Decision Tree: Risk & Opportunities
(→Method Description) |
|||
Line 8: | Line 8: | ||
== Method Description == | == Method Description == | ||
− | + | The decision tree is used to evaluate the risk and cost within a project. It can be used for feasibility studies, reassessment of existing structures or shutdown of old structures. An example to use this is: a production factory is being build but would need a source of water which could provide 100 units of water per day. They have two choices to comply | |
+ | |||
+ | <ref name="Probability" /> | ||
== Application == | == Application == |
Revision as of 09:00, 21 September 2017
Contents |
Abstract
Uncertainty is a massive issue in project management and can lead to high cost and disadvantages if not handled correctly. The project manager must therefore be able to make the best decisions based on the information available.
The decision tree is a tool that can aid the project manager to ensure the best outcome of a problem.
It is based on a tree-like model where each branch is a path of decisions and possible events. Each step include the cost and possibility of that event to occur.
By identifying all the possible events and their chance to occur it gives the project manager the ability to calculate the highest probability for each path.
When combining this with the cost of each event the project manager is able to estimate the cost/benefits for each decision.
Method Description
The decision tree is used to evaluate the risk and cost within a project. It can be used for feasibility studies, reassessment of existing structures or shutdown of old structures. An example to use this is: a production factory is being build but would need a source of water which could provide 100 units of water per day. They have two choices to comply
Application
Limitations
Alternatives
Annotated Bibliography
References