Simon's four levels of control

From apppm
(Difference between revisions)
Jump to: navigation, search
 
(11 intermediate revisions by 2 users not shown)
Line 1: Line 1:
 +
''*Disclaimer: The articles are created by DTU students. As part of the course, students are introduced to knowledge related to IP rights, plagiarism and copyright infringement. Additionally, the articles are a product of critical engagement of students with the literature review, and their aim is to contribute to the Project Management holistic field of science. If you discover any potential copyright infringement on the site, please inform thereof by sending an email to ophavsret@dtu.dk.''
 +
 +
 +
''Developed by Javier Gumà''
 +
 +
 
<div style="text-align: justify;">
 
<div style="text-align: justify;">
 
==Abstract==
 
==Abstract==
  
The Levers of Control (hereby LOC) Framework is firstly introduced as a Managemment Control Systems tool in Simons' "Levers of Control: How managers use innovative control systems to drive strategic renewal" (1995). The LOC framework is constituted by four blocks: Belief systems and Interactive Control systems creating positive forces, and Boundary Control Systems and Diagnostic Control Systems creating negative forces. It must be noted that positive/negative forces are not considered as good/bad forces but as different types of forces that must be balanced to achieve proper business strategy. The concept of balance or dynamic tension is central to the proper use of the tool as the later publications took effort on demonstrating (Anne- Marie Kruisa, 2015). Despite the fact that his theory about opposing forces, the number of citations (over 3000 in Google Scholar) gives Simons'  LOC framework a consolidated position within Management Control Systems literature. This article intends to give a theoretical basic description of the LOC framework presenting the different blocks of the framework and then to clarify the concept of what Simons understands as '''balance''' between innovation and creativity coming from the enablement of the employees, and the the control and set of boundaries that have to be implemented by managers, based on litterature.Then, since the LOC is traditionally a business management tool, a relation with Control Systems in Project Management is proposed taking into account the tool's limitations.
+
The Levers of Control (hereby LOC) Framework is firstly introduced as a Management Control Systems tool in Simons' "Levers of Control: How managers use innovative control systems to drive strategic renewal" (1995)<ref name="Simons">Simons, R. ''Levers of Control: How Managers Use Innovative Control Systems to Drive Strategic Renewal''. Boston: Harvard Business School Press, 1995.</ref>. The LOC framework is constituted by four blocks: Belief systems and Interactive Control systems creating positive forces, and Boundary Control Systems and Diagnostic Control Systems creating negative forces. It must be noted that positive/negative forces are not considered as good/bad forces but as diverse types of forces that must be balanced to achieve proper business strategy. The concept of balance or dynamic tension is central to the proper use of the tool as the later publications took effort on demonstrating <ref name="Exploratory balance">Anne-Marie Kruis, Roland F. Speklé, Sally K. Widener(2015). ''The Levers of Control Framework: An exploratory analysis of balance''. Management Accounting Research 32(2016) 27-44</ref>. Even though his theory about opposing forces, the number of citations (over 3000 in Google Scholar) gives Simons'  LOC framework a consolidated position within Management Control Systems literature. This article intends to give a theoretical basic description of the LOC framework presenting the different blocks of the framework and then to clarify the concept of what Simons understands as '''balance''' between innovation and creativity coming from the enablement of the employees, and the control and set of boundaries that have to be implemented by managers, based on literature.Then, since the LOC is traditionally a business management tool, a relation with Control Systems in Project Management is proposed taking into account the tool's limitations.
 +
 
 +
 
  
  
 
==The Levels Of Control Framework==
 
==The Levels Of Control Framework==
  
As previously mentionned, the LOC is an analytic tool serving to assess the different functions of Management Conctrol Systems (MCS) within a company or a team. MCS has two main functions: 1) '''controlling''' linked with predictability, efficiency and formalitty, and 2)'''enabling''' linked with innovation, spontaneity and transparency. Simon distinguishes two different blocks for each one of MCS' functions.  
+
As previously mentioned, the LOC is an analytic tool serving to assess the distinct functions of Management Control Systems (MCS) within a company or a team. MCS has two main functions: 1) '''controlling''' linked with predictability, efficiency and formality, and 2) '''enabling''' linked with innovation, spontaneity and transparency. Simons distinguishes two different blocks for each one of MCS' functions.  
  
 
[[File:LOC.PNG|thumb|upright=2.0|Simons Levers Of Control Framework]]
 
[[File:LOC.PNG|thumb|upright=2.0|Simons Levers Of Control Framework]]
  
 
===Beliefs Systems===
 
===Beliefs Systems===
The first one of the four blocks is '''Beliefs Systems''', and it is associated to the '''core values''' of a company. Such core values are usually stated by the mission and the vision of an enterprise, and set the purpose and the direction in which the objectives should be pointed. Simons himself defines the '''beliefs''' as "the explicit set of organizational definitions that senior managers communicate formally and reinforce systematically to provide basic values, purpose and direction for the organization." (Simons 1995) In other words: they create '''positive forces''' that inspire.
+
The first one of the four blocks is '''Beliefs Systems''', and it is associated to the '''core values''' of a company. Such core values are usually stated by the mission and the vision of an enterprise, and set the purpose and the direction in which the objectives should be pointed. Simons himself defines the '''beliefs''' as "the explicit set of organizational definitions that senior managers communicate formally and reinforce systematically to provide basic values, purpose and direction for the organization." <ref name="Simons">Simons, R. ''Levers of Control: How Managers Use Innovative Control Systems to Drive Strategic Renewal''. Boston: Harvard Business School Press, 1995.</ref>. In other words: they create '''positive forces''' that inspire.
  
 
===Boundary Systems===
 
===Boundary Systems===
 
On the other hand, '''Boundary Systems''' embody the limitations and constraints within which lower-level employees creativity is to be contained. '''Boundary Systems''' can be associated with codes of conduct, risks to be avoided or operational guidelines. Simons describes them as "formally stated rules, limits and proscriptions tied to defined sanctions and credible threat of punishment… to allow individual
 
On the other hand, '''Boundary Systems''' embody the limitations and constraints within which lower-level employees creativity is to be contained. '''Boundary Systems''' can be associated with codes of conduct, risks to be avoided or operational guidelines. Simons describes them as "formally stated rules, limits and proscriptions tied to defined sanctions and credible threat of punishment… to allow individual
creativity within defined limits of freedom." (Simons 1995) Therefore, '''Boundary Systems''' create negative forces that constraint individuals' imagination.
+
creativity within defined limits of freedom." <ref name="Simons">Simons, R. ''Levers of Control: How Managers Use Innovative Control Systems to Drive Strategic Renewal''. Boston: Harvard Business School Press, 1995.</ref>. Therefore, '''Boundary Systems''' create negative forces that constraint individuals' imagination.
  
 
===Diagnostic Control Systems===
 
===Diagnostic Control Systems===
Another one of the blocks of the LOC framework is '''Diagnostic Control Systems''' they are used to monitor specific critical indicators in relation to performance and objectives therefore using them to compare performance to expectations. They allow managers to follow-up operations remotely, while focusing on predicting uncertainties and strategy modifications. According to Simons they are "the formal information systems that managers use to monitor organizational outcomes and correct deviations from preset standards of performance." Consequently, they are seen as '''negative forces'''.Examples of these control systems could be budgets, KPI scorecards, project monitoring systms, etc...
+
Another one of the blocks of the LOC framework is '''Diagnostic Control Systems''' they are used to monitor specific critical indicators in relation to performance and objectives therefore using them to compare performance to expectations. They allow managers to follow-up operations remotely, while focusing on predicting uncertainties and strategy modifications. According to Simons they are "the formal information systems that managers use to monitor organizational outcomes and correct deviations from preset standards of performance." Consequently, they are seen as '''negative forces'''. Examples of these control systems could be budgets, KPI scorecards, project monitoring systems, etc...
  
 
===Interactive Control Systems===
 
===Interactive Control Systems===
The fourth block of the LOC framework is '''Interactive control Systems'''. They allow the flow of innovative ideas to flow bottom-up from lower ranks motivating them to think creatively creating '''positive forces'''. According to Simons they are the "formal information systems managers use to involve themselves regularly and personally in the decision activities of subordinates." (Simons 1995) Also, Simons argues that these control systems should generate data that should be regularly discussed to generate learning and stimulation (Simons 1999). Therefore, and in opposition with '''Diagnostic Control Systems''', '''Interactive Control Systems''' require much higher managerial implication.They can take the form of budgeting systems, balanced scorecards and project monitoring systems. The difference between '''diagnostic control systems''' and '''interactive control systems''' resides more on the way managers use them to interact with employees rather than on their techinal design.  
+
The fourth block of the LOC framework is '''Interactive control Systems'''. They allow the flow of innovative ideas to flow bottom-up from lower ranks motivating them to think creatively creating '''positive forces'''. According to Simons they are the "formal information systems managers use to involve themselves regularly and personally in the decision activities of subordinates." <ref name="Simons">Simons, R. ''Levers of Control: How Managers Use Innovative Control Systems to Drive Strategic Renewal''. Boston: Harvard Business School Press, 1995.</ref>. Also, Simons argues that these control systems should generate data that should be regularly discussed to generate learning and stimulation. Therefore, and in opposition with '''Diagnostic Control Systems''', '''Interactive Control Systems''' require much higher managerial implication. They can take the form of budgeting systems, balanced scorecards and project monitoring systems. The difference between '''diagnostic control systems''' and '''interactive control systems''' resides more on the way managers use them to interact with employees rather than on their technical design.  
  
 
==The concept of Balance or Dynamic Tensions==
 
==The concept of Balance or Dynamic Tensions==
  
The LOC framework's strength as a tool resides in balancing the tensions between positive empowering forces and negative constraints. Litterature is rather vague in describing how to achieve balance and some authors even propose that different systems and different environments can lead to different balance situations according to their approach to strategy<ref name="Exploratory balance">Anne-Marie Kruis, Roland F. Speklé, Sally K. Widener(2015). ''The Levers of Control Framework: An exploratory analysis of balance''. Management Accounting Research 32(2016) 27-44</ref>. For instance, a small system in an entrepreneurial environment where the focus is on identifying emerging opportunities can achieve balance more easily emphasizing in interactive control systems, therefore adressing strategy as a pattern. Instead, a big system in a corporate environment concerned about strategy as a plan, is more likely to achieve balance emphasizing in boundary control systems to monitor performance. Some even state<ref name="Henri">Henri, J.F., 2006. ''Management control systems and strategy: a resource-based perspective''. Account. Organ. Soc. 31, 529–558.</ref> that different states of balance between interactive control systems and diagnostic control systems can be used for different purposes.  
+
The LOC framework's strength as a tool resides in balancing the tensions between positive empowering forces and negative constraints. Literature is rather vague in describing how to achieve balance and some authors even propose that different systems and different environments can lead to different balance situations according to their approach to strategy<ref name="Exploratory balance">Anne-Marie Kruis, Roland F. Speklé, Sally K. Widener(2015). ''The Levers of Control Framework: An exploratory analysis of balance''. Management Accounting Research 32(2016) 27-44</ref>. For instance, a small system in an entrepreneurial environment where the focus is on identifying emerging opportunities can achieve balance more easily emphasizing in interactive control systems, therefore addressing strategy as a pattern. Instead, a big system in a corporate environment concerned about strategy as a plan, is more likely to achieve balance emphasizing in boundary control systems to monitor performance. Some even state<ref name="Henri">Henri, J.F., 2006. ''Management control systems and strategy: a resource-based perspective''. Account. Organ. Soc. 31, 529–558.</ref> that different states of balance between interactive control systems and diagnostic control systems can be used for different purposes.  
Simons' idea of balance has some similarities with a stream of organizational research holding that firms have to be "ambidextrous" with exploration to and explotation to control respectively strategic renewal and innovation, and predictable goal achievement. Within this stream of research, some argue that success requires control simultaniously pursuing exploration and explotation with equal weights<ref name="Cao">Cao, Q., Gedajlovic, E., Zhang, H., 2009. ''Unpacking organizational ambidexterity:dimensions, contingencies, and synergistic effects''. Organ. Sci. 20, 781–796.</ref>. Others propose that ambidexterity can be achieved alternating exploration and explotation phases over time <ref name="Gupta">Gupta, A.K., Smith, K.G., Shalley, C.E., 2006. ''The interplay between exploration andexploitation''. Acad. Manage. J. 49, 693–706.</ref>.
+
Simons' idea of balance has some similarities with a stream of organizational research holding that firms have to be "ambidextrous" with exploration to and exploitation to control respectively strategic renewal and innovation, and predictable goal achievement. Within this stream of research, some argue that success requires control simultaneously pursuing exploration and explotation with equal weights<ref name="Cao">Cao, Q., Gedajlovic, E., Zhang, H., 2009. ''Unpacking organizational ambidexterity:dimensions, contingencies, and synergistic effects''. Organ. Sci. 20, 781–796.</ref>. Others propose that ambidexterity can be achieved alternating exploration and exploitation phases over time <ref name="Gupta">Gupta, A.K., Smith, K.G., Shalley, C.E., 2006. ''The interplay between exploration and exploitation''. Acad. Manage. J. 49, 693–706.</ref>.
 +
 
  
==The Levers of Control Framework in Project, Programme and Portfolio Management==
 
===The Four levers in Project Management===
 
According to the Project Management Institute, "projects and programs are undertaken to achieve business strategy outcomes, for which many organizations now adopt formal organizational governance.[...] Because the project success may be judged on how well the resultant product or service supports organizational governance, it is important for the project manager to be knowledgeable about corporate/organizational governance policies and procedures pertaining to the subject matter of the product or service..." (PMBOK 5th edition) It can be deduced from such statement that the applicability of the LOC framework in a Project Management context seems pertinent. Still, some nuances have to be made since the elements forming the different blocks might differ because of a higher importanceof stakeholders' and sponsors' influence in Project Management in comparison to Business Management.
 
  
 
==Dynamic Tensions in Project Management and Project Life Cycle==
 
==Dynamic Tensions in Project Management and Project Life Cycle==
 +
===The Four levers in Project Management===
 +
According to the Project Management Institute, "projects and programs are undertaken to achieve business strategy outcomes, for which many organizations now adopt formal organizational governance.[...] Because the project success may be judged on how well the resultant product or service supports organizational governance, it is important for the project manager to be knowledgeable about corporate/organizational governance policies and procedures pertaining to the subject matter of the product or service..."<ref name="PMBOK"></ref> It can be deduced from such statement that the applicability of the LOC framework in a Project Management context seems pertinent. Still, some nuances have to be made since the elements forming the different blocks might differ because of a higher importance of stakeholders' and sponsors' influence in Project Management in comparison to Business Management.
 
Another notable difference between LOC application in Business Management and Project Management is the fact that the optimal state of balance may shift throughout the Project Life Cycle-because of the high variance of costs and uncertainties along the way-, while it should be more stable in Business Management.  
 
Another notable difference between LOC application in Business Management and Project Management is the fact that the optimal state of balance may shift throughout the Project Life Cycle-because of the high variance of costs and uncertainties along the way-, while it should be more stable in Business Management.  
 
[[File:Risk&Costvstime.PNG|thumb|upright=2.0|Impact of Variable Based on Project Time]]
 
[[File:Risk&Costvstime.PNG|thumb|upright=2.0|Impact of Variable Based on Project Time]]
According to the Project Management Base of Knowledge (5th edition), the Project Life Cycle Phases are:
+
According to the Project Management Base of Knowledge<ref name="PMBOK"></ref>, the Project Life Cycle Phases are:
 
*Starting the project
 
*Starting the project
 
*Organizing and preparing  
 
*Organizing and preparing  
Line 44: Line 52:
 
===Dynamic tensions in starting the project phase===
 
===Dynamic tensions in starting the project phase===
  
The main activities in starting the project being the definition of the project and the authorisation of this one, logic says that balance should be acquired emphasizing in Beliefs Systems and Interactive Control Systems.(PMBOK) During the defintion project managers have to ensure the staff is acknowledging the expected outcomes and the objectives set based on them, through what could be seen as '''Interactice control systems'''. These could be considered as ''Beliefs System'' since they will set he "mission" the projects intends to fullfil. On the other hand, the acceptable risks(i.e. stringency in environmental or safety requirements, budget, etc...) and the code of conduct are to be defined in this phase and could be seen as the '''Boundary systems''' definsing the employees limitations. Since no project work is done, and the phase objectives are mostly the definition of the scope, the objectives and the boundaries in which staff will be free to operate, emphasis should be given to '''Interactive Control Systems''' to ensure that further empowerment leading to creativity will be driven in the intended direction for the project. Still the feasability of the project is to be checked in thise phase and therefore '''Diagnostic Control Systems''' must not be pushed apart.
+
The main activities in starting the project being the definition of the project and the authorization of this one, logic says that balance should be acquired emphasizing in Beliefs Systems and Interactive Control Systems.<ref name="PMBOK">''A guide to the project management body of knowledge'',5th edition,2013</ref>. During the definition project managers have to ensure the staff is acknowledging the expected outcomes and the objectives set based on them, through what could be seen as '''Interactive control systems'''. These could be considered as ''Beliefs System'' since they will set he "mission" the projects intends to fulfill. On the other hand, the acceptable risks(i.e. stringency in environmental or safety requirements, budget, etc...) and the code of conduct are to be defined in this phase and could be seen as the '''Boundary systems''' defining the employees limitations. Since no project work is done, and the phase objectives are mostly the definition of the scope, the objectives and the boundaries in which staff will be free to operate, emphasis should be given to '''Interactive Control Systems''' to ensure that further empowerment leading to creativity will be driven in the intended direction for the project. Still the feasibility of the project is to be checked in this phase and therefore '''Diagnostic Control Systems''' must not be pushed apart.
  
 
===Dynamic tensions in organizing and preparing===
 
===Dynamic tensions in organizing and preparing===
  
Within this phase, the project documents that will be used are developed defining the deliverables that will have to be made in the following phases, building up the '''Boundary Systems''' and further defining the indicators that will serve for '''Diagnostic Control Systems'''.
+
Within this phase, the project documents that will be used are developed defining the deliverables that will have to be made in the following phases, building up the '''Boundary Systems''' and further defining the indicators that will serve for '''Diagnostic Control Systems'''. Therefore despite the balance might still be emphasizing in empowering, it is more likely to progressively move into more negative forces defining the expected performance in time and objective terms. '''Boundary Systems''' have to be properly communicated to employees by the end of this phase since the cost of making changes in the following phases is severely increased.
 +
 
 +
===Dynamic tensions in carrying out the project work===
 +
 
 +
Design and execution are done within these phase, therefore the importance of '''Diagnostic control systems''' is increased to ensure performance and predictable goals. Regarding '''Beliefs''' and '''Boundary Systems''', they should be defined and understood by the time the organization arrives to this phase. Since change costs at this point tend to be elevated '''Interactive Control Systems''' should be used to suggest changes. The amount of importance provided to '''Interactive Control Systems''' at this phase depends on the type of project. It must be noted that ''carrying out the project work'' appears to be the most sensitive phase in terms of finding the right balance between dynamic tensions, due to the existence of a loop formed between planning, executing and monitoring and controlling processes.
 +
 
 +
===Dynamic tensions in closing the project===
 +
 
 +
Given that the tasks in this phase are related to reporting and delivering, and thus not much innovation or creativity are required, the balance in this case should be inclined into '''Diagnostic Control Systems''' and '''Boundary Systems'''.
 +
 
 +
==Limitations==
 +
 
 +
As previously mentioned, Simons' levers of control despite being an impactful theory in Management Control Systems and Business Management, is also criticized for being ambiguous, ill-defined, or vaguely defined in some of its concepts. Some authors have tried to discuss such ambiguities.<ref name="ambig">Sophie Tessiera, David Otleyb, 2012. ''A conceptual development of Simons’ Levers of Control framework''. Management Accounting Research 23 (2012) 171– 185</ref>. The claim in that regard is that vague of definition of the concepts leads to mixed empirical results that impede the bulding of a unified body of knowledge. A clear example is the definition of the balance, where infinite possibilities exist depending on each case. Despite the fact that some progress has been made, Kruis, Speklé and Widener <ref name="Exploratory balance"></ref> for example gathered empirical data about 217 managers belonging to different companies, considered as successful, in different environments. Such data helped making a series of case studies that allowed them to propose a series of balance scenarios linked to the companies industries.
 +
So far no literature exists on the use of the LOC framework in a Project Management context, but the limitations are evident aswell since different optimal balance scenarios can be seen through the different phases of a single project.
 +
 
 +
==Conclusion==
 +
 
 +
This article has presented a description of Simons' Levers of Control framework based the existing literature in Business Management. It has been described that the framework is formed of four building blocks two of them creating positive forces that are meant to enable employees, and two of them creating negative forces that are meant to constrain them. It has also been explained the concept that balance between these positive and negative forces leads to successful business management according to Simons theory. Once LOC's blocks were defined and the dynamic tensions have been explained, a proposition on how could that theory be applied to project management was made. It was stressed that successful balance situations may evolve and change throughout the project life cycle. Finally a statement was made on the limitations expressed in literature about the tool and its ambiguities.
  
 
==Annotated Bibliography==
 
==Annotated Bibliography==
 +
1. '''Levers of Control: How Managers Use Innovative Control Systems to Drive Strategic Renewal''': is the book in which Simons fully presented his theory about the four levers of control and presents not only the levers themselves but the concept of balance that is required for successful business management.
 +
 +
2. '''The Levers of Control Framework: An exploratory analysis of balance''': this article provides an overview of the theory behind Simons' four levers of control. By defining the nature of the four levers and the reviewing the literature on the concept of balance, the article sets the bases to their further intent of making an empirical study of how different organizations found a proper balance scenario.
 +
 +
3.''' Management control systems and strategy: a resource-based perspective''': the article presents the use of diagnostic control systems and interactive control systems in a business management resource-based context, and argues about different possible combinations of their usage and their effect on dynamic tensions.
 +
 +
4.'''Unpacking organizational ambidexterity: dimensions, contingencies, and synergistic effects''': studies the concept of ambidexterity in combining exploratory and exploitative activities. The article further concludes about the benefits of managing the trade-offs of both types of actions.
 +
 +
6.'''A guide to the project management body of knowledge''': constitutes a common base of knowledge on project management theory and experiences. The guide is used in the article to find scenarios, cases and similarities in Project Management with Business Management, in terms of Managing control Systems, that could benefit from the use of the LOC framework.
 +
 +
7.''' A conceptual development of Simons’ Levers of Control framework.''': reviews the literature on the LOC, and studies the ambiguities and vague definitions with the intent of shedding some light on it.
 +
 +
 
==References==
 
==References==
  <references/>
+
   
 +
<references/>
 +
 
 +
[[Category:Project Management]][[Category:Actions]][[Category:Complexity]][[Category:Control]][[Category:Tool]]

Latest revision as of 10:30, 17 May 2019

*Disclaimer: The articles are created by DTU students. As part of the course, students are introduced to knowledge related to IP rights, plagiarism and copyright infringement. Additionally, the articles are a product of critical engagement of students with the literature review, and their aim is to contribute to the Project Management holistic field of science. If you discover any potential copyright infringement on the site, please inform thereof by sending an email to ophavsret@dtu.dk.


Developed by Javier Gumà


Contents

[edit] Abstract

The Levers of Control (hereby LOC) Framework is firstly introduced as a Management Control Systems tool in Simons' "Levers of Control: How managers use innovative control systems to drive strategic renewal" (1995)[1]. The LOC framework is constituted by four blocks: Belief systems and Interactive Control systems creating positive forces, and Boundary Control Systems and Diagnostic Control Systems creating negative forces. It must be noted that positive/negative forces are not considered as good/bad forces but as diverse types of forces that must be balanced to achieve proper business strategy. The concept of balance or dynamic tension is central to the proper use of the tool as the later publications took effort on demonstrating [2]. Even though his theory about opposing forces, the number of citations (over 3000 in Google Scholar) gives Simons' LOC framework a consolidated position within Management Control Systems literature. This article intends to give a theoretical basic description of the LOC framework presenting the different blocks of the framework and then to clarify the concept of what Simons understands as balance between innovation and creativity coming from the enablement of the employees, and the control and set of boundaries that have to be implemented by managers, based on literature.Then, since the LOC is traditionally a business management tool, a relation with Control Systems in Project Management is proposed taking into account the tool's limitations.



[edit] The Levels Of Control Framework

As previously mentioned, the LOC is an analytic tool serving to assess the distinct functions of Management Control Systems (MCS) within a company or a team. MCS has two main functions: 1) controlling linked with predictability, efficiency and formality, and 2) enabling linked with innovation, spontaneity and transparency. Simons distinguishes two different blocks for each one of MCS' functions.

Simons Levers Of Control Framework

[edit] Beliefs Systems

The first one of the four blocks is Beliefs Systems, and it is associated to the core values of a company. Such core values are usually stated by the mission and the vision of an enterprise, and set the purpose and the direction in which the objectives should be pointed. Simons himself defines the beliefs as "the explicit set of organizational definitions that senior managers communicate formally and reinforce systematically to provide basic values, purpose and direction for the organization." [1]. In other words: they create positive forces that inspire.

[edit] Boundary Systems

On the other hand, Boundary Systems embody the limitations and constraints within which lower-level employees creativity is to be contained. Boundary Systems can be associated with codes of conduct, risks to be avoided or operational guidelines. Simons describes them as "formally stated rules, limits and proscriptions tied to defined sanctions and credible threat of punishment… to allow individual creativity within defined limits of freedom." [1]. Therefore, Boundary Systems create negative forces that constraint individuals' imagination.

[edit] Diagnostic Control Systems

Another one of the blocks of the LOC framework is Diagnostic Control Systems they are used to monitor specific critical indicators in relation to performance and objectives therefore using them to compare performance to expectations. They allow managers to follow-up operations remotely, while focusing on predicting uncertainties and strategy modifications. According to Simons they are "the formal information systems that managers use to monitor organizational outcomes and correct deviations from preset standards of performance." Consequently, they are seen as negative forces. Examples of these control systems could be budgets, KPI scorecards, project monitoring systems, etc...

[edit] Interactive Control Systems

The fourth block of the LOC framework is Interactive control Systems. They allow the flow of innovative ideas to flow bottom-up from lower ranks motivating them to think creatively creating positive forces. According to Simons they are the "formal information systems managers use to involve themselves regularly and personally in the decision activities of subordinates." [1]. Also, Simons argues that these control systems should generate data that should be regularly discussed to generate learning and stimulation. Therefore, and in opposition with Diagnostic Control Systems, Interactive Control Systems require much higher managerial implication. They can take the form of budgeting systems, balanced scorecards and project monitoring systems. The difference between diagnostic control systems and interactive control systems resides more on the way managers use them to interact with employees rather than on their technical design.

[edit] The concept of Balance or Dynamic Tensions

The LOC framework's strength as a tool resides in balancing the tensions between positive empowering forces and negative constraints. Literature is rather vague in describing how to achieve balance and some authors even propose that different systems and different environments can lead to different balance situations according to their approach to strategy[2]. For instance, a small system in an entrepreneurial environment where the focus is on identifying emerging opportunities can achieve balance more easily emphasizing in interactive control systems, therefore addressing strategy as a pattern. Instead, a big system in a corporate environment concerned about strategy as a plan, is more likely to achieve balance emphasizing in boundary control systems to monitor performance. Some even state[3] that different states of balance between interactive control systems and diagnostic control systems can be used for different purposes. Simons' idea of balance has some similarities with a stream of organizational research holding that firms have to be "ambidextrous" with exploration to and exploitation to control respectively strategic renewal and innovation, and predictable goal achievement. Within this stream of research, some argue that success requires control simultaneously pursuing exploration and explotation with equal weights[4]. Others propose that ambidexterity can be achieved alternating exploration and exploitation phases over time [5].


[edit] Dynamic Tensions in Project Management and Project Life Cycle

[edit] The Four levers in Project Management

According to the Project Management Institute, "projects and programs are undertaken to achieve business strategy outcomes, for which many organizations now adopt formal organizational governance.[...] Because the project success may be judged on how well the resultant product or service supports organizational governance, it is important for the project manager to be knowledgeable about corporate/organizational governance policies and procedures pertaining to the subject matter of the product or service..."[6] It can be deduced from such statement that the applicability of the LOC framework in a Project Management context seems pertinent. Still, some nuances have to be made since the elements forming the different blocks might differ because of a higher importance of stakeholders' and sponsors' influence in Project Management in comparison to Business Management. Another notable difference between LOC application in Business Management and Project Management is the fact that the optimal state of balance may shift throughout the Project Life Cycle-because of the high variance of costs and uncertainties along the way-, while it should be more stable in Business Management.

Impact of Variable Based on Project Time

According to the Project Management Base of Knowledge[6], the Project Life Cycle Phases are:

  • Starting the project
  • Organizing and preparing
  • Carrying out the project work
  • Closing the project

[edit] Dynamic tensions in starting the project phase

The main activities in starting the project being the definition of the project and the authorization of this one, logic says that balance should be acquired emphasizing in Beliefs Systems and Interactive Control Systems.[6]. During the definition project managers have to ensure the staff is acknowledging the expected outcomes and the objectives set based on them, through what could be seen as Interactive control systems. These could be considered as Beliefs System since they will set he "mission" the projects intends to fulfill. On the other hand, the acceptable risks(i.e. stringency in environmental or safety requirements, budget, etc...) and the code of conduct are to be defined in this phase and could be seen as the Boundary systems defining the employees limitations. Since no project work is done, and the phase objectives are mostly the definition of the scope, the objectives and the boundaries in which staff will be free to operate, emphasis should be given to Interactive Control Systems to ensure that further empowerment leading to creativity will be driven in the intended direction for the project. Still the feasibility of the project is to be checked in this phase and therefore Diagnostic Control Systems must not be pushed apart.

[edit] Dynamic tensions in organizing and preparing

Within this phase, the project documents that will be used are developed defining the deliverables that will have to be made in the following phases, building up the Boundary Systems and further defining the indicators that will serve for Diagnostic Control Systems. Therefore despite the balance might still be emphasizing in empowering, it is more likely to progressively move into more negative forces defining the expected performance in time and objective terms. Boundary Systems have to be properly communicated to employees by the end of this phase since the cost of making changes in the following phases is severely increased.

[edit] Dynamic tensions in carrying out the project work

Design and execution are done within these phase, therefore the importance of Diagnostic control systems is increased to ensure performance and predictable goals. Regarding Beliefs and Boundary Systems, they should be defined and understood by the time the organization arrives to this phase. Since change costs at this point tend to be elevated Interactive Control Systems should be used to suggest changes. The amount of importance provided to Interactive Control Systems at this phase depends on the type of project. It must be noted that carrying out the project work appears to be the most sensitive phase in terms of finding the right balance between dynamic tensions, due to the existence of a loop formed between planning, executing and monitoring and controlling processes.

[edit] Dynamic tensions in closing the project

Given that the tasks in this phase are related to reporting and delivering, and thus not much innovation or creativity are required, the balance in this case should be inclined into Diagnostic Control Systems and Boundary Systems.

[edit] Limitations

As previously mentioned, Simons' levers of control despite being an impactful theory in Management Control Systems and Business Management, is also criticized for being ambiguous, ill-defined, or vaguely defined in some of its concepts. Some authors have tried to discuss such ambiguities.[7]. The claim in that regard is that vague of definition of the concepts leads to mixed empirical results that impede the bulding of a unified body of knowledge. A clear example is the definition of the balance, where infinite possibilities exist depending on each case. Despite the fact that some progress has been made, Kruis, Speklé and Widener [2] for example gathered empirical data about 217 managers belonging to different companies, considered as successful, in different environments. Such data helped making a series of case studies that allowed them to propose a series of balance scenarios linked to the companies industries. So far no literature exists on the use of the LOC framework in a Project Management context, but the limitations are evident aswell since different optimal balance scenarios can be seen through the different phases of a single project.

[edit] Conclusion

This article has presented a description of Simons' Levers of Control framework based the existing literature in Business Management. It has been described that the framework is formed of four building blocks two of them creating positive forces that are meant to enable employees, and two of them creating negative forces that are meant to constrain them. It has also been explained the concept that balance between these positive and negative forces leads to successful business management according to Simons theory. Once LOC's blocks were defined and the dynamic tensions have been explained, a proposition on how could that theory be applied to project management was made. It was stressed that successful balance situations may evolve and change throughout the project life cycle. Finally a statement was made on the limitations expressed in literature about the tool and its ambiguities.

[edit] Annotated Bibliography

1. Levers of Control: How Managers Use Innovative Control Systems to Drive Strategic Renewal: is the book in which Simons fully presented his theory about the four levers of control and presents not only the levers themselves but the concept of balance that is required for successful business management.

2. The Levers of Control Framework: An exploratory analysis of balance: this article provides an overview of the theory behind Simons' four levers of control. By defining the nature of the four levers and the reviewing the literature on the concept of balance, the article sets the bases to their further intent of making an empirical study of how different organizations found a proper balance scenario.

3. Management control systems and strategy: a resource-based perspective: the article presents the use of diagnostic control systems and interactive control systems in a business management resource-based context, and argues about different possible combinations of their usage and their effect on dynamic tensions.

4.Unpacking organizational ambidexterity: dimensions, contingencies, and synergistic effects: studies the concept of ambidexterity in combining exploratory and exploitative activities. The article further concludes about the benefits of managing the trade-offs of both types of actions.

6.A guide to the project management body of knowledge: constitutes a common base of knowledge on project management theory and experiences. The guide is used in the article to find scenarios, cases and similarities in Project Management with Business Management, in terms of Managing control Systems, that could benefit from the use of the LOC framework.

7. A conceptual development of Simons’ Levers of Control framework.: reviews the literature on the LOC, and studies the ambiguities and vague definitions with the intent of shedding some light on it.


[edit] References

  1. 1.0 1.1 1.2 1.3 Simons, R. Levers of Control: How Managers Use Innovative Control Systems to Drive Strategic Renewal. Boston: Harvard Business School Press, 1995.
  2. 2.0 2.1 2.2 Anne-Marie Kruis, Roland F. Speklé, Sally K. Widener(2015). The Levers of Control Framework: An exploratory analysis of balance. Management Accounting Research 32(2016) 27-44
  3. Henri, J.F., 2006. Management control systems and strategy: a resource-based perspective. Account. Organ. Soc. 31, 529–558.
  4. Cao, Q., Gedajlovic, E., Zhang, H., 2009. Unpacking organizational ambidexterity:dimensions, contingencies, and synergistic effects. Organ. Sci. 20, 781–796.
  5. Gupta, A.K., Smith, K.G., Shalley, C.E., 2006. The interplay between exploration and exploitation. Acad. Manage. J. 49, 693–706.
  6. 6.0 6.1 6.2 A guide to the project management body of knowledge,5th edition,2013
  7. Sophie Tessiera, David Otleyb, 2012. A conceptual development of Simons’ Levers of Control framework. Management Accounting Research 23 (2012) 171– 185