Case Analysis: Wind Energy== |
Revision as of 12:30, 11 February 2018
TRisk Management in Renewable Energy Projects The needed of introduce renewable energy in the grid system is a clear reality. Traditional energy sources like fossil fuels or nuclear energy carry complex risks which has been evaluated and optimized in the last decades. Meanwhile, renewable energy project outlines new risk that has to be taken into consideration. Some of these problems are not well address yet, increasing the uncertainty in some of these technologies. Wind energy is not total stable, for the discontinuity of the wind. Solar energy policies are not clear in many countries, changing continuously depending of the government. Or biomass energy, which addresses the shortage and supply chain problem. Risk is a key part of all these technologies and how to manage it is a challenge which is going to be faced for the global society in the following years. Energy Project Managers has to the responsibility of this changes in order to reach success and transform both the energy sector and the society [1] [2].
Contents |
Introduction
Energy sector is known for being complex and uncertain [3]. Energy market is changing continuously, appearing new products, tools, processes and policies [4]. Because of this, the risk is inherent and companies must take into consideration many factor and variables to decide which projects they are going to invest. Especially important is risk management in renewable energy projects where the horizon is larger and the amortization of the projects is a key factor [5]. In this article is discussed different attributes which have in common the different energetical technologies and the specific characteristics in the risk management of them.
Traditionally, fuel and nuclear industry has been the areas which higher risk. Fuel industry outline the exploration problem. Oil wells are not exactly localized and thousands of miles of dollars are spending every year to find new wells. The prospecting stages included desk-top studies, geological mapping, geochemical surveys, geophysical surveys and multi-client seismic surveys [6]; all of them without knowing if it will we find a well at the end. The financial risk is high, being the main reason why oil company agree venture to share the risk and the benefits. According to Deloitte [7], about a third of global oil and gas companies are at risk of insolvency. Bad decisions about how manage these risks has been fatal for companies like Canadian-listed Pacific Exploration & Production with $5.3 billion in debt in 2016 [8]. Another risk related to this resource are environmental, an example is the great disaster which happened in Spain in 2002 with Prestige sinking, with 11,000 tonnes of toxic fuel oil [9].
Nuclear technology has also numerous risk factors. Risk management in nuclear energy is different than risk management in fuel energy; in this case it is more important prevent from any fail than budget; due to the catastrophic consequences of an accident [10]. The two main risks are human health and policies. Nuclear energy is potentially dangerous. An accident could cause human loses, environmental catastrophes, inter alia. To avoid this the power stations has a strong security system which a lot of redundancy system and there are specific software packages who optimize the probability of accident. A nuclear accident is almost impossible that happen but the consequences would be terrible if it is not mitigated fast enough. Political risk is liked directly with the previous one. Because of its potential effects, public opinion does not feel comfortable with this type of power stations, tending to make a social amplification of the risk [11] [10]. As result, some governments have decided to close them; an example is Spanish nuclear park, which is being closed after a strong public opinion opposition [12].
Although non-renewable energy sources are an inherent risk source and should be managed carefully, this article is going to be focus on the renewable energy projects. Firstly, main considerations are addressed and risk analysis is presented. After that, different type of risks and risk sources are explained, stressing the evaluation and the response in order to mitigate them. In the following sections this article proposes a risk evaluation of a specific case. Finally, it is addressed how all these risks are going to affect renewable industry in the next years is discussed.
Risk Management: Main consideration
Energy sector is rule for the premise: safe and sustainable production. To archive this goal renewable energy is fundamental because it reduce both environmental and human risks and CO2 emissions. New renewable technologies are a true reality in some countries, that are strongly boosting for them. European Union is the area where is more developed; with counties like Denmark, that has planned a 70% of renewable market share and to be the first country with a zero CO2 emissions capital in 2025 [13]. Other regions along the work are working hard in this direction like China or South America, having huge investment in renewable energy. Risk associated to these technologies are by far lower than risk in non-renewable projects. To keep on developing a sustainable industry, countries must include them in their policies. On the other hand, does it not have to be forgotten that renewable projects have also risk and manager should know how to face it. In the following section the potential risk is presented and evaluated. Some of these risks have similar mitigations process than a traditional industry, but others should be faced with other perspective and proper actions should be taken. For instance, ethical problem of growing biomass to produce energy instead of growing food for people, when there are millions of people dying of hunger along the planet. “Project risk is an uncertain event or condition that, if it occurs, has a positive or negative effect on the project objective”. To reach mitigation of the risks, some stages are outlined [14]:
- Planning: in this first stage the activities of the project are decided by the Project Manager.
- Identification: risk that could affect the project are addressed. It is important consider them all because if they are not considered, it will not be further analysis of them.
- Qualitative Analysis: analysing the different risk to prioritize them depending on their effects in the project.
- Quantitative Analysis: analysing the consequences vs the probabilities. This point is further explained in evaluation of the risk
- Response Planning: manuals, procedures and techniques are set up to reduce possible threats overt the project´s goals.
- Monitoring and Control: finally, everything should be monitoring; impacts, consequences, mitigations, procedures and so on. This activity let the Project Manager take actions in the project risk, reducing impacts and consequences and improving mitigation actions.
This process has different stages for different author but it could be sum up as “loop of control2, proposed by International Project Management Journal in 1999 [15]:
Risk Management in Renewable Energy Projects
Type of risk
In renewable energy project several risks could be addressed. The most important are political and social, economic and environmental. The three of them are addressed in PMBOK guide, it is outlined that managers must understand the conditions and trend because the social-economic-environmental influences have a major effect in the project development. [4]. Each of them has a different risk level and the mitigation tools vary.
- Political and social: society opinion could be determinant to decide in which technology invest. Generally, policies are linked with social tendencies. If a project is not accepted by the citizens, government could publish a law to set barrier to that technology facilitating the implementation of other. For instance, the USA elections in 2016 which faced Donald Trump, supported of oil and gas technologies and do not caring about climate change and Hillary Clinton, supported of renewable policies; Trump´s victory has brought a reduction in renewable projects in this country and companies has gone to invest in others [16].
- Economy and market: fifty years ago, renewable energies were not viable but the technological improvements in the last decades has become them viable or potentially viable. There are still some barriers which difficulties their entrance in the energy market. Economically there are mainly two barriers; high discount rates which creates a long-time amortization, impossible to fulfil for technologies like some of the solar ones or the Compressed Air Energy Storage (CAES), in these cases the best option to support them is government incentives in the first stages [17]. The second one is the high cost of the technologies due to they used to be new and firms have to buy or produce patents; a cost-reducing solution used to be the way to face this restriction. In the market barrier renewable projects have to face a restricted access to technology, for being not available or available at high cost because other companies have the patents stages [17]. This is the main reason why companies and government in this sector invest huge amount of money in R&D. Finally, the control of the energy sector. Energy is a key resource and governments and companies have a strong control over the pool. The entrance of new companies with news products probably is one of the worst attributes of the energy market, being not viable investment in some technologies. An example is the wind energy, windmills started to be highly used when governments and companies start to invest, reducing the cost, creating new power stations and introducing new policies.
- Environmental: it is highly discussed in the academic field if renewable energy is as good as used to say. Some author outline that they are completely clean because they used resources that are infinite so they will never run out of energy source; wind in wind energy or sun energy in solar energy are some examples. On the other hand, there are author that question this statement. In order to produce electric energy with these technologies are necessary other materials, like rare earths, that are extremely scarce. The use of these technologies could be limited not for the energy resource, as happen in non-renewable energies, but the materials needed to produce windmills and solar panels.
Evaluation of the risk
There are differences indicator to measure the risk. Project Manager should evaluate them to obtain the risk impact and the risk likelihood. [18]
- Safety: generally, renewable energy projects are safer than non-renewable energy projects, wind farms or solar vs nuclear or coal power stations. For this reason, safety is not considering a key aspect in the evaluation of the risk in renewable energy projects.
- Environmental impact: this point is one of the most favourable for renewable energy projects. The CO2 emissions are quite low in the production stage, which is normally the most evaluated, placing this type of projects as an optimal decision for the zero emission objectives of many companies. Some examples of energy firms who has included renewable energy projects as its core business are Ørsted [19]; Acciona [20] or Iberdrola S.A [21].
- Cost: thought the years this variable has been improving in renewable energy projects. In the first stages of the technology development cost was the main reason to choose non-renewable energy project over renewable energy project. Develop, construction and financing were extremely high and these projects were only possible with governments incentives and aids. These situations have improved and it is easier finance Energy Project Management. Wind energy is an example of this improvement.
- Schedule: this point is highly relevant in the Project Management task has it is indicated in Management of Portfolios. Activities should be correctly planned taken into consideration all the stakeholder [1]. Renewable energy projects used to Long-term horizon, being especially sensitive for this point. A mediocre schedule could be fatal for projects like biomass or hydraulic power stations.
Project Manager is responsible of study these risks and reach to conclusions. After analysing all of them is should be done a Risk Matrix to evaluate which of them are the most and the less important. This matrix has two axes; risk impact risk in the x-axis and risk likelihood in the y-axis. This is the analysis of both of them:
- Risk probability: some risks are more likely to happen than others; this is reflected in the following table where likelihood are assigned to each category. A five-point scale, going from one, when incident is not planned to happen, to five, when it is known that that consequence is going to happen.
Scale | Category | Risk definition | Likelihood (%) |
---|---|---|---|
5 | Certain | Incident is going to happen | 100 |
4 | Likely | There are high expectances that incident will happen | 70 |
3 | Possible | Incident could happen, but it is not highly likely | 15 |
2 | Unlikely | Incident could happen, but it is highly unlikely | 5 |
1 | Rare | Incident is not planned | 1 |
- Risk Impact: the consequences of the risks vary. Some of them could be extremely harmful and others could be do not be important. In the following table is proposed a five-point scale, typically used in these types of projects. The scales go from one, which represent a trivial risk that is almost not harmful, to five, which represent a severe risk that is extremely dangerous.
Consequence | Scale |
---|---|
Severe | 5 |
Major | 4 |
Moderate | 3 |
Minor | 2 |
Trivial | 1 |
Finally, both risk impact and risk probability should be combined into the Risk Matrix [14]. In this case it is a standard 5x5 matrix, but it is used other types too. For example, a 3x3 matrix with the external vs immediate project risks. [22]. It is important have a proper evaluation to get a good risk matrix in order to develop a proper Portfolio Risk Response which addressed the risks by priority and incorporates the corresponding resources and activities in the budget, schedule and portfolio management plan. [23]